Preview

Thesis GCCC

Powerful Essays
Open Document
Open Document
16138 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Thesis GCCC
1.1 Introduction

This research dissertation was written to fulfil a major element of the final year of the BSc Construction Management (Honours) degree programme in the Galway Mayo Institute of Technology.

The subject selected, Construction Procurement Reform, was chosen following a procurement reform put in place on 1st January 2007 to take effect on 19th February 2007. I chose this topic for my dissertation as this reform, to the method of contracting for public works projects, is of such significance that it fundamentally alters the relationships between the Client and Contractor involved in these projects.

In May 2004 the Government decided to reform the approach to procuring public works projects. The reforms were a Value for Money initiative to help address concerns in Government circles, in the media and amongst the public generally regarding project cost overruns on public works contracts, the main objective being to allocate risk to those best able to manage and control it. This would involve shifting responsibility for managing and controlling risks from the public sector to Contractors.

Following discussions between Government departments and the forum for the construction industry known as the Government Contract Committee for Construction (GCCC), the main issue identified by the Government departments was that the current contracting arrangements were failing to achieve Cost Certainty resulting in major cost and time overruns.

A number of principal objectives were then set out by the GCCC for these contracts. They are:

Greater Cost Certainty and Value for Money
More cost effective delivery of public works
Standardised public sector terms and conditions

Also included in the construction procurement reforms is a ‘Standard Condition of Engagement for Construction Consultants’ contract. The objective here is to develop more client-focused and standardised conditions for the employment of construction consultants. Prior to this,



References: Constructing the Team, The Latham Report, 2004 Public Works Contracts for Building Works Designed by the Employer, Department of Finance Public Sector Procurement Regulations, Department of Finance, 2006 Public Expenditure 2007, Department of Finance, 2007 The RIAI Contracts, David Keane, 2001 Forms of Tender, Agreement and Bond for use in Works of Civil Engineering Construction, Institute of Engineers of Ireland, 2002 GDLA Agreement and Conditions of Contract for Building Work, Royal Institute of the Architects of Ireland, 1982 Public Works Construction Contracts Training Manual, National Public Procurement Policy Unit, May 2007.

You May Also Find These Documents Helpful

  • Good Essays

    This project plans to develop a methodology to estimate future projects’ costs and their appropriate contingency reserves for changing prices in constructional projects. Based on the methodology, recommendations will be given in order to change Ministry of Construction’s policies that relates to project budgets, and how to deal with the current policies if they are not changed.…

    • 311 Words
    • 2 Pages
    Good Essays
  • Better Essays

    Many clients to the construction industry will often face a steep learning curve on their construction project or programme. To establish a valid and robust procurement strategy at the outset is considered a key aspect to achieving a successful outcome to their business or organisation objectives. A significant number of clients come into the category of either being described as occasional or inexperienced. They will rely on their appointed professionals to assist in their selection of the best-suited procurement path.…

    • 3692 Words
    • 22 Pages
    Better Essays
  • Better Essays

    5) Quality Assurance – No clear quality control plan was required in the contract. No agency approvals were contained in the contract terms which precluded the contractor from starting a new phase of the project. No acceptance testing procedures were included. The terms for quality control and acceptable performance are very vague.…

    • 1374 Words
    • 4 Pages
    Better Essays
  • Best Essays

    Managing Change

    • 2917 Words
    • 12 Pages

    The pace of change has accelerated to a significant pace in organisation over recent years. Changes in external environment have brought about the need for organisations to adapt their internal attitudes, strategies, structures and operations to meet the demands of new external conditions (Craig et al 2005). The construction Industry is no exception to this rule and in July 1994 Sir Michael Latham was commissioned by the United Kingdom government and industry organisations to review procurement and contractual arrangements in the UK construction industry, aiming to tackle controversial issues facing the industry during a period of lapse in…

    • 2917 Words
    • 12 Pages
    Best Essays
  • Good Essays

    The company's relationship with contractors is predominately transactional in nature where construction work is tendered and bid on a competitive basis. Work is primarily awarded based on lowest cost with some consideration for…

    • 612 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Riba Plan of Work

    • 2055 Words
    • 9 Pages

    The choice of procurement route has a fundamental influence on how different Work Stages proceed. This is summarised in outline as far as possible but the exact way in which different Stages are conducted within the overall project programme needs careful consideration at the outset. It is worth noting that the RIBA Plan of Work was originally developed to reflect the needs of Traditional contract forms. The subsequent development of alternative contract forms such as PFI, BSF and partnered contracts means that RIBA Stages don’t necessarily fit precisely with discrete stages in these alternative contract forms. The Achieving Excellence in Construction Procurement guide 11 Sustainability identifies the intervention points for larger programmes such as BSF including PFI. See www.ogc.gov.uk.…

    • 2055 Words
    • 9 Pages
    Good Essays
  • Good Essays

    One of the main problems in this sector employers is that the concept and design phase of a contract is not exactly located .it is not clear. Therefore, a detailed and comprehensive tender documents at the disposal of contractors for the price not…

