Preview

Tunnel Case Study

Good Essays
Open Document
Open Document
817 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Tunnel Case Study
Channel Tunnel Project Management Mistakes
Bellevue University
PMGT335-316S Project Cost
15 February 2012

Channel Tunnel Project Management Mistakes
The Channel Tunnel (Chunnel) project was one of the largest privately funded construction projects in history, and one plagued with mistakes. The project created a rail link between England and France spanning over 30 miles with 23.5 of the miles under water. The project melded a difficult mix of numerous contractors and regulatory agencies with bankers and two national governments (Fairweather, 1994). While an overall success the project suffered from many planning and management mistakes that caused it to be grossly over budget and late.
One of the key mistakes that befell the project was also one of the costliest. The contract that was entered into between Eurotunnel and Transmache Link (TML) for the terminals and the mechanical and electrical equipment was a lump-sum contract (Fairweather, 1994). This decision was driven by the desire of the bankers involved in the project for a level of certainty on the costs. This error could have been prevented with a few basic project management techniques. The bankers, being a key stakeholder, had the right to have their desires understood by Eurotunnel before any contracts were signed. What failed to happen was effective communications between the engineers at Eurotunnel who had the knowledge to understand the risks involved with this phase of the project and the bankers who were requiring a contract basis that was not appropriate to the type of project. The PMBoK (2008) provides that a proper project management plan with a thorough stakeholder management strategy and an effective communications plan could have ensured all stakeholders were aware of the risks and prepared to conduct contract negotiations with full knowledge and understanding.
Another stakeholder issue stemmed from the lack of structure and boundaries placed on the Intergovernmental



References: Fairweather, V. (1994, May). The channel tunnel: Larger than life, and late. Civil Engineering, 64(5), 42-46. Project Management Institute. (2008). A guide to the project management body of knowledge (4th ed.). Newtown Square, PN: Project Management Institute.

You May Also Find These Documents Helpful

  • Better Essays

    It Management Mgt2 Task 3

    • 4060 Words
    • 13 Pages

    Cited: A guide to the project management body of knowledge (PMBOK guide 5th edition).Newtown Square, Pa.: Project Management Institute, Inc., (2013)…

    • 4060 Words
    • 13 Pages
    Better Essays
  • Powerful Essays

    Project Management Institute. 2008. A Guide to Project Management Body of Knowledge Fourth Edition. Pennsylvania, USA: Project Management Institute, Inc…

    • 13536 Words
    • 144 Pages
    Powerful Essays
  • Powerful Essays

    References: Project Management Institute. (2008). A guide to the project management body of knowledge: PMBOK guide (4th ed.). Newton Square, PA: Author. ISBN: 9781933890517.…

    • 13779 Words
    • 56 Pages
    Powerful Essays
  • Good Essays

    7.05h World History

    • 447 Words
    • 2 Pages

    The Chunnel is an undersea railway linking England to France. It is 34.1 miles long crossing the English Channel. The Channel Tunnel possesses the longest undersea portion of any tunnel in the world. The tunnel carries high-speed Eurostar passenger trains. The successful project, organized by Eurotunnel, began construction in 1988 and opened in 1994.…

    • 447 Words
    • 2 Pages
    Good Essays
  • Good Essays

    The Chunnel

    • 385 Words
    • 2 Pages

    Just getting started on the Channel Tunnel was a monumental task. Funds had to be raised (over 50 large banks gave loans), experienced engineers had to be found, 13,000 skilled and unskilled workers had to be hired and housed, and special tunnel boring machines had to be designed and built.…

    • 385 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    Euro Tunnel

    • 3136 Words
    • 13 Pages

    * Management overestimate the chance of project success as stated in Eurotunnel prospectus of 1987. The justification was that “Whilst the undertaking of a tunnelling project of this nature necessarily involves certain construction risks, the techniques to be used are well proven. The directors believe… that 10%... would be a reasonable allowance for the possible impact of unseen circumstances on construction costs.” In reality the tunnel project was delayed and cost double as much as estimated from £4.9bn in 1987 to £10.1bn in 1994.…

    • 3136 Words
    • 13 Pages
    Powerful Essays
  • Powerful Essays

    The information in this report explains the project’s progress since the last report which was provided in 2000. Contained in the report are results determining the reasons for the delay in project completion and why the deadline of December 2002 was missed. The report also includes reasons explaining why the costs more than doubled from £195 million in the month of September 2000 to £431 million in the month of February 2004. The management of the project and the control approaches were also analyzed and the results included in the…

