Preview

The Case Of Millennium Erectors Corporation

Powerful Essays
Open Document
Open Document
1053 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
The Case Of Millennium Erectors Corporation
VARIATION ORDER

Changes arise for various reasons and throughout all stages of a project. To regulate changes, a project manager must be aware of the causes and plan to avoid circumstances which give rise to changes. During the conceptual and development stages, numerous changes are made in the name of design development. At these primary stages the ability to influence cost is greatest and lest control is executed, the financial ability of the owner or the economic feasibility of the project may be surpassed.

Essentially, a variation is a modification to the scope of works in a construction contract in the manner of an addition, substitution or omission from the original scope of works.

It frequently occurs that a contractor of a project
…show more content…
Variations should not be acted upon unless the change has been authorized by the recognized authority. An authorized change becomes a change order, which will affect the cost of the project.

In the case of Millennium Erectors Corporation, regarding the R Square Residences project, there have been at least four variation orders issued in the past few months by the project engineer. Two of them will be studied for the sake of this report.

The first example is the front page letter for the additive change order claim for the adjustment of the fire exit stairs from the ground floor to the ninth floor as shown in Figure 6.1. It appears that there has been at least a change in cost as according to the claim, combining in the cost for the concreting works, reinforcement bar works, and formworks, there is a total net additive cost of Php38,833.76. Attached with this claim are photos of the stairs as proofs and the photos of plan for the stairs. It can be seen in the proof photos that the stairs were lacking in concrete as the other end of the stairs have protruding steel bars that have to be covered in
…show more content…
Delays in obtaining permissions that the contractor has taken practical steps to evade.

Often, change orders may also be necessary to alter the original contract schedule because of delays that arose in the project due to unexpected situations. The owner, the contractor or a third party may be accountable for delay.

In construction contracts, there are what are called force majeure contract clauses which refer to incidences which are beyond the reasonable control of any party to the construction contract. These are known as "acts of god" or "unavoidable casualty." For these types of events, claims for a time extension are typically allowed. These claims are due to severe weather, floods, fire, sabotage, etc.

As an example, Figure 6.3 shows the time extension claim with the attached supporting documents such as the PAGASA advisories and rainfall monitored on the day the typhoon named “Karen” struck the country last October 2016.

In this letter, the reader is notified that a one day time extension is claimed due to the extreme weather inclement that is beyond the control of the contractors and engineers. A good case of the force majeure contract, this is a claim that must be accepted by the owner of the

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Tony Tavare Case

    • 233 Words
    • 1 Page

    Hello Paul, I am not the one that approve or deny a variance request. Tony Tavares makes this decision.…

    • 233 Words
    • 1 Page
    Satisfactory Essays
  • Satisfactory Essays

    Proj586 - Week 2 Quiz

    • 932 Words
    • 4 Pages

    A) The triple constraint of project management describes the interdependency between the three cornerstones of a project: 1. Scope - all the work we have to do in order to create the clearly specified product. 2. Schedule - the time we need in order to create that product. 3. Budget - the total amount of money we need in order to create that product. If the scope is increased because of additional features added to the product then the time and amount of money has to increase as well. In order to shorten the time we could reduce the scope and consequently reduce the budget of that project. The time could be shortened as well by involving more resources…

    • 932 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Requests outside the scope of project are considered change orders and these changes may delay the project delivery and also increase the costs of project.…

    • 420 Words
    • 5 Pages
    Satisfactory Essays
  • Best Essays

    In 1987, the trustee of a property trust employed CDG Pty Ltd (the first respondent) to design the foundations of a commercial building. The second respondent was a civil engineer employed by the first respondent and was its project manager in relation to the complex’s design and construction.…

    • 2813 Words
    • 10 Pages
    Best Essays
  • Satisfactory Essays

    Inclement weather, the risk is high but the impact is low, but there is little to nothing we can do about this, it is an act that cannot be controlled and all we can pretty much do is to schedule construction for summer and landscaping for…

    • 311 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    Snow Storm Lawsuit Summary

