I red lined plans showing the location of the proposed gas meters under the stairs and emailed them over to Nick M. for review.
Notes from today's conference call with the Team:
Schedule update Civil URA covering utility work? Update from Sarah? - Stormwater is covered - wet and dry underground utilities are not included - as per Robert. Everything will be submitted to Sfingi today Sarah will update and stamp - send out today/tomorrow. …show more content…
Quotes are all in - Zadok to compile, include letter, and send today Storage Unit Design Update - Structural engineer out of town this week - back next week.
Lighting submittals - Zadok received the selections - waiting on final CO request from Hedgehog and we'll process it. Siding - Pricing in - Zadok to compile and send in today Door submittals update - Coming today Steel drawings - came in last night - Nick reviewing, will send to MDA/Sfingi today Drywall subs - Pricing in, references contacted - Nick will compile and send off today
AgraTec - They finished up framing the exterior walls on Building B and started working on framing the interior walls. I assisted Kevin through out the day on layout and Structural design.
Grand Teton Concrete - Ryan showed up before the scheduled pour today and finished doweling in the shovel footing to the exterior walls, and also installed the rest of the expansion joint around the interior of the stem wall on Building A. Then his guys worked on the rest of the day pouring concrete and finishing the
floor.