Code for Course: Assignment Number: Student number: Group Code Number:
MBL405-5 02 750-163-3 BOT1000
MBL 405-5
Student No: 750-163-3
Table of Contents
Question 1: Construct the nine elements of the plan identified................................................. 4 i. ii. iii. iv. v. Statement of Objectives.................................................................................................. 4 Work Breakdown Structure............................................................................................. 5 An activity on node (PERT) network ........................................................................... 6 A determination of the critical path(s) and the duration along the path. ..................... 7 An activity list, early-start schedule, slack list and master schedule. Assume every
activity begins at its early start, regardless of resource constraints. ..................................... 8 vi. A period labor requirements table for each group and the project as a whole. Include
bar graphs to illustrate the labour load. ................................................................................. 9 vii. A cumulative labour requirements table table for each group and the project as a
whole. Include line graphs to illustrate the cumulative loads............................................... 12 viii. A schedule based on the leveling of labour requirements that could be achieved
without lengthening project duration by more than 14% in calendar days. ......................... 15 ix. A cash flow requirement graph for the project when leveled, assuming that charges
are uniformly distributed throughout the activity .................................................................. 17 Question 2: Analyze the plan for potential problems............................................................... 19 Question 4: