1. Base – Awarded. Jeff has been coordinating with them on design efforts.
a. Jay is doing a site visit.
b. CPS received the initial shop drawings for review. They looked good and have been approved. Jeff will send Randy, Gary, Jason and Dick the shop drawings.
c. CPS is working with Enercept to ship the panels to NY on Feb 8th, because CPS doesn’t have anyone on site in NY till then to receive the shipment.
2. Structure – Awarded. Jeff has been coordinating with them on design efforts.
a. CPS met with vendor yesterday to talk about approach for assembly with current resources at Summit. In two weeks, meeting on assembly steps.
b. CPS discussed with them the possibility of having a factory rep come to Summit …show more content…
Paint floor – NSF is wondering if the floor should be painted. CPS discussed this multiple times and decided to remove the requirement for painting the floor to make the schedule. CPS is talking to the vendor to verify schedule impacts of painting. CPS discussed bare steel that has been used in North Slope shops, which has performed well. Pat agreed with the approach and said rubber matting may be used, if required. If the vendor can make the schedule, Pat said to proceed with submitting an additional CR. If it is decided to paint the steel, send Pat an email with the cost, so he can discuss the approach with …show more content…
Discuss if CRREL heaters will be available.
1. Jason is trying to get into contact with the people at CRREL who have the heaters. He hasn’t had any luck yet. CPS is working on contingency options.
Alaska:
B. NEON –
1. Garage Updates –
a. A few punchlist items remaining – window repair, replace pressure gauge, and fine tuning of the vehicle exhaust system. JRE is planning on going up in late Jan or Feb. Jeff will coordinate this trip with JRE.
b. Drafting has been working on as-builts; they are almost complete.
c. CR for the transformer has been sent to NSF, so CPS will be able to make final payment to JRE.
d. De-obligation – Pat said that NEON is planning to take back any remaining funding. CPS will need to submit a CR for the de-obligation. Pat said that it sounds like Bio is interesting in using the funding to do additional work with CH. CPS is still finalizing costs, but will plan to have a final cost by the end of the Jan.
2. Estimate for APP5 Support – CPS is finalizing these costs. Jason has developed an initial estimate of around $7k for this work, but he is working on verifying the costs. CPS will send NSF a final cost estimate. Program:
C. Next Meeting – Next meeting is scheduled for Jan