Preview

Space Constructors

Satisfactory Essays
Open Document
Open Document
570 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Space Constructors
Space Constructors Inc.
Hanchen Li
Jianyang Zhang
St. Thomas University
BUS 670 Advanced Operations Management
Dr. Paul D. Maxwell
Jan 29, 2014

1. Reduce total project duration as much as possible without unnecessary additional cost. Indicate the new critical path or paths. Show how much slack or float remain in the noncritical paths.

Below is the path without unnecessary additional cost.

Path
Original times(weeks) reduce total duration as much as possible with additional cost time(weeks)
Slack or float(weeks)
Original Cost (Dollars)
Additional total cost(Dollars)
ADG
3+5+4=12
2+3+2=7
5
5000+10000+10000=$25000
10000+18000+24000= $52000
AF
3+7=10
2+5=7
3
5000+11500= $16500
10000+17500= $27500
BG
6+4=10
4+2=6
4
14000+10000= $24000
26000+24000= $50000
CEG
2+2+4=8
1+2+2=5
3
2500+8000+10000= $20500
5000+8000+24000= $37000

From the excel, we can find that the ADG and AF are the longest path, so both are the critical paths. From the slack or float remain time, we can find how much slack or float remain in the noncritical paths.

2. Assume that the situation proves to be less urgent than it seems to Messrs Alison and Phillips. Revises the schedule in order to complete the job within ten weeks. Indicate the new cost and critical path or paths.

From the excel above, we can find that Path AF and BG is ten weeks. And the path CEG is 8 weeks. So just need to control the path ADG within 10 weeks. So activity A and D are to use original time, and D use additional cost time. SO
ADG=3+5+2=10 so cost is 5000+10000+24000=39000
If A and G to use original time, and D is to use additional cost.SO
ADG=3+3+4=10, and cost is 5000+18000+10000=33000
So the second one is a better option because it is cheaper.
ADG=10 AF=10 BG=10 CEG=8 total cost is 33000+16500+24000+20500=94000
And paths ADG AF BG are both critical paths

3. Suppose SCI were proceeding on the 10 week schedule and it became

You May Also Find These Documents Helpful

  • Good Essays

    -2- 6. The critical path of a project network is the: a. shortest time path through the network. b. path with the fewest activities. c. path with the most activities. d. longest time path throught the network.…

    • 882 Words
    • 8 Pages
    Good Essays
  • Good Essays

    RSM222 Midterm

    • 1583 Words
    • 9 Pages

    b. In some cases, under applied overhead is closed out to cost of goods sold…

    • 1583 Words
    • 9 Pages
    Good Essays
  • Satisfactory Essays

    QAT1 Task 4

    • 501 Words
    • 7 Pages

    Determine each of the following: Task Earliest Start Latest Start Earliest Finish Latest Finish Slack A 0 6.5 3 9.5 6.5 B 0 0 7 7 0 CRITICAL C 3 9.5 7.5 14 6.5 D 7 7.5 18.5 19 0.5…

    • 501 Words
    • 7 Pages
    Satisfactory Essays
  • Powerful Essays

    PROJ 586 Final Exam

    • 872 Words
    • 4 Pages

    6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time.…

    • 872 Words
    • 4 Pages
    Powerful Essays
  • Satisfactory Essays

    The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) b) Identify the critical path (6 points) c)…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Huffman Trucking Benefits

    • 278 Words
    • 2 Pages

    The Critical Path Method will indicate the longest path of planned to the end of the project. It is a very good tool to use because it will give the Project Manager a good idea of what tasks that must be completed on time in order for the project to continue smoothly. This method is commonly used in the development of new…

    • 278 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    First Cars Ltd

    • 1031 Words
    • 5 Pages

    Critical path analysis is a method that is used to plan out the many activities involved in a project to be able to find the most efficient way of complete it and how to complete it on time.…

    • 1031 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    Brs Mdm3 Tif Ch07

    • 2550 Words
    • 19 Pages

    4) Refer to the figure. What is the slack time, in days, associated with activity D?…

    • 2550 Words
    • 19 Pages
    Powerful Essays
  • Satisfactory Essays

    E (by 1 day) and B (by 1 day). The cost impact of crashing these activities is $300.…

    • 668 Words
    • 20 Pages
    Satisfactory Essays
  • Satisfactory Essays

    In 1672 The Puritans belief was very strict which made it hard on the women during that time.The roles and treatments of the women was made were they had to submissive to the men. The characters Abigail, Mary Warren, and Elizabeth was portrayed as simple-minded, controlling, weak, and submissive women.…

    • 384 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Finannce

    • 5864 Words
    • 45 Pages

    Paper costs are irrelevant because these costs will be the same with either the old printer or the new printer.…

    • 5864 Words
    • 45 Pages
    Powerful Essays
  • Satisfactory Essays

    Week 6 Discussion

    • 375 Words
    • 2 Pages

    Using the performance measures given in the problem and those you computed in (1) above, do the following:…

    • 375 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Phase 4 DB

    • 379 Words
    • 1 Page

    Critical Path Method (CPM) is yet another tool for the project manager to use to organize, plan, and control the development of a project. It calculates the longest path to get to the end of a project and tells which activities are critical. It ca be used for projects of any size and illustrates the dependencies between scheduled activities. However, it does not tell you anything about the resources or where they fit into the project.…

    • 379 Words
    • 1 Page
    Satisfactory Essays
  • Satisfactory Essays

    R.C. Coleman Case Study

    • 435 Words
    • 2 Pages

    2. To complete the expansion in 40 weeks with an 80% probability of success, the activities would need to have a completion time of 38 weeks. This is given the same variance score and times for the schedules above. However, presently it is unable to conclude five weeks earlier without an increase in funding, workers and supplies.…

    • 435 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    PROJ 586 Final Exam

    • 814 Words
    • 4 Pages

    6. (TCO C) If _____ is positive, it represents the maximum amount of time that the activities on a particular path can be delayed without jeopardizing the completion of the project by its required completion time.…

    • 814 Words
    • 4 Pages
    Good Essays

Related Topics