Huntsville Plant Organizational Structure Keller Graduate School of Management The organizational structure is basically the system that a company develops to organize itself it determines who is in charge of what. There are different types of structures. The main structures are the Functional structure‚ the Autonomous structure‚ and the matrix structure. Each structure has advantages and disadvantages; each company needs to make a decision on what type of structure
Premium Organization Structure Management
Project Name | Huntsville Plant Project | Project Number | 005 | Project Manager | David Myers | Prioritization | High | Owner(s) | Walter Seitz | Start Date: | April 17‚ 2011 | Scheduled Completion Date: | June 30‚ 2012 | Mission | The construction of a new Seitz plant in Huntsville‚ AL that will be operational by June 30‚ 2012. | | Scope | 1) Select resources such as architect‚ real estate consultant and general contractor. 2) Recruit and train managers for the new plant
Premium Project management Construction Management
Huntsville Plant Project [PM586 Project Management Systems – Project –I] 06/02/2010 Keller Graduate School of Management Table of Contents Contents Table of Contents 2 Essay 1 Project Communication Plan 3 Essay 2 Risk Management Plan 5 Appendix 8 Project charter 8 Mission 8 Scope 8 Objectives 9 Assumptions 9 Constraints 9 Time/Decision Points 10 Cost/Financial Assumptions 10 User Acceptance Criteria/Quality 11 Project Scope Statement
Premium Project management
Karen Brown PROJ586 Huntsville Project November Term Week Three Question #1 Estimated Completion Time of Project According to the requirements that we have set for this project we will not be able to complete it by the expected date of November 2013. With the amount of resources that we need to complete the project our new projected end date is January 30‚ 2014. There are a few options that we can take to reduce the amount of time needed to complete this project by the proposed date
Premium Project management Construction
Huntsville Plant Project Activities Schedule Analysis With the current estimates for activity durations and dependencies of some activities on others‚ the earliest that the Huntsville Project can be finished is July 7‚ 2012 – 1 week late of the desired schedule. However‚ it should not be a big problem to fit these activities in the desired schedule as 1 week delay is relatively small compared to the total project duration of 66 weeks. The following activities are on the critical path (Gido‚ Celements
Premium Critical path method Construction Resource allocation
The Huntsville Plant Project will be ready by the June 30‚ 2012 deadline set by the board of directors because the Project has covered all of the areas necessary in its planning. Huntsville has identified the team that they are going to use for the project. They have been informed with the details of the task that are required of them. The company’s team has an idea of what they must do to keep the project on track. The schedule coordinates the activities with the resources that are readily available
Premium Project management
Huntsville Project Construction of a New Plant Jamie Alvarez kajafla@hotmail.com Project Management Systems November‚ 2011 Senior Faculty: Donald George Project Name | NEW PLANT IN HUNTSVILLE SEITZ CORPORATION | Project Number | 1 | Project Manager | JAMIE ALVAREZ | Prioritization | 1 | Owner(s) | WALTER SEITZ | Start Date: | APRIL 17 2011 | Scheduled Completion Date: | JUNE 30 2012 | Mission | | In January 2010‚ the board of directors of SEITZ
Premium Project management Construction
This project was performed to determine how different concentrations of salt water effect plants. The test that will be performed will prove which concentration will have the worst effect. The hypothesis is that by measuring the plants growth each day‚ the largest concentration of salt will harm the plants the most. First‚ the plants were purchased and the water was prepared with the salt concentrations. Second‚ the plants were watered each day with the different concentrations of salt. Third‚ the
Premium Water Test method Measurement
HUNTSVILLE PROJECT TEAM MEETING As the Huntsville project manager to effectively coordinate and host a progress meeting with team members. There are three things that must be accomplished: meeting objectives; use the minimum amount of time; and participants should leave with a sense of direction and effectiveness in the meeting process. With these criteria in mind‚ the process of structuring‚ planning‚ preparation‚ and execution of the Project Progress Team Meeting will be a definite success
Premium Project management Team
Primary project management organizational structures A project organization is a structure that facilitates the coordination and implementation of project activities. Its main reason is to create an environment that fosters interactions among the team members with a minimum amount of disruptions‚ overlaps and conflict (pm4dev‚ 2007).Selecting the organization structure is one of the most important points to start any project. On the basis of unique characteristics of the project‚ each project structure
Premium Project management Organization