Preview

The Grantt Charts Provides Both A Plann

Satisfactory Essays
Open Document
Open Document
439 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
The Grantt Charts Provides Both A Plann
The Grantt charts provides both a planning function and control function.

Reference

Bozarth, C.C. and Handfield, R.B. (2012). Introduction to operations and supply chain management (3rd ed.). Upper Saddle River, New Jersey: Pearson Prentice Hall. ISBN: 9780132747325

Discussion 1 Ivron Robertson
From the end of Chapter 14, complete Discussion Question 3: What are the main advantages of using a network-based approach to project management rather than a Gantt chart? Under what circumstances might a Gantt chart be preferable to a network-based approach? Respond to at least two of your classmates’ postings. Reading from the text, the main advantage(s) of using a network based-approach to project management rather than a Gantt chart is that “Network diagrams improve on Gantt charts by visually showing the linkages between various activities” (Bozarth, C.C. and Handfield, R.B. pg.443 (2012) I think a circumstance that might be preferable to a Gantt chart would be a construction build for an office building, parking garage, or playground. This graphical tool is great for showing expected start and end times for project activities, and being able to track actual progress against these time targets.
Nicholas Rosetti Emai
Unlike grant based approaches, Network based let you actually see the connection between different tasks. This is important when you have tasks that need to be done but you don't really know how long it will take In a Gantt chart, it shows a time-frame on when tasks need to be completed. So with this being said, if you do not know how long certain tasks in a project will take and there are various different tasks that must be completed while needing to know how they correlate to other tasks, you should use a network based approach. If you have a time frame for each task a Gantt based approach will be sufficient. (Bozarth, Handfield 2012) As stated, a Gantt based approach has a time frame for each task. I think this approach will be great in an

You May Also Find These Documents Helpful

  • Powerful Essays

    Nt1330 Unit 6 Paper

    • 579 Words
    • 3 Pages

    Project Network Diagram which includes tasks, task estimates, task dependencies, resource names, and completion %.…

    • 579 Words
    • 3 Pages
    Powerful Essays
  • Satisfactory Essays

    INDEX 1 WORK BREAKDOWN STRUCTURE -------------------------------------- 3 2 WORKBREAKDOWN STRUCTURE OUTLINE --------------------------- 4 3 NETWORK DEVELOPMENT DIAGRAM -------------------------------------- 6 4 GANTT CHART ---------------------------------------------------------------------- 7 5 FORMAL REPORT -----------------------------------------------------------…

    • 311 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    CMGT 410 Week 4 Resources

    • 508 Words
    • 3 Pages

    Gantt diagram showing duration estimates for all tasks and their sequencing (including precedence relations) and highlighting any critical path(s) arising from task dependencies ultimately determining the minimal duration of a project…

    • 508 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    In regard to network analysis, an effective project manager must possess a solid, but not necessarily expert, understanding of network infrastructure, topology, and security. More important than actual technical knowledge is the project manager’s ability to organize complex tasks, provide critical direction to technical resources, create, update, and manage the project plan, manage escalations, and facilitate effective relationships with management and stakeholders. The network analysis project manager should have several successful projects in their past to refer to, be able to iteratively adjust the project plan as required, work under pressure, and display proficiency with various project reporting and management tools such as Microsoft Project and the Microsoft Office Suite. Along with accurate and timely reporting and status updates tailored to specific audiences, the network analysis project manager will report directly to the Kudler Fine Foods sponsors and stakeholders and manage all technical resources associated with the…

    • 899 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Chapter 7: Advanced Project Network Analysis and Scheduling (pp. 240-272, 275-277) Earned Value Project Management Chapter 7: Plan and Schedule the Project (pp. 63-74) Course Project, Part 1 (CP-1) Due Graded Discussion Topics…

    • 390 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Gantt Chart Analysis

    • 1192 Words
    • 5 Pages

    Due to the time that it will take to complete the assignment, I have created a large Gantt chart to compensate the full amount of time it will take to finish construction. I have discovered that all of the tasks rely on the tasks previous to them as it is a building site. For example the construction team cannot pour concrete into the holes for support until the holes have been created or the clearance of the site of all the rubble after the site was cleared.…

    • 1192 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    Chapter 3 of Systems Analysis and Design in a Changing World explains the techniques and steps required to build a project schedule using the Gantt chart view in MS Project. This appendix provides a similar explanation of how to build a project schedule, but it is based on using a PERT/CPM chart or diagram for the schedule format. A Gantt chart and a PERT/CPM chart both provide essentially the same information about project activities and tasks. Each chart has unique strengths and weaknesses. As you learned in Chapter 3, a Gantt chart is a type of bar chart that is superimposed on a calendar. The primary strength of a Gantt chart is that the bars show the duration and project progress as compared to the days and weeks of the calendar. The calendar comparison provides an effective visual representation of the project timeline and helps you track project progress, because the Gantt chart shows what should have been accomplished by a specific date and what has actually been completed on that date. Chapter 3 illustrates an example of the tracking view of a Gantt chart. A PERT/CPM chart, as you will learn in this appendix, is a network type of diagram with boxes that represent the tasks or activities of the project, and with connecting arrows that represent the sequence and dependencies between tasks. The strength of a PERT/CPM chart is that, as a network, it provides a visual representation of the relationships between tasks of a project. During the development of the project schedule, and especially while trying to determine task dependencies, a PERT/CPM chart is an effective tool. PERT, which stands for Project Evaluation and Review Technique, was first developed in the 1950s and was used by the United States Department of Defense to organize, monitor, and control very large, complex defense projects. CPM, which stands for Critical Path Method, was developed independently, also in the…

    • 4887 Words
    • 20 Pages
    Good Essays
  • Good Essays

    The network diagram display logical relationships among the various activities that take place within a project. It also allows the project manager to see how the various activities flow towards to…

    • 576 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    2.3 Compare and contrast work breakdown structure, Gantt charts, program evaluation review technique, and critical path method.…

    • 760 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    Project Network

    • 1752 Words
    • 8 Pages

    A project network illustrates the relationships between activities (or tasks) in the project. Showing the activities as nodes or on arrows between event nodes are two main ways to draw those relationships.…

    • 1752 Words
    • 8 Pages
    Good Essays
  • Good Essays

    Giant Chart

    • 631 Words
    • 3 Pages

    * A Gantt charts is not recommended to define the work breakdown structure and the schedule activities at the same time.…

    • 631 Words
    • 3 Pages
    Good Essays
  • Better Essays

    projects, multiple users, and multiple projects. All of these tools can produce Gantt charts and…

    • 1139 Words
    • 2 Pages
    Better Essays
  • Satisfactory Essays

    36. A must finish before B can start, both A and C must finish before D can start…

    • 259 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    3.2.1. Gantt Chart (Duration should start from initial development to final deliberation, must depend on the model)…

    • 496 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Project Management

    • 963 Words
    • 4 Pages

    ‘The network diagram is defined as a graphical presentation of the project’s activities shows the planned sequence of work’ Burke (2003, p.131). It is also called as precedence diagramming method (PDM). ‘It is a method of constructing a project schedule network diagram that uses boxes or rectangles, which referred to as nodes, to represent activities and connects them with arrows that show the dependencies’ The Project Management Book of knowledge (PMBOK) (2004, p. 132). The network diagram (Appendix 1.0) has been drawn out accordingly to the table 1 for Jashol Ltd in order to show activities and period it takes to customise luxury cars for its customers.…

    • 963 Words
    • 4 Pages
    Good Essays