Westband Construction (Change Orders) Construction Articlee
WESTBAND CONSTRUCTION LTD.
9910 39 Avenue
P.O. Box 2408
Edmonton, Alberta
T5J 2R4

October 27 - 2011

City of Edmonton
Drainage Branch

Dear Madam / Sir,

Request for Change Order:

Regarding to our meeting dated July 30, 1993; WestBan Construction Limited needs City’s approval for extra time and cost to precede with additional scope of the construction work (changing slope in North and East banks, adding required shoring for stabilizing the soil, leaving shoring in the ground, pouring tank concrete walls instead of shotcrete), according to the option B for both North and East Slopes (Attachment F2), the chosen schemes for slope remedies are attached in this document.

WestBan, due to the delays of City of Edmonton and UMA in providing requested services to this company, believed that the justifications in cost and schedule are necessary to complete the project within satisfactory quality.

WestBan is proposing extra CAD$72,500 and additional 28 days to the original project duration according to general conditions to the contract clauses 410.1, 404.3 and 404.4. It is noteworthy that the total amount of money requested is additional to the insurance of North and South slopes which stipulated in Attachment G Section 1.2 (Course of Construction Insurance). The detailed cost breakdown and the revised schedules are attached for references.

The revised milestone dates are as followed:
Completion of Storage Tank: 17-Sept-1993
Completion of Mech./Piping: 08-Oct-1993
Completion of Electrical/Control: 15-Oct-1993
Substation Completion: 12-Nov-1993

We appreciated your considerations regarding this change order.

Sincerely Yours,
Project Manager, WestBan Construction Limited.

The change order is requested to be issued according:

WestBan Construction Limited provided the City of Edmonton with work schedule, work plan, WBS and bulk excavation for reviewing on May 25, 1993 for evaluation. All documents

You May Also Find These Documents Helpful

  • Good Essays

    Pm 598 Week 2

    • 702 Words
    • 3 Pages

    All bids must be itemized along with Labor and Materials broken out. Working hours are from 7:00 AM to 7:00 PM, 7 days a week. Weekend work is not required however, if you are including weekend work in order to meet or beat the schedule please make note of it. All insurance information must be submitted with your bids confirming all of you workers compensation etc. is up to date. Additionally please submit your company’s safety…

    • 702 Words
    • 3 Pages
    Good Essays
  • Better Essays

    Midterm Comm293

    • 5099 Words
    • 21 Pages

    Part A Brigante Construction Ltd. entered into a contract on October 1, 2002 with the province of British Columbia to construct a multi-unit residential complex in Whistler. The contract price is fixed at $500 million and Brigante expects that the project will be complete by the end of 2005. Other information re: the contract is provided below. Brigante has a December 31st year-end. In $ millions Costs incurred (during the year) Estimated costs to complete at the end of the year 2002 $ 80 320 2003 $ 125 235 2004 $ 140 130 2005 $ 75 0…

    • 5099 Words
    • 21 Pages
    Better Essays
  • Good Essays

    accounting

    • 463 Words
    • 2 Pages

    Your staff people on the engagement report real frustration 挫折on this matter. They have concluded that the client cannot be successful in its rezoning efforts, and, therefore, they have suggested that the land be written down 减低帐面价值 to $15,000,000. The client has obviously objected, arguing that any such adjustment prejudges their ability to do their job.…

    • 463 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    busn 5060

    • 3073 Words
    • 13 Pages

    Guidelines for Minimum Standards in Water Well Construction, Province of British Columbia — June 1982. (n.d.). . Retrieved July 11, 2014, from http://www.env.gov.bc.ca/wsd/plan_protect_sustain/groundwater/library/standards/Guidelines_1982/standr1.html…

    • 3073 Words
    • 13 Pages
    Powerful Essays
  • Powerful Essays

    Where the amount is left blank, or “N/A” is inserted, the item is not to be provided as part of the tenancy.…

