Basic Project Data
•
•
•
•
Project duration is 123 days.
The work scheduled is 2,693 hours.
The cost for personnel is $173,329.43.
The project contains 55 tasks.
Cash Flow
This cash flow report indicates the baseline plan for spending on labor resources.
Task Usage
This task usage report depicts the number of hours, start times, and finish times for each task
(and for each resource assigned to the task).
•
Inventory tasks are front-loaded to have the task complete as soon as possible.
•
Report times are back-loaded to plan the time for the report to be completed and ensure availability of resources.
•
Due to resource leveling with a resource constraint, some tasks are started, then paused, then finished at a later date to ensure that the project is not delayed by a second task to which the resource is assigned.
Table 1: Resource Usage for Each Work Package and Task
Task
Number
1
2
3
4
5
6
7
8
9
10
11
12
13
Task Name
Computer inventory and requirements
Inventory computers in use by new telecommuters
Elizabeth
Marcel
Determine requirements to use current computers
Marcel
Identify computers for upgrade
Marcel
Determine requirements for technology
Elizabeth
Clemencia
Report outcomes for inventory and requirements
Elizabeth
Marcel
Clemencia
Technical support
Determine technical support needed
Hugh
Jackson
Identify staff requirements
Hugh
Jackson
Report technical support needs and staff requirements
Hugh
Jackson
Computing support
Identify required computer support relative to inventory
Kimberly
Lianne
Identify staff requirements
Hugh
Lianne
Work
Duration
Start
Finish
340 hrs
140 hrs
70 hrs
70 hrs
60 hrs
60 hrs
40 hrs
40 hrs
60 hrs
40 hrs
20 hrs
40 hrs
11.43 hrs
22.85 hrs
5.72 hrs
200 hrs
120 hrs
60 hrs
60 hrs
40 hrs
20 hrs
20 hrs
40 hrs
20 hrs
20 hrs
210 hrs
120 hrs
60 hrs
60 hrs
50 hrs
20 hrs
45.18