    • 1160 Words
    • 5 Pages
    Good Essays
  • Best Essays

    References: 1. Alexander F H Loke. 1998 RISK MANAGEMENT AND CREDIT SUPPORT IN PROJECT FINANCE (Singapore Journal of International & Comparative Law. 2. Kenn Dolan June 2009; Exploring Techniques for Making Better Project Investment Decisions. 3. Kenn Dolan June 2009; MANAGING PROJECT APPRAISAL & FEASIBILITY. 4. Dr Patrick X.W. Zou1, on “Identifying Key Risks in Construction Projects: Life Cycle and Stakeholder Perspectives” (2004). 5. Brian A. Burt, BDS, MPH, PhD (2001) DEFINITIONS OF RISK. 6. Global association of risk professionals, June 2004; The History of Financial Risk Management: A (Mostly) Personal View. 7. Simon A. Burtonshaw-Gunn, Risk and Financial Management in Construction. 8. Dr Patrick. X.W. Zou1, Identifying Key Risks in Construction Projects: Life Cycle and Stakeholder Perspectives. 9. Uher, T. (2003) Programming and Scheduling Techniques, UNSW Press, Sydney 10. Uher, T.E. and Toakley, A.R. (1999) Risk Management in the Conceptual Phase of a Project, International Journal of Project Management, 17(3), 161-169. 11. Abdou, O.A. (1996) Managing Construction Risks, Journal of Architectural Engineering, 2(1), 3-10. 12. Flanagan, R. and Norman, G. (1993) Risk Management and Construction, Victoria: Blackwell Science Pty Ltd, Australia. 13. Ward, S.C. and Chapman, C.B. (1995) Risk-Management Perspective on the Project Lifecycle, International Journal of Project Management, 13(3), 145-149. 14. Project Management Body of Knowledge (PMBOK) from the Project Management Institute 15. Oxford English Dictionary (2009) 16. Study by the National Economic Development Office, London. 17. ISO 31000 (2009) /ISO Guide 73:2002 18. Mehr et al, Management: Concepts and applications 19. http//www.dispute in construction.com/construction-claim-consultants 20. Duff, Michael A. and Reid, David R (Sept 2001) Operational risk management: A holistic approach 21. K.G Krishnamurthy, S.V Ravindra.Construction and Project Management for Engineers, Architects, Planners and builders – 22. D Arcy,Steven P. Volume 12 Journal of risk Management of Korea,…

    • 2629 Words
    • 11 Pages
    Best Essays
  • Powerful Essays

    The unprecedented escalation of prices escalations in the construction industry has caused significant financial hardships for unprepared supplier, subcontractors, contractors, and owners. Contract losses suffered, projects delayed, or serious disputes resulting from the efforts of constructions industry players to mitigate, shift or recoup the financial consequences of this sudden and dramatically price escalations. Yet, it is certain that profits have been lost, relations have been damaged, projects have been impacted, and construction lawyers have been called upon to look for ways to soften or shift the impact of price escalations on their unprepared constructions client.[11]…

    • 17613 Words
    • 71 Pages
    Powerful Essays
  • Powerful Essays

    Uap Document 301

    • 4499 Words
    • 18 Pages

    UAP DOCUMENT 301: GENERAL CONDITIONS SECTION 1: DEFINITIONS  CONTRACT DOCUMENTS – consists of the following: 1. Agreement 2. General conditions 3. Special provisions 4. Specifications 5. Drawings  OWNER – person ordering the project for execution  ARCHITECT – commissioned by the owner  ENGINEER – person so named in the contract document  PROJECT REPRESENTATIVE – full time construction inspector hired by owner assisting in the supervision of the work.  CONTRACTOR – person or firm whose proposal has been accepted & contract awarded  SUB-CONTRACTOR – having direct contact with contractor, acts in behalf of the contractor in executing any part of the contract  SURETY – person, firm, or corporation providing guarantee for contractor’s bonds  PROPOSAL – offer of a bidder  PROPOSAL BOND – cashier’s check or surety bond with the proposal submitted by the bidder to guarantee that the bidder will enter into the contract.  PERFORMANCE BOND – (15%) approved form of security furnished by the contractor as a guarantee to execute work in accordance with terms of the contract.  PAYMENT BOND – (15%) approved form of security furnished by the contractor as guarantee to pay all obligations arising from the contract  GUARANTEE BOND – (15%) approved form of security furnished by the contractor to guarantee to the quality of materials and workmanship performed.  AGREEMENT – contract between owner and contractor undertaking the project  ADVERTISEMENT/ INVITATION TO BID – notice or invitation issued to bidders giving information of the magnitude and extent of the project, nature, etc.  BID BULLETIN – additional information on contract documents  INSTRUCTION TO BIDDERS – list of instructions on preparation & conditions for award of contract  DRAWINGS – graphical representation of work  GENERAL CONDITIONS – printed…

