Preview

Project Manager Status Report

Satisfactory Essays
Open Document
Open Document
899 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Project Manager Status Report
Project Status Report Template
This Weekly Project Status Report Template is free for you to copy and use on your course project.
Project Status Report
Project Title: ___________________
Week ending: ____________________

Project Status Summary Percent Complete: ___% (approximate)

Scope
Schedule
Cost
Risks
Quality

Provide a quick executive overview of the status of the project in this section It is intended for high level management so it should not get too much into the details of the project. However, it should highlight anything specific, which should be brought to their attention. The Scope/Schedule/Cost/Quality table above is a quick way to present a color coded dashboard for the status report. Typically a variance of +/- 5% will warrant a yellow cautionary color and +/- 10% will warrant a red warning color. For a project which needs tighter control +/- 2% and +/- 5% are used for these thresholds; whereas, other projects with less strict control may use 10% and 20% variances. The percent complete here should be the percent completion of the entire project. For any constraint which is yellow or red this section should contain brief explanation the reason why.

Example:
The project schedule is 7% behind schedule due to inclement weather which has affected the installation of the fiber optics throughout the campus. This should not affect the project completion date as crews are planning to make up the time by working weekends and extended hours next month.

The project risks is red due to the inclement weather and servers which were delivered last month weren't configured with the correct hardware specifications. The impact of the inclement weather on the schedule will be mitigated by having crews make up the time by working weekends and extended hours next month. Currently we are working with the server vendor to resolve the server hardware configuration problem. The configuration delivered will not handle the work load of

You May Also Find These Documents Helpful

  • Powerful Essays

    PROJ 592

    • 2367 Words
    • 10 Pages

    An Earned Value analysis reflected that the project is currently behind schedule. The schedule variance (SV) indicated a negative $565,226.34 and the scheduled performance index showed as .69. When SV is a negative number and SPI less than one, this indicates the project is behind schedule. After calculating the CPI/SPI value (1/.69= 1.45), any values above 1.3 should be investigated immediately, because those numbers are much too good to be true. In addition based on the Work Breakdown Structure the total duration was 6 days behind schedule. The new completion date in the WBS also indicates that the schedule completion date currently is 10days behind schedule.…

    • 2367 Words
    • 10 Pages
    Powerful Essays
  • Satisfactory Essays

    Ilab Week7

    • 297 Words
    • 2 Pages

    According to the Project summary, this project is currently on schedule. The project summary is currently indicating that the project is coming in under budget by $1,720.00.…

    • 297 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Is3110 Week2 Assignment

    • 348 Words
    • 2 Pages

    in terms of bandwidth and storage. Your company has never traded with the U.S. Government at this…

    • 348 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Huntsville Plant

    • 654 Words
    • 3 Pages

    The Huntsville Plant Project will be ready by the June 30, 2012 deadline set by the board of directors because the Project has covered all of the areas necessary in its planning. Huntsville has identified the team that they are going to use for the project. They have been informed with the details of the task that are required of them. The company’s team has an idea of what they must do to keep the project on track. The schedule coordinates the activities with the resources that are readily available to the Project Manager. There is a sequence, in which the task that is highlighted must be completed before another assigned task is started.…

    • 654 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Due to recent budget cuts affecting the Modell Charter School, the board has chosen to reduce the funds from the existing Enterprise Resource Planning System (ERP) project. The decision was made to purchase a less expensive software package then the original one selected for the project. One of the main purposes the original ERP system the school wanted to install was to integrate the human resource, payroll and finance systems together. This integration was going to help streamline the day to day processes and assist in making information more accountable. By…

    • 13779 Words
    • 56 Pages
    Powerful Essays
  • Powerful Essays

    Pm592 Course Project 2

    • 3890 Words
    • 16 Pages

    After entering the data and setting the project to 40% completion, we noticed that the project is behind schedule. This was apparent by the Schedule Variance and the SPI (Schedule Performance Index). The Schedule Variance for the project is ($570,977.84) with a Schedule Variance Percentage of -35%. We also noticed that…

    • 3890 Words
    • 16 Pages
    Powerful Essays
  • Satisfactory Essays

    JDT@ task 1A

    • 625 Words
    • 2 Pages

    Gannt Chart and/orWBS Create a gannt chart and list all the projects, the estimated time to completion as well as estimated cost. List each part of the project and give it a time line on the chart. Using this you can track it daily, weekly, monthly, or whenever you wish. Could also use a WBS to breakdown the projects and put a time line on each part of the project to show how each team member worked on it. Using this will show you how close you can get to being finished by year end as the case study states it was finished 6 months early.…

    • 625 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Review the list of reasons why plans fail as described in Ch. 11 of Project Management. Which of these reasons applies to defining and sequencing activities? As a project manager, what steps may you take to prevent your plan from failing?…

    • 335 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    The Work Breakdown Structure (WBS) contains the different activities within a project. Every activity necessitates outputs from several experts following different measures and timelines. The total of these activities represent the end deliverable. In order to control the task effectively the project supervisor must track the logical order of the various parts. He must visualize the final project deliverable. Views regarding project management, benefits and restrictions, bottlenecks, changes to risk or time in a crisis, and four points touched.…

    • 1092 Words
    • 5 Pages
    Better Essays
  • Good Essays

    Blue Zuma Part 2

    • 310 Words
    • 2 Pages

    Once the changes are in place, the duration of the project has been reduced from 290 days to 274 days. This improvement has reduced the overall length of the project, thus allowing the deadline set by the Mr. Lane (President). We are confident we can now complete the project by January 27.…

    • 310 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    The critical activities are B, C, E, F, H, J and K. The project should be completed (earliest finish) in 43 weeks - therefore R.C. Coleman’s 40 week completion time cannot be achieved. The probability of R.C. Coleman meeting the 40 week deadline is ~10%. This is a low chance, so they should be cautioned if they make 40 weeks their deadline.…

    • 656 Words
    • 3 Pages
    Powerful Essays
  • Good Essays

    Zuma Project

    • 1253 Words
    • 6 Pages

    If the project is resource constrained, then the finish date will be 2/18/09, since there was an additional 40 days added to the project duration. Additional personnel should be added in order to meet the desired new deadline.…

    • 1253 Words
    • 6 Pages
    Good Essays
  • Satisfactory Essays

    In many studies and reports, project successes tend to be measured against the prescribed schedule, cost and performance. In reality, project success measurement should be against projects constraints and the operational readiness status of the business environment. The combination of the two will assist in efficiently using the product or service as intended.…

    • 683 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    The estimated project completion date is TUE 11/13/13 with duration of 127 days. After leveling and re-allocating work along the project line, the project got delayed for 3 days so that the completion day moved up to FRI 11/21/13 (total duration of 130 days). (MS Project 2007)…

    • 613 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Overall decision making and schedule completion were the successes of this project. Decision making based on project management development, resource allocation, communication styles and team dynamics were highlights of the ultimate scores. The project was completed after the optimum deadline, although not totally out of the window of opportunity.…

    • 1509 Words
    • 7 Pages
    Good Essays

Related Topics