In this homework assignment, you will be working through four Activity In Box (AIB) problems. Using the activity, duration, and predecessor information given in this document, you should first construct a network for each "project." [Each problem will have its own network.]
Once you have constructed the network, please answer the corresponding questions. Once you answer the questions, please post your responses to the Drop Box. You do not have to submit your network diagrams, the answers to the questions are sufficient.
Once the homework assignment has been graded, the solution key will be made available. The network diagrams will be provided, along with the answers to the questions.
Good Luck!
Problem 1
The following data were obtained from a project to create a new portable electronic.
Activity Duration Predecessors
A 5 Days ---
B 6 Days ---
C 8 Days ---
D 4 Days A, B
E 3 Days C
F 5 Days D
G 5 Days E, F
H 9 Days D
I 12 Days G
Step 1: Construct a network diagram for the project.
Step 2: Answer the following questions: (15 points total)
a) What is the Scheduled Completion of the Project? (5 points)
32 Days
b) What is the Critical Path of the Project? (5 points)
The most critical path is B – D – F – G – I: 32 Days
c) What is the ES for Activity D? (1 points)
Day 6
d) What is the LS for Activity G? (1 points) Day 15
e) What is the EF for Activity B? (1 points) Day 6
f) What is the LF for Activity H? (1 points) Day 32
g) What is the float for Activity I? (1 points) There is no float period for