FA
02-08-14
Incorporated Comments
APJ
SKH
A
FA
26-07-14
ORIGINAL ISSUE
APJ
SKH
Rev
Status
Date
MODIFICATIONS
Estab.
Check.
Appr.
Project :
TATA Power LAB Modernización
Client : QAIT DEPARTMENT:- TATA POWER
Contractor :
Document Title :
SAT procedure for proposed LAB
Drawing number :
Original signed by
DATE
NAME
SIGN
PO Number:
Established
SCALE : /
STANDARD :
IEC
Checked
Approved
Size : A4
Revision: B
Sheet No: 1
Qty. of Sheets: 13
Table of Contents
1 Introduction 4 SAT Procedures 5
Table 1:Documents contents 4
1 Introduction
1.1 Purpose of the Document
This document describes the Site acceptance test procedure of the LAB System functionality in QAIT department for TATA Power, Trombay.
Site Acceptance Test: The Site Acceptance Test (SAT) is the final check to make sure the system installed/delivered at is operating properly.
1.2 Contents of the Document
This document describes the Site acceptance test procedure, and is composed of the following:
Chapter
Title
Contents
1
Introduction
This chapter itself.
2
Test procedure
Procedure for the Site Acceptance Test
Table 1:Documents contents
1.3 Documentation Reference
Functional requirement of the project has already been considered in the documents submitted to TATA Power during the course of the project. The Documentation mentioned under the following categories may be referred during the testing.
1.4 Definitions, Acronyms and Abbreviations
ACSI - Abstract Communication Service Interface
DR – Disturbance recorder
GOOSE - Generic Object Oriented Substation Events
HSR - High Availability Seamless Redundancy
IEC - International Electro technical Commission
IED - Intelligent Electronic Device
MMS - Manufacture's Messaging Specification
PRP