MRP and LP solver
Part 1
Using material requirements planning (MRP) manages production of the motor drive assembly. Using MS Excel solver for the optimization of aggregate production plan
1. Introduction
Material Requirements Planning (MRP) manages production planning and inventory for manufacturing. An MRP system can be used to ensure the availability of materials and products for production and customers, to maintain the lowest possible level of inventory, and to plan manufacturing activities, delivery schedules and purchasing activities.
2. Lab assignments
Week 10 (Oct 28):
- Using the product structure and bill of materials (BOM) of the motor drive assembly used in Project 1, including motor drive assembly, subassembly, and components.
The subassembly includes pneumatic shifting mechanism in TKF02M16A_ASM2, transmission in
TKF02M16A_ASM3,
dual motor assembly in TKF02M16A_ASM4, and output shaft in TKF02M16A_ASM1.
- It is assumed that the motor drive assembly will be delivered to the customer for weeks 9, 10, 11, 13, and 14, the corresponding units are 10, 20, 15, 20 and 25, respectively. The on-hand inventory, the scheduled receipts and the lead time for each item are shown in the following table.
- Develop the MRP order release plan for final assembly, four subassemblies and six components 27, 112, 119, 1, 4, and 120.
Items
Motor drive assembly
Lead time
(week)
3
On hand inventory
(unit)
20
Scheduled receipts (unit) no All 4 subassemblies
2
10
15 at week 2, 3
All components
1
20
20 at week 2
-
You may use the following format:
Motor drive: lead time 3 weeks
1
Gross requirement on-hand inventory
(20)
scheduled receipts net requirements planned order release subassembly: lead time 2
1
2
3
4
5
6
7
8
9
10
10
20
11
15
12
13
20
14
25
2
3
4
5
6
7
8
9
10
11
12
13
14
1
weeks
Gross requirement on-hand inventory
(10)
scheduled receipts
15
net requirements planned order release
Component: lead time 1 weeks
1
Gross requirement on-hand inventory (20) scheduled receipts net requirements planned order release
15
2
3
4
5
6
7
8
9
10
11
12
13
14
20
3. Outcomes to hand in
Assignment No
Type
Mark
Description
A6
Report
3
MRP
4. Report Contents
A6 Week 10 (Due: Nov. 4):
1. The product structure and BOM.
2. MRP results for the assembly, 4 subassemblies, and 6 given components.
3. If an item is required in two subassemblies of a product, discuss how to make MRP plan for such common-use items.
4. What is the objectives of integrated manufacturing planning and control systems?
5. Discuss major elements of a manufacturing planning and control system (MPCS).
2
You May Also Find These Documents Helpful
-
ACI delivers the two components of the assembly line system on September 20, 2010, and agrees to deliver the packaging segment to EMI by December 20, 2010. The delivery date for the packaging segment is delayed because ACI does not have that component on hand at the time the sales agreement is entered into. As such, ACI has to manufacture that component. Because of the backlog of orders ACI has in its manufacturing department at the time it enters into the sales agreement with EMI, it cannot commit to delivering the packaging segment to EMI until December 20, 2010. ACI actually delivers the packaging segment on December 15, 2010, and agrees to install the complete assembly line system at EMI’s Pilsen facility on January 5, 2011. ACI cannot install it sooner because its installation technicians are either otherwise committed to other customer installation orders or on vacation for…
- 838 Words
- 4 Pages
Good Essays -
Parts are purchased by buyers in the China Plant’s purchasing department from a local Chinese company. While this company attempts to maintain adequate quantities of electric motors in stock to meet all its order requirements, its on-time deliveries over the past year have averaged only 93%.…
- 471 Words
- 2 Pages
Satisfactory Essays -
Team D Final Project Assign Learning Teams Team D Charter Team D Cerificate of Originality Create Project Plan Team D approve Project Plan Team D Submit Project Plan Paper for Memory Management (Linux, MAC, Windows) Paper for Process Management (Linux, MAC, Windows) Paper for File Management (Linux, MAC, Windows) Paper for Security Management (Linux, MAC, Windows Team D review WK 3 Assignment. Team D submit First Rough Draft of Final Paper. Proceed?…
- 870 Words
- 4 Pages
Satisfactory Essays -
In other words, the development stage provides a foundation for the selected product as it will be built as a prototype to be later sold to the public in order to increase sales and profits.…
- 7258 Words
- 20 Pages
Powerful Essays -
From week 3 to week 13, your grade for each of these activities will form part of your final grade. There…
- 4385 Words
- 18 Pages
Powerful Essays -
Ringo overdub drums in Abbey Road studio. “I, Me, My” He is the last Beatle to play at a Beatles recording session…
- 507 Words
- 3 Pages
Satisfactory Essays -
Problem tree analysis is a key to many kinds of project planning. Problem tree analysis helps to find solutions by mapping out the anatomy of cause and effect around an issue but with more structure. The problem can be broken down into manageable pieces which allow clearer views on priorities and stronger focuses on objectives in planning. It is often the first step in win-win solutions.…
- 632 Words
- 3 Pages
Satisfactory Essays -
1) From the interaction does it seem to you that Alan is actively listening? Why or Why not? It does not seem that Alan is actively listening at all. He may be hearing the voices of his employees but he is not listening to them as they answer the questions that he has asked. He is also not mindful in his interactions with his employees. He is scribbling notes, shaking his head, constantly frowning and does not give the person he is talking to direct eye contact when speaking to them. Finally, Alan is not responding appropriately to what his employees are saying. He is not showing through his words or actions that he cares nor is interested in engaging them in further conversation.…
- 855 Words
- 4 Pages
Good Essays -
Weekly readings are indicated on the course schedule. They are all from the course textbook.…
- 652 Words
- 3 Pages
Satisfactory Essays -
3) Week3 (Note: This week is based on Recent articles so view this as a template):…
- 563 Words
- 3 Pages
Powerful Essays -
Weeks #5 and #6 / Monday, February 18 – Friday, March 1 / Session 4…
- 901 Words
- 4 Pages
Satisfactory Essays -
* Is responsible for starting the assembly process and for the initial accuracy of the order.…
- 1968 Words
- 8 Pages
Powerful Essays -
To deliver to the company a completely operational 25,000 square foot manufacturing and distribution facility. To install all plant equipment and complete testing to ensure that all plant equipment is working to specifications. To complete an extensive walk-through one week prior to sign off by production management.…
- 839 Words
- 4 Pages
Powerful Essays -
Assessment will be handed out on week 1 and should be completed /submitted by week 4.…
- 2022 Words
- 9 Pages
Powerful Essays -
14. During which weeks of the course will you be expected to complete an intelliPath unit?…
- 331 Words
- 3 Pages
Satisfactory Essays