    • 914 Words
    • 16 Pages
    Powerful Essays
  • Satisfactory Essays

    Taxpayer Case

    • 756 Words
    • 4 Pages

    Question 1 There is a time table about John: DATE | ACTIVE | $ | PROPERTY | 01/03/1996 | Purchase | $100,000.00 | Burwood | 01/07/2011 | Purchase | $300,000.00 | Camberwell | 01/09/2011 | Declared this house to be his main residence | | Camberwell | 30/12/2011 | Post to New York, rent property | | Camberwell | 01/03/2012 | Sell | $175,000.00 | Burwood | 30/12/2016 | Back to Melbourne | | | 01/02/2017 | Sell | $500,000.00 | Camberwell | The CGT consequences of these events must process as follow: Property at Burwood Step 1 - has he made a capital gain or loss?…

    • 756 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    opma 317

    • 395 Words
    • 5 Pages

    Since two weeks were added to task #3 - Obtaining Final Drawings and Building Permits, in order to complete the project in the original normal time with minimal costs, he would crash activities #2, and #1 since these activities would reduce the project by two weeks’ time at a minimal cost of $7000 as shown by our project crashing…

    • 395 Words
    • 5 Pages
    Satisfactory Essays
  • Good Essays

    Jim Brown

    • 770 Words
    • 4 Pages

    The reasons that we propose this are because that this is the method that will save the company the most time. Not only does it save the company time, but if the company were to ever fall into trouble with labor union strikes, this plan is guaranteed to be the most cost effective when facing with the steep penalties of not meeting the time limit. In addition if everything goes very smoothly the company will finish the project 8 weeks earlier than expected and save money on overhead expenses.…

    • 770 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Northern Drilling case

    • 1152 Words
    • 5 Pages

    Through this project Northern (1) could be established as one of the Canada’s most technically competent drilling contractors, achieve its growth strategy, (2) diversify its income sources and decrease its dependency on its biggest client (Noranda), (3) strengthen its reputation which is important to win long-term complex projects in the future and (4) gain an additional minimum gross profit of over $6mln (see exhibit 3, scenario 2).…

    • 1152 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    Sea to Sky Highway Report

    • 2786 Words
    • 12 Pages

    This report examines, from a construction management point of view, the Sea to Sky Highway Improvements Project. The project was initiated in 2004 and completed in 2009. The impetus for the project was the awarding of the 2010 Winter Olympic Games being awarded to Vancouver/Whistler British Columbia in 2003.…

    • 2786 Words
    • 12 Pages
    Powerful Essays
  • Powerful Essays

    Max Lionel

    • 2861 Words
    • 26 Pages

    The justification and validity of the project needs to be confirmed before the project proceeds. This document is used to clarify the project purpose and justification and to gain approval to proceed to the next phase.…

    • 2861 Words
    • 26 Pages
    Powerful Essays
  • Good Essays

    James Tobin Research Paper

    • 16994 Words
    • 68 Pages

    unemployment in the US in the worst of the Depression in 1932‐33 and back up to 17% during the…

    • 16994 Words
    • 68 Pages
    Good Essays
  • Good Essays

    My job experience and qualifications allowed me to gain proper knowledge about construction inspection, quality control maintaining design standard, drawings and structural design. My time as a consulting engineer makes me an appropriate candidate for this position.…

    • 860 Words
    • 4 Pages
    Good Essays
  • Better Essays

    Building Automation

    • 2847 Words
    • 12 Pages

    DS, Danish Standard, DS 21906. P-Net, Multi-master, multi-net fieldbus for sensor, actuator and controller communications.…

    • 2847 Words
    • 12 Pages
    Better Essays
  • Powerful Essays

    In implementation of data's indicate that majority of the construction works suffered with an extended delay that lead to the major disputes lots of time and money, and the end user can not use the intended projects on the appropriate time. And in several instances the dalliance is not the intention for both the client and contractor as it does not help both, either in the performance or in the cash flow.…

    • 17613 Words
    • 71 Pages
    Powerful Essays

Related Topics