    • 2170 Words
    • 9 Pages
    Powerful Essays
  • Good Essays

    Millau Viaduct

    • 12693 Words
    • 51 Pages

    The choice of the route: integrating local and environmental interests (1988-1990) The project: difficult choice and thorough investigations (1991-1996)  Choosing between the high and low solution  Definition of the project  Competition for the design  Selection of the design Conception of the project: elaborating and developing the design (1997-1998) The concession: delivering the Millau Viaduct under a BFOT scheme The signature of the contract: a „three steps‟ process  First step: tendering process and candidates‟ selection  Second step: judging and elaborating bidders‟ propositions  Third step: negotiating and finalizing the contract Main features of the contract: financing and risk allocation…

    • 12693 Words
    • 51 Pages
    Good Essays
  • Good Essays

    Spread across Azerbaijan, Georgia and Turkey largest cross-border infrastructure construction project in the world dubbed the “contract of the century”. Financing was agreed after over two years of appraisal of the potential environmental and social impacts relating to the project.…

    • 1240 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    BAA has learned how to deal with major construction risks in complex projects that include the delivery of the Heathrow Express project. Further, BAA conducted research specifically on problems associated with airport projects and identified poor systems delivery and integration during the final stage of project execution as a major reason why international airports fail to open on time. BAA concluded that transferring the risk to the contractor offered no real protection for the client. The only way to succeed on T5 was to change the “rules of the game” by establishing a new governance structure and commercial principles embodied in the T5 agreement. BAA was under the leadership of Sir John Egan, who instructed BAA to adopt successful lean production techniques found in automobile, retailing, and other high-volume industries to achieve an orderly, predictable, and replicable approach to project design. Despite operational problems that occurred when T5 was first launched, the T5 project achieved its design and construction performance targets for cost, time, quality, and…

    • 1341 Words
    • 6 Pages
    Powerful Essays
  • Powerful Essays

    A INTRODUCTION Type of project Principal transport nodes Major associated developments  Lane Cove Tunnel  Joint Select Committee on Cross City Tunnel (Parliamentary Inquiry)  Infrastructure Implementation Group Review of Future Motorways  Cross City Tunnel Performance Audit  Upgrade of Bourke St  Reopening Parent projects Current status B BACKGROUND TO PROJECT Principal project objectives Key enabling mechanisms Main organisations involved  Key parties from the government  Key government agencies  Key private sector parties Planning and environmental regime  Broad Government policy  Outline of planning legislation  Environmental statements  Overview of public consultation  Ecological mitigation  Regeneration Appraisal methods/approaches Land acquisition…

    • 19501 Words
    • 79 Pages
    Powerful Essays
  • Satisfactory Essays

    Please highlight the major areas of strength in the management of this phase of the project:…

    • 277 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Mismanagement and fraud appear at the top of the list of faults and problems. There is no real effort to tackle the core issues behind these failures for one reason or the other. Unless these projects and their failures are aired in open courts people will continue to fumble in the dark for the real reasons of failures and be reliant on ill-informed journalism to further confuse them.This happen basically came from the client, consultant or contractor. Miscommunication between these three parties can cause the project is abandoned. Many problems may arise during construction project implementation; one main concern is delay. Delay is the time overrun either beyond completion date specified in a contract, or beyond the date that the parties agreed upon for delivery of a project.…

    • 1000 Words
    • 4 Pages
    Powerful Essays
  • Good Essays

    Nicmar

    • 1761 Words
    • 8 Pages

    ASSIGNMENT NICMAR / SODE OFFICE 1. PROGRAMME : GRADUATE PROGRAMME IN CONSTRUCTION PROJECT MANAGEMENT : : MODULE # 18…

    • 1761 Words
    • 8 Pages
    Good Essays
  • Satisfactory Essays

    Smart Tunnel

    • 474 Words
    • 2 Pages

    Construction of a bored tunnel along this length will be using NATM techniques. However, it would have been slow and costly and would in practice require systematic advance jet grouting from the surface. In order to ensure the SMART tunnel construction time is finish according to the timeline given and within the safety measure of the tunnel boring, therefore this length is reverted to tunnel boring machine (TBM) excavation.…

    • 474 Words
    • 2 Pages
    Satisfactory Essays

Related Topics