Preview

The Network Diagram

Satisfactory Essays
Open Document
Open Document
540 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
The Network Diagram
1.2. ACTIVITIES TIMING AND TOTAL FLOAT

To determine timing of activities in the network diagram the following calculations were done for each node: Earliest Start-(ES), Earliest Finish-(EF), Latest Start-(LS) and Latest Finish-(LF).

Field and Keller (1998, p. 191) ES and EF are found by using the forward pass through the network … from the unique project start node and ends at the unique project completion node.

ES is the ending day for the previous node/activity, where more than one activity preceded an activity, the ES time was taken from the activity whose ending day has the largest number.

EF is the ES added to the duration of the activity (given), e.g. Activity-A, (start node: zero) plus its duration 4 days: EF is 4 days. Activity-A figure becomes the ES for the next successive Activity-B; this sequential calculation is done for all nodes straight to the last project node.

Project duration was calculated using formula-1:

(Field and Keller 1998, p. 190) defined LF as the latest time by which the node must be reached in order for the project to finish by its required completion date.
The latest event time is the latest time the node must be reached in order for the project to finish by its required completion date as defined by Field and Keller (1998, p. 190). LS and LF of each activity is calculated using a backward pass.

LF of a node is the LS of the succeeding node and latest day that the project can finish to meet the project duration; where an activity preceded two activities, the LF was taken from the succeeding activity with the smallest LS time.

LS time is the latest day an activity can start for the project to be completed on-time, it is found by subtracting the duration from the LF time. Example: LS of Activity-H(29) becomes LF-(29) of its preceding Activity-G.

Schwalbe (2009, p. 139) Float is the amount of time an activity may be delayed without delaying a succeeding activity or project finish date. It

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Step 1: Construct a network diagram for the project. (NOTE: EF for activity H should be 19)…

    • 552 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    QAT1 Task 4

    • 501 Words
    • 7 Pages

    E 7.5 14 12.5 19 6.5 F 7 7 17 17 0 CRITICAL G 17 17 23.5 23.5 0 CRITICAL H 18.5 19 29.5 30 0.5 I 23.5 23.5 30 30 0 CRITICAL J 30 30 33.5 33.5 0 CRITICAL a. Duration of project: 33.5 weeks b. Slack for task A: 6.5 weeks c. Slack for task H: 0.5 weeks d. Task F scheduled start: week 7 e. Task I scheduled completion: week 30 4.…

    • 501 Words
    • 7 Pages
    Satisfactory Essays
  • Powerful Essays

    PROJ 586 Final Exam

    • 872 Words
    • 4 Pages

    6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time.…

    • 872 Words
    • 4 Pages
    Powerful Essays
  • Satisfactory Essays

    Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project? (5 points) b) What is the Critical Path of the Project? (5 points) c) What is the ES for Activity D? (1 points) d) What is the LS for Activity G?…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Date constraints –> Date constraints establishes time milestones or benchmarks on a project that the entire construction team works toward…

    • 3773 Words
    • 12 Pages
    Powerful Essays
  • Best Essays

    Is3350 Unit 1 Assignment

    • 3307 Words
    • 14 Pages

    In order to calculate the timing of an activity ‘Duration’ of the activity needs to be summed up with the ‘Earliest Finish…

    • 3307 Words
    • 14 Pages
    Best Essays
  • Satisfactory Essays

    What is the EF for Activity B? Day 4 g. What is the LF for Activity H? Day 22 h. What is the float for Activity I? 0…

    • 562 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Brs Mdm3 Tif Ch07

    • 2550 Words
    • 19 Pages

    3) Refer to the figure. What is the slack time, in days, associated with activity E?…

    • 2550 Words
    • 19 Pages
    Powerful Essays
  • Satisfactory Essays

    TPV1 Sample Questions

    • 453 Words
    • 3 Pages

    D. Milestones are indicators that any of the project major events have already taken place…

    • 453 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    ____ 6. A(n) ________ path for a project is the series of activities that determine the earliest time by which the project…

    • 2493 Words
    • 10 Pages
    Powerful Essays
  • Powerful Essays

    Mgt150 Assignment 1

    • 970 Words
    • 4 Pages

    University of Management and Technology MGT 150 Project Management Assignment 1 Bottom-up cost estimating exercise (Module 3, pp. 19-20) 1.0 Research 1.1 Birdhouse Book…………………………………………………. …… $ 30.00 1.2 Jimmy’s time to read up on birdhouses…………………….… …… $ 4.00 1.3 Dad’s time………………………………………………………. ….… $ 80.00 2.0 Materials acquired 2.1 Lumber…………………………………………………………..…

    • 970 Words
    • 4 Pages
    Powerful Essays
  • Satisfactory Essays

    AIB Problem

    • 565 Words
    • 3 Pages

    e ) What is the slack time (float) for activity E? (1 points) Answer: 4 days f)…

    • 565 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Dragonfly case study

    • 1041 Words
    • 5 Pages

    2. The red dotted line represents the circular dependency between activity A4 and activity A9.…

    • 1041 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    D.U Singer Hospital

    • 5200 Words
    • 21 Pages

    activity begins at its early start, regardless of resource constraints. ..................................... 8 vi. A period labor requirements table for each group and the project as a whole. Include…

    • 5200 Words
    • 21 Pages
    Good Essays
  • Good Essays

    Zuma Project

    • 1253 Words
    • 6 Pages

    If the project is resource constrained, then the finish date will be 2/18/09, since there was an additional 40 days added to the project duration. Additional personnel should be added in order to meet the desired new deadline.…

    • 1253 Words
    • 6 Pages
    Good Essays