Preview

D.U Singer Hospital

Good Essays
Open Document
Open Document
5200 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
D.U Singer Hospital
Project Planning, Scheduling and Control: Assignment 2 D. U. Singer Hospital Products Corp.

Code for Course: Assignment Number: Student number: Group Code Number:

MBL405-5 02 750-163-3 BOT1000

MBL 405-5

Student No: 750-163-3

Table of Contents
Question 1: Construct the nine elements of the plan identified................................................. 4 i. ii. iii. iv. v. Statement of Objectives.................................................................................................. 4 Work Breakdown Structure............................................................................................. 5 An activity on node (PERT) network ........................................................................... 6 A determination of the critical path(s) and the duration along the path. ..................... 7 An activity list, early-start schedule, slack list and master schedule. Assume every

activity begins at its early start, regardless of resource constraints. ..................................... 8 vi. A period labor requirements table for each group and the project as a whole. Include

bar graphs to illustrate the labour load. ................................................................................. 9 vii. A cumulative labour requirements table table for each group and the project as a

whole. Include line graphs to illustrate the cumulative loads............................................... 12 viii. A schedule based on the leveling of labour requirements that could be achieved

without lengthening project duration by more than 14% in calendar days. ......................... 15 ix. A cash flow requirement graph for the project when leveled, assuming that charges

are uniformly distributed throughout the activity .................................................................. 17 Question 2: Analyze the plan for potential problems............................................................... 19 Question 4:

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Step 1: Construct a network diagram for the project. (NOTE: EF for activity H should be 19)…

    • 552 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Proj586

    • 1206 Words
    • 5 Pages

    I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) 30 days b) Identify the critical path (6 points) BCDFH = 30 Days c) What is the slack time (float) for activity A? (1 points)…

    • 1206 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Pm 592 Week 1

    • 340 Words
    • 2 Pages

    Below is a graphic representation of the detailed Work Breakdown Structure to facilitate the project on hand:…

    • 340 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) b) Identify the critical path (6 points) c)…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    12) Refer to Figure 22-1. Technological change is illustrated in the per-worker production function in the figure above by a movement from…

    • 1248 Words
    • 5 Pages
    Satisfactory Essays
  • Powerful Essays

    Economics 101

    • 1678 Words
    • 4 Pages

    6. Give the table below, which statement is true. Labour hours needed to produce a unit of…

    • 1678 Words
    • 4 Pages
    Powerful Essays
  • Satisfactory Essays

    Aib Problem Solution

    • 608 Words
    • 3 Pages

    Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project? (2 points) 32 -> CORRECT b) What is the Critical Path of the Project? (3 points)…

    • 608 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    If the bakery currently makes 1500 loaves per month with a labor productivity of 2.344 loaves per labor hour, then Lackey will need to add _______ worker(s) to meet the increased demand. (2-points)…

    • 647 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The firm only has one “rational” stage of production where the two lines (AP & MP) intersect at the point where average product is at its maximum. Using the table listed above with the graphs it shows that the rational stage of production would be at 10 labour units.…

    • 455 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    BTC case analysis

    • 1576 Words
    • 7 Pages

    Production: 3% of net variance in material, labour, variable overhead, labour rate variance, and the variable and…

    • 1576 Words
    • 7 Pages
    Powerful Essays
  • Good Essays

    Direct Labour

    • 844 Words
    • 4 Pages

    The company’s plant has a capacity of 130,000 direct labor-hours per year on a single-shift basis. The company’s present employees and equipment can produce all five products.…

    • 844 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Labour |Total Product |Marginal Product |Fixed Cost |Variable Cost |Total Cost |Marginal Cost | |0 |0 | ___ |800 |0 |800 | _______ | |1 |60 |60 |800 |160 |960 |160 | |2 |180 |120 |800 |300 |1100 |140 | |3 |260 |80 |800 |450 |1250 |150 | |4 |230 |-30 |800 |575 |1375 |125 |…

    • 683 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    By using the same concept above we can determine the present value of Gold Mine.…

    • 1099 Words
    • 5 Pages
    Good Essays
  • Good Essays

    assigment 3

    • 558 Words
    • 3 Pages

    For this assignment, using the situation given below, apply the S.W.O.T. Situational Planning Strategy which was described in Chapters 4 and 7 of your course text:…

    • 558 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Pm 592 Week 2

    • 1092 Words
    • 5 Pages

    Note: For this problem, only items 5 and 6 are considered "labor" for the purpose of calculating items 8 and 9.…

    • 1092 Words
    • 5 Pages
    Good Essays