Management has been gathering the following data over the past four months:
The president has attended conferences at which the importance of throughput time, manufacturing cycle efficiency, and delivery cycle time were stressed, but no one at the company is sure how they are computed. The data to compute these measures have been gathered and appear below:
Month
1
2
3
4
Wait time per order before start of production, in days
16.7
15.2
12.3
9.6
Inspection time per unit, in days
0.1
0.3
0.6
0.8
Process time per unit, in days
0.6
0.6
0.6
0.6
Queue time per unit, in days
5.6
5.7
5.6
5.7
Move time per unit, in days
1.4
1.3
1.3
1.4
Required:
1. For each month, compute the following operating performance measures:
a. Throughput time.
b. Manufacturing cycle efficiency (MCE).
c. Delivery cycle time.
2. Using the performance measures given in the problem and those you computed in (1) above, do the following:
a. Identify areas where the company seems to be improving.
b. Identify areas where the company seems to be deteriorating or stagnating.
c. Explain why you think some specific areas are improving while others are not.
3. Refer to the move time, process time, and so forth, given above for month 4.
a. Assume that in month 5 the move time, process time, and so forth, are the same as for month 4, except that through the implementation of Lean Production, the company is able to completely eliminate the queue time during production. Compute the new throughput time and MCE.
b. Assume that in month 6 the move time, process time, and so forth, are the same as for month 4, except that the company is able to