BCGBC4003A/CPCCBC4003A Assignment 1 Part 1 1. Outline four areas within the above clause that could be identified as being unbalanced and give reasons why. I. The contractor gives the Superintendent‚ within 5 business days of when the Contractor should reasonably have become aware of that causation occurring‚ a written claim for an EOT evidencing the facts of causation and of the delay to WUC and any (Milestones). The reason for this being unbalanced is that 5 business days is too short of