    • 4499 Words
    • 18 Pages
    Powerful Essays
  • Better Essays

    1. Mark Pole et al state in Industry Guidance for Clients (2007:16) the importance of verifying the competence of the architect (Norman Foster), contractors (Multiplex) and other members that are involved in the project, (i.e. consultants, steel construction…). Participants have to be ‘adequately resourced and appointed early enough for the work they have to do’ (HSE publication L144, 2007:16)…

    • 1379 Words
    • 6 Pages
    Better Essays
  • Powerful Essays

    Construction revolves around different activities culminating into a constructed facility borne out of the wish and desire of the client. A construction project is completed as a result of the combination of many events and interactions, planned or unplanned, over the life of a facility, with changing participants and processes in a constantly changing environment (Saqib, Farooqui and Lodi, 2008). The growth of towns has accelerated as a result of high population growth. Large and complex projects have been built, attracting consultants and contractors from all over the world. Most of these parties appear to lack a sufficient understanding of the social, cultural, and physical environment under which construction takes place. This situation, coupled with poor project scope definition, has led to inadequate designs, which often lead to many changes to plans, specifications, and contract terms (Arain 2002). It is in the design stage where the requirements of the client are identified and the constructive aspects and the standards of quality are defined through procedures, drawings and technical specifications. Currently, the work within the design stage is split into several temporary sequences, and it is delivered to different specialists for its execution.…

    • 10192 Words
    • 41 Pages
    Powerful Essays
  • Satisfactory Essays

    It does not apply to construction contracts entered into by a natural person for any construction work in respect of any building which is less than four storey’s high and which is…

    • 376 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Private and Publie Job

    • 786 Words
    • 4 Pages

    There are always different points of view between the needs of clients for public and for private sectors. There are 4 major factors affecting the choice of different procurement and contractual arrangement in both the public and private sectors. They are “Prestige”, “Profitability”, “Expectation” and “Quality”. The factor will be different in every case or project with different humanity, person, company… Prestige is very important especial for those project by public sector. It could be one of the factors that would affect a company for many years. For an example, many of the government projects is over budget as they thought before, that was not because they had a poor management and arrangement, it was because they will always try to do the best as they can to afford others people negative command. Therefore, change and change happened during the civil work or building time but still need to be finished on time. In this case, the public sectors had to invest more and more money into the project and try to maintain the quality of wok, finishing time on the project and the expectation for public. However it is not usually happened in the private sectors side, because for most of them the major factor affecting them is “Profitability” Profitability is the other major factor, without it no one will get in to the business. Most of the clients on private sectors side will put this factor on the top of their project. Sometime they will decrease the building time for the project. They want to finish it faster mostly because of two issues. First it could save money in their pocket and also they will have more people go for another project. In the positive side it is mean that they can use less time and limited people or workers and less money to work on the projects in hand. Second is the market. In an open market like Hong Kong that we are living right now, the unit price is different in every day. Every single developer want to sell it in a higher price to gain as…

    • 786 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    Safety and Health

    • 6805 Words
    • 28 Pages

    Construction 21 Steering Committee (1999) Re-Inventing Construction. Ministry of Manpower and Ministry of National Development, Singapore. Drewer, S. (1980) Construction and development: A new perspective. Habitat International, Vol. 5, 3/4, pp. 395-428. Egan, J (1998) Rethinking Construction. Department of the Environment, Transport and the Regions, http://www.construction.detr.gov.uk. Engineering News Record various issues in 1990 to 1999. Handy, C B (1985) Understanding Organizations, 3rd Edition. Penguin, Harmondsworth. Hill, R C and Bowen, P (1997) Sustainable construction: Principles and a framework for attainment. Construction Management and Economics, 15, 223-239. Hassan, T, Mitrovic, D, Gayoso, A and Hunter, I (1998) The Future LSE Industry, Work Package 2 of Report on the ELSEWISE Project. European Construction Institute, Loughborough. Hillebrandt, P M (1999) Problems of larger local contractors: Causes and possible remedies. Paper presented at Second Meeting of CIB TG29, Kampala, Uganda, 25-26 June. Hillebrandt, P M (2000) Economic Theory and the Construction Industry. Macmillan, London. Hofstede, G (1980) Culture’s Consequences: International differences in work related values. Sage, Beverly Hills. Latham, Sir M (1994) Constructing the Team. Her Majesty’s Stationery Service (HMSO), London. Liu, A M M and Fellows, R (1999) Cultural issues. In Rowlinson, S. and McDermott, P. (Eds.) Procurement Systems: A guide to best practice in construction. Spon, London, pp. 141-162. Liu, A M M and Fellows, R F (1999) The impact of culture on project goals. In Ogunlana, S. (ed.) Profitable Partnering in Construction Procurement. Spon, London, pp. 523-532. Miles, D and Neale, R (1991) Building for Tomorrow: International experience in construction industry development.…

    • 6805 Words
    • 28 Pages
    Powerful Essays