Work Method Statement
|Work Procedure No |WP |G |05 |

Work Procedure for Construction Formwork, Reinforcement, and Concreting

Scope:

Form work: This work shall consist of furnishing and fixing of form work (shuttering) of approved quality for cast-in-situ pre cast /pre-stressed plain and reinforced concrete with necessary props, staging centering scaffolding any temporary construction required for their support.

Reinforcement: This work shall consist of furnishing and placing of high yield strength deformed bars of the shape and dimensions as shown in approved drawings.

Concreting: This work shall consist of furnishing and placing of plane of reinforced concrete of all grades with 40 or 20mm down graded aggregates as defined in technical specification of contract, machine mixed and mechanically vibrated to the required level, slope, etc as per approved drawings

Reference:

MoSRT&H specifications and technical specifications of contract documents.

Plant /Machinery and Equipment:

|S No. |Plant / Equipment |Make /Model / Features |Nos. |
|1 |Transit Mixer |6 CUM. capacity |according to type and quantum of work and lead|
|2 |Concrete Pump / Boom Placer / Chute / |Suitable capacity and numbers, to be decided according to type and quantum of work |
| |Tremmie | |
|3 |Needle Vibrator |Suitable capacity |@ as suggested in point 6 of the ‘Procedure’ |
| | | |below |
|4 |Form Vibrator

You May Also Find These Documents Helpful

  • Powerful Essays

    A concrete organization has capability to become a big vendor to a lot of construction organizations. In this report you will see an account of the project of starting up a concrete organization, the development concept, the controlling methods, and what reports will be important to keeping an effective company. To achieve success a new company must be sure to stay up with all of the rivalry that's coming up.…

    • 2333 Words
    • 8 Pages
    Powerful Essays
  • Satisfactory Essays

    Rebar Work: is used to reinforce the foundations, its sizes, configuration and installation is carried out in accordance with architect technical design. The main components of rebar are steel bars, offset bends, stirrups, hairpins, dowels, corner bars, etc. This task involves lots of manual handling whilst moving the steel bars, long sitting or standing in awkward body position and repetitive hand movement in teams of wires snap tying and using hand pliers.…

    • 456 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Palmer Bird

    • 4419 Words
    • 17 Pages

    and masonry work on the exterior cladding of the building and hired an engineering firm,…

    • 4419 Words
    • 17 Pages
    Powerful Essays
  • Satisfactory Essays

    bubbaganoosh

    • 515 Words
    • 3 Pages

    Urban Constructions has several policies, procedures and practices in place to protect the client, suppliers, our staff and our contractors. Limitations placed upon our team can restrict the project to what it will produce. To make this subdivision successful, we must follow these procedures.…

    • 515 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    8 CONSULTANT’S PROPOSED DESIGN & CONSTRUCTION SCHEDULE ........................... 8 CONSULTANT DESIGN SCHEDULE ........................................................................................ 9 BID DOCUMENT CONSTRUCTION SCHEDULE…

    • 13739 Words
    • 88 Pages
    Powerful Essays
  • Good Essays

    Know how to comply with relevant legislation and official guidance when erecting structural carcassing components.…

    • 807 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Anzac Bridge

    • 342 Words
    • 2 Pages

    The materials that were used to construct this bridge consisted of prestressed concrete, steel casings, prestressed steel, reinforcing steel wire strands and polyethylene. It was built on each side of the land and was eventually connected together in the middle. It was constructed by using a formtraveller (a travelling formwork) and setting up the formwork before positioning and tensioning the cables. They then proceeded to place the reinforcement cement and pouring on the concrete. This was made in a cycle with each cycle being used to make…

    • 342 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    PROJ598

    • 2385 Words
    • 11 Pages

    This work shall deliver is facilities to include the construction of one baseball field that will accommodate a semi-pro baseball team, the construction of one clubhouse, and the construction of one parking area sized to hold 50 cars. A 20-acre parcel of land will be provided for the construction of these facilities, which has already been acquired. The contractor shall be responsible for the demolishing, clearing, removal, and disposal of existing buildings and trees. The site shall be evenly graded to drain away from the playing field. The Contractor shall erect a perimeter fence and security lighting. The Contractor shall be responsible to make utilities operational, to include power, water, and sewer. The Contractor shall be responsible for coordination with the utility companies. Refer to the detailed Description of Work, and Specifications and Drawings, in Sections 2.0 and 4.0, respectively, for details.…

    • 2385 Words
    • 11 Pages
    Powerful Essays
  • Powerful Essays

    Building Technology: Report

    • 8563 Words
    • 29 Pages

    9 Steel Framed..................................................................................................................................................... 9 Concrete Framed........................................................................................................................................ 12 Task 3 (P7) Explain environmental and legislative constraints............................. 13 Building Act 1984, HASAWA 1974, the code for sustainable homes.......................................13 Town and country planning, CDM.........................................................................................................14 Task 4 (P8) Explain the infrastructure that supports construction.............................................15 Scaffolding, Trench support systems, Forklift trucks, Dumper trucks...........................................16 Cement mixers, Excavators, Cranes, Small plant and tools................................................... 16 Supply of building materials, prefabricated component.....................................................…

    • 8563 Words
    • 29 Pages
    Powerful Essays
  • Powerful Essays

    Figure 4 View of the 3D physical model testing of the entrance configuration conducted in the wave basin at UNSW…

    • 2444 Words
    • 10 Pages
    Powerful Essays
  • Good Essays

    P6- Describe the techniques used to construct and finish the component elements of a superstructure.…

    • 1075 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Catapult Project

    • 1422 Words
    • 6 Pages

    A document on an existing catapult design (including sketches, dimensions, materials, Bill of Materials, and estimated build procedure) was to be created prior to construction This documentation was to then be used to replicate the existing design (original) using all the same parts and materials, within the documented specifications Individual documents were to be produced outlining the work undertaken Contraption was to be fabricated within the provided specifications:…

    • 1422 Words
    • 6 Pages
    Good Essays
  • Good Essays

    |2 |Civil Finishes :- A) B/W, Plaster & |) Micro Scheduling |1)If VFC drawings are not received in well in advance then|…

    • 505 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Construction and installation methods are identified which optimise the economical use of resources & meet statutory & contractual requirements Methods of construction: sequencing of work; organisation of resources (labour, plant, materials, finance); construction & installation techniques; temporary works…

    • 739 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    A steel frame situated around a building’s core or along exterior walls offers structural support. The frame’s columns, however, are free to rock up and down within steel shoes secured at the base.…

    • 3476 Words
    • 14 Pages
    Powerful Essays

Related Topics