Preview

Strategic project management

Satisfactory Essays
Open Document
Open Document
416 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Strategic project management
Project Management C11PA
3 hours
Answer All of Section A and 2 Questions from Section B
Section A – Answer all of this section
Question 1
a) From the following logic table draw a fully analysed (AON) network diagram for the activities listed below and calculate the normal duration for this project and identify the critical path(s).
(8 marks)
Activity Dependence Normal Crash
Normal Crash
Duration Duration Cost £ Cost in days in days
£
A
3
3
3000 3000
B
A
7
3
3000 7000
C
B
4
4
4000 4000
D
C
29
9 10000 25000
E
C
6
3
3000 9000
F
G
20
10 10000 12000
G
A
18
8 20000 22000
H
F
2
1
5000 10000
I
D,G,H
2
1
4000 6000
J
I
5
5 15000 15000
K
J
1
1
1000 1000
b) Due to unexpected delays in some predecessors, this project should take no longer than
30 days. As a project manager you are requested to conduct a trade-off analysis in this pursuit. Data from the analysis must provide the following requirements:
• The most economic sequence for crashing
• The project duration and cost after each crash
• The final critical path(s)
(16 marks)
c) Draw the crash slope (crash curve), illustrating the financial consequences of each crash.
(3 marks)
(Total 27 Marks)

Question 2
a) It is important to monitor the performance of the implementation of the project once it starts. Table 2 below shows weekly performance data for engineers executing a work package to upgrade an IT system. The work has been priced on the assumption that each team will complete 25 zones per week at budgeted cost of £1000 per zone, over a 10week project period.
From the data prepare an Earned Value Analysis (EVA), to 2 decimal places, comparing weekly performance of each team. Your analysis must include brief comment on the scheduled progress and cost performance of each week
(8 marks)

Table 2: Actual weekly costs and progress report at week 4

Week Team
1
1
2
2
1
2
3
1
2
4
1
2

No of zones completed Actual weekly

You May Also Find These Documents Helpful

  • Good Essays

    Proj586 Week 4

    • 660 Words
    • 3 Pages

    The budget for the preparation phase is $1,282,442 and the duration of the preparation phase would be 47 weeks.…

    • 660 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Step 1: Construct a network diagram for the project. (NOTE: EF for activity H should be 19)…

    • 552 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Nt1310 Unit 4

    • 555 Words
    • 3 Pages

    b. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?…

    • 555 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    • The project schedule is liberal in respect to time for completion of each phase, because not keeping up with the…

    • 1244 Words
    • 5 Pages
    Powerful Essays
  • Satisfactory Essays

    Managerial Statement: The expected duration of the project is 31 working days. Critical Activities are I, J, K, L, and M.…

    • 678 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    PROJ 586 W4 Homework

    • 588 Words
    • 3 Pages

    b) Which activities should be crashed to meet a project deadline of 13 days at minimum cost? What is the cost impact of crashing these activities? [3 points]…

    • 588 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Week 3 Aib Problems

    • 895 Words
    • 4 Pages

    The most critical path is B – D – F – G – I: 32 Days…

    • 895 Words
    • 4 Pages
    Satisfactory Essays
  • Powerful Essays

    It221 Final Project

    • 2390 Words
    • 10 Pages

    Currently Cyber Solutions has satellite locations in 15 major cities around the United States that provide onsite IT solutions for companies within their service area, but do not have an integrated database that updates…

    • 2390 Words
    • 10 Pages
    Powerful Essays
  • Good Essays

    Red Zuma Project

    • 402 Words
    • 2 Pages

    5. The total duration to complete the project changed and actually increased after resource leveling and made the completion later than the original…

    • 402 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    Ibrahim Sacin

    • 657 Words
    • 3 Pages

    how long noncritical activities be delayed before they cause an increase in the project completion time? All this question answered excel page 1,2,,3,4,5,6.…

    • 657 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Apache Case Study

    • 387 Words
    • 2 Pages

    d. Cannot have time to suggest or modify the end product according to quality or client requirements…

    • 387 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    STRATEGIC MANAGEMENT PROJECT

    • 5936 Words
    • 22 Pages

    The H. J. Heinz Company, also known as the Heinz Company and commonly known as Heinz and famous for its "57 Varieties" slogan and its ketchup, is an American food processing company with world headquarters in Pittsburgh, Pennsylvania.…

    • 5936 Words
    • 22 Pages
    Powerful Essays
  • Good Essays

    Project Management

    • 10906 Words
    • 44 Pages

    Before implementing activity based costing for the entire organization, it is always a great idea to do a pilot run. The best candidate for this pilot run is the department that suffers from profit making…

    • 10906 Words
    • 44 Pages
    Good Essays
  • Powerful Essays

    PROJECT MANAGEMENT

    • 3019 Words
    • 10 Pages

    PilTel, also known as Pilipino Telephone Corporation at the 90’s or known today as the PLDT Communications and Energy Ventures, Inc. (PSE:PCEV) is a telecommunications company and was incorporated in the Philippines with limited liability on July 18, 1968 and was listed on the Philippines Stock Exchange in July 1995. Until 1991, PCEV’s sole business was providing a fixed telecommunications services to eight cities and municipalities in the Philippines. In April 2000, PCEV launched a digital prepaid cellular service, under the Talk ‘N Text brand, using the Global System for Mobile Communications (GSM) platform of Smart Communications, Inc. (SMART) (PCEV, n.d.a).…

    • 3019 Words
    • 10 Pages
    Powerful Essays
  • Satisfactory Essays

    Project Management

    • 294 Words
    • 2 Pages

    However, the company is aware from press coverage and from surveys among its own customers that there is a growing public demand to be able…

    • 294 Words
    • 2 Pages
    Satisfactory Essays