    • 1891 Words
    • 8 Pages

    This case is about a lawsuit that generated from a small community hospital due to a snow storm. During the storm many hospital health care providers were unable to report to work due to the weather, and the Chief Executive Officer was vacationing in the Bahamas. In the meantime, many patients suffered from lack of care and injuries. As a result, many relatives of those patients decided to sue the hospital on their behalf after they died a year later for negligence, duty of care, and wrongful death. This paper will identify and explain the legal, ethical, professional, and business considerations that the hospital would have to face under the unfortunate circumstances.…

    • 1891 Words
    • 8 Pages
    Better Essays
  • Good Essays

    Risk Management Plan Devry

    • 1424 Words
    • 6 Pages

    3. Weather issues causing delay in outside work. This could cause construction delays on the roof and the outside fencing area.…

    • 1424 Words
    • 6 Pages
    Good Essays
  • Satisfactory Essays

    Law 531 Memorandum

    • 981 Words
    • 4 Pages

    This memo is in response to the dispute over the contract between Span Systems and Citizen-Schwarz AG (C-S). Management is taking the necessary steps in resolving the issues C-S is reporting of low quality deliverables and schedule delays. C-S is threatening rescission of their contract and demand immediate transfer of all unfinished codes (University of Phoenix, 2002, Legal Environment of Business: Contract Creation and Management, Law 531). C-S must prove a material breach is occurring and give adequate notice to Span Systems to issue a rescission (Cheeseman, 2010). Span Systems and C-S signed a one-year contract worth $6 million dollars that has five clauses for breach of contract and a project structure clause. This memo will identify what management is doing to avoid legal risks, minimize liabilities, and benefit from opportunities presented to make this contract successful.…

    • 981 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    Week Five Essay PM 3110

    • 1317 Words
    • 4 Pages

    One effective Way to make changes will be having an emergency meeting with the stakeholders and staff that are currently working on this project. At this point the whole project needs to be reevaluated and see if these changes can be done without having to change date lines. As (pinto 2010 p.6) addresses “Projects provided a philosophy and strategy for the management of change “Change is an abstract concept until we establish the means by which we can make real alterations in the things we do and produce.…

    • 1317 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    Essay

    • 1594 Words
    • 7 Pages

    The construction must start on January 14, 2004 and must be completed within fifteen months. Liquidated damages (penalty clause) of $250,000 per calendar day of delay beyond March 31, 2005 is written into the contract. On the other hand, Ace will receive an Early Completion Bonus of $100,000 per day for each workday the project is completed before March 31, 2005.…

    • 1594 Words
    • 7 Pages
    Powerful Essays
  • Powerful Essays

    Three Mile Island Effects

    • 3565 Words
    • 15 Pages

    potential dangers has been far more amplified than that of today. From the inception of nuclear…

    • 3565 Words
    • 15 Pages
    Powerful Essays
  • Satisfactory Essays

    Annotated Bibliography

    • 680 Words
    • 3 Pages

    Assaf, S.A. and Al-Hejji, S. (2006) Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349-57.…

    • 680 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    The End

    • 805 Words
    • 4 Pages

    Homeowners who use contractor to complete repair to their homes are using the function “The Law Provides Predictabilities”, because the contract law provides homeowner with a level of assurance the repair will be completed.…

    • 805 Words
    • 4 Pages
    Good Essays
  • Better Essays

    National Flood Insurance

    • 1715 Words
    • 7 Pages

    Fegan, R. & Olexa, M. (1998). The Disaster Handbook: How the National Flood Insurance Program (NFIP) works. Retrieved June 18, 2007 from http://209.85.165.104/search?q=cache:eTvpkW-4_g8J:disaster.ifas.ufl.edu/PDFS/CHAP04/D04-36.PDF+NFIP&hl=en&ct=clnk&cd=17&gl=us…

    • 1715 Words
    • 7 Pages
    Better Essays
  • Powerful Essays

    Clause 19.1 of PSSCOC, defines the variations as “any change in the original contract intention”.…

    • 1911 Words
    • 8 Pages
    Powerful Essays