Preview

Theory of Constraints & Project Management

Satisfactory Essays
Open Document
Open Document
718 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Theory of Constraints & Project Management
William Agadzi
RPJM-103/Fall 2009
Exercise: Goldratt

How Does The Theory of Constraints Apply To Project Management
The goal of every project is to make profit. The sooner the project is completed, at least by the deadline, the better it is for the project to accrue its potential benefits –and vice versa. Constraints, negatively affect project goals. In the triple-constraints (time, cost, scope), time remained the most impacting constraint to projects. The critical chain resolved this issue by removing protection time from tasks, aggregating them into feeding and project buffers, and placing them in strategic locations within the project network where they will serve to protect the project as a whole. This way, the fixed elements of each task is the aggressive but possible estimate, whilst the variable components are called safety. The safety is managed and adjusted time after time to the needs of the schedule. However, time is not the only constraint affecting projects, and the technique of Theory of Constraint (TOC) deals with these constraints to optimize project performance.
While applying TOC the project manager first and foremost, identifies the most important factor that constraints the project in that stage of development. This is done by continuous assessment of the project and process management to recognize the most pressing constraint. For in any given project scenario, there are constraint of resource, quality etc that present challenges to project’s success. To avoid applying the right solution to wrong problem however, the project manager above all pinpoints, through the technique of TOC, the number one constraint that has the potential to derail the project.
Then, supposing after the initial assessment the issue turns out to be one of a resource constraint the project manager takes advantages of the drawback. For instance, if the resource is equipment that does not produce to a required capacity at a given time, it will be scheduled to

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Proj586 - Week 2 Quiz

    • 932 Words
    • 4 Pages

    A) The triple constraint of project management describes the interdependency between the three cornerstones of a project: 1. Scope - all the work we have to do in order to create the clearly specified product. 2. Schedule - the time we need in order to create that product. 3. Budget - the total amount of money we need in order to create that product. If the scope is increased because of additional features added to the product then the time and amount of money has to increase as well. In order to shorten the time we could reduce the scope and consequently reduce the budget of that project. The time could be shortened as well by involving more resources…

    • 932 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    In week four material we learned about IT projects and how crucial and essential these projects are to a business. We learned the importance of these projects and project management. A key point discussed in week four material is project planning and the triple constraints of project management. The triple constraints of project managements include the time, scope, and cost of a project. Every project also should be assessed using five steps or stages:…

    • 546 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Whatever the type of project, there are three important elements of cost, schedule and performance project managers must achieve in order to attain a successful project outcome. These elements are interrelated which means a slight change of one of the elements such as prolonging the project time schedule highly affect the element of cost or more…

    • 1428 Words
    • 6 Pages
    Powerful Essays
  • Satisfactory Essays

    Introduction to Project Scheduling IX. The Critical Path Method (CPM) X. Program Evaluation and Review Technique (PERT) XI. Project “Crashing”…

    • 5350 Words
    • 1 Page
    Satisfactory Essays
  • Good Essays

    Investiong in Tufs

    • 524 Words
    • 3 Pages

    Another thing that went wrong in the project is the imbalance between its scope and the scheduling of the project as result of the management pressure to produce fast result regardless of what feasible. This problem would have avoided if the scheduling of the project take into account what was possible more than what was desired given the scheduling of the project.…

    • 524 Words
    • 3 Pages
    Good Essays
  • Better Essays

    The constraints which ultimately compromise the project’s performance are the quality the driver constraints. These are constraints that do not fail without dragging the project down to failure along with it. This is also the least flexible of all the constraints. The other constraint is the middle constraint which are constraints that are not as rigid as the driver constraints neither they are very flexible. The last one is the weak constraint which is the most flexible constraints. These constraints are very important but still possess the greatest flexibility.…

    • 1283 Words
    • 6 Pages
    Better Essays
  • Powerful Essays

    The consideration of resources adds another dimension (beyond the element of time) to planning and scheduling. In many projects, the amounts of the various types of resources available to perform the project activities are limited. Several activities may require the same resources at the same time, and there may not be sufficient resources available to satisfy all the demands. If sufficient resources are not available, some activities may have to be rescheduled for a later time when resources are available for them.…

    • 2049 Words
    • 9 Pages
    Powerful Essays
  • Good Essays

    Pert Mustang

    • 1016 Words
    • 5 Pages

    A table containing the project activities, the time estimates and the precedence relationship will be prepared and a network diagram will be drawn to structure the immediate predecessor activities. The critical activities will be identified to indicate that the project can be completed within 45 working days.…

    • 1016 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Pm Tests

    • 443 Words
    • 2 Pages

    b) If the project schedule is relaxed or lengthened, what is the impact on quality? (15 points) (Points : 30)According to the triple constraints: "Scope, Time, Cost". All three of these impact the quality depending on which trade off is affecteda) The longer a project takes to complete, the more it will impact the quality of the project as a whole. b) Being relaxed or expanding the time frame for completion will impact scope and cost. Why? More money and less time to complete the work package deliverables.…

    • 443 Words
    • 2 Pages
    Good Essays
  • Better Essays

    The Work Breakdown Structure (WBS) contains the different activities within a project. Every activity necessitates outputs from several experts following different measures and timelines. The total of these activities represent the end deliverable. In order to control the task effectively the project supervisor must track the logical order of the various parts. He must visualize the final project deliverable. Views regarding project management, benefits and restrictions, bottlenecks, changes to risk or time in a crisis, and four points touched.…

    • 1092 Words
    • 5 Pages
    Better Essays
  • Good Essays

    Southwest Airlines

    • 775 Words
    • 4 Pages

    Chapter 14 is titled “Project Planning and Scheduling” and it is mainly about the planning and scheduling of projects with the unique, one-time production activity. There were three main objectives that were described in this chapter and there were time, cost, and performance. These objectives are conflicting, trade-offs among them must constantly be made in the course of managing projects. They also go through three phases: planning, scheduling, and control. This planning phase organizes and establishes the objectives for the project.…

    • 775 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Project Management

    • 440 Words
    • 2 Pages

    The time constraint refers to the amount of time available to complete a project. The cost constraint refers to the budgeted amount available for the project. The scope constraint refers to what must be done to produce the project's end result. These three constraints are often competing constraints: increased scope typically means increased time and increased cost, a tight time constraint could mean increased costs and reduced scope, and a tight budget could mean increased time and reduced scope.…

    • 440 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Exam 3 Study Guide

    • 2230 Words
    • 9 Pages

    1. How can we use the Project Life Cycle and the triple constraint triangle to assess a project’s performance?…

    • 2230 Words
    • 9 Pages
    Powerful Essays
  • Good Essays

    1) What are some of the principal reasons why project management has become such a popular business tool in recent years?…

    • 687 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Pinto Pm2 Ism Ch10 1

    • 3754 Words
    • 21 Pages

    INSTRUCTOR’S RESOURCE MANUAL CHAPTER TEN Project Scheduling: Lagging, Crashing, and Activity Networks To Accompany PROJECT MANAGEMENT: Achieving Competitive Advantage By Jeffrey K. Pinto CHAPTER 10 PROJECT FOCUS – A Crushing Issue: How to Destroy Brand New Cars INTRODUCTION 10.1 LAGS IN PRECEDENCE RELATIONSHIPS…

    • 3754 Words
    • 21 Pages
    Satisfactory Essays