20092811 Kristen’s Cookie Company 1. In order to find the time for filling a rush order‚ we just need to sum up the amounts of time needed for each task: 6+2+1+9+5+2+1 = 26 min 2. If we can prepare one order in 26 minutes‚ it does not mean that it will take 52 minutes to prepare 2 orders. We can start preparing next order while the first one is in process. 26 min 10 min 10 min If we assume that one order contains 1 dozen
Premium Baking Costs Variable cost
Case Report: Kristen’s Cookie Company Do Tra My – Section 24 1. Process Analysis: The flow chart is included in the Appendix Task Order Entry Wash+Mix Spooning Setting Baking Cooling Packing Accepting Payment Total Resource None You You Roommate + Oven Oven None Roommate Roommate Cycle Time (mins/dozen) 0 6 2 1 9 5 2 1 26 Capacity (dozens/hour) Infinity 10x3=30 30 60 6.67 12 30 60 Flow Time (mins) 6 2 1 9 5 2 1 26 Table 1: Process Analysis Assumptions: Order is for a full box (a dozen cookies)
Premium Rate equation Time Flowchart
Kristen’s Cookie Company Here is the Process Flow Diagram: The whole process throughput time of making a dozen of cookies is 26 minutes. It takes washing‚ mixing and spooning 8 minutes to make a dozen of cookies. And preparation and bake time totally are 10 minutes. The final step of cooling‚ packing and accepting payment of cookies takes roommate 8 minutes to finish the cycle. Assume the night capacity is 4 hours‚ so Kristen and roommate have 240 minutes operating time. Since the oven only
Premium Mix Baking Wage
5. Yes. If Kristen and roommate can only do their own job‚ the max order(order by order) they can process is 8 orders a night. But if they can cross-training‚ would 1. Receive order print and reply Roommate 1 minute/order Mix ingredients Kristen 6 minutes /max 3trays Spooning cookies onto tray Kristen 2 minutes/tray Cookies in oven Roommate 10 minutes/tray Cool down cookies
Premium Salary HTTP cookie Wage
Case: KRISTEN’S COOKIE COMPANY The case described about Kristen’s cookie company which provide freshly made cookies with variety of ingredients available to add to the cookies. The company is established in the on campus apartment. The cookies are made by 2 people‚ using a standard dough mixing equipment‚ tray and the apartment oven. Below is the explanation and evaluation of the preliminary process design in making and selling the cookies to the customers. Kristen’s cookie company promises that the
Premium Baking Mathematics
Question 1 Rush order takes the least possible time for preparing the dozen of cookies. The following is a detailed summary of time used to prepare the rush order: Activity Time Wash the bowl‚ add and mix ingredients 6 minutes Dish up the tray (1 dozen) 2 minutes Put the cookies in the oven‚ start timer 1 minute Bake the cookies 9 minutes Remove the tray from the oven* 0 minute Let the cookies cool 5 minutes Pack the cookies 2 minutes Accept payment 1 minute Total time: 26 minutes
Premium Baking The Time Girl
MGMT 571 Kristen’s Cookie - Case Assignment Dr. Yunus Kathawala Students Name : Mohammed Jomah Al-Shami – GUST1301102033 Yasser Sheikh Amin - GUST1301102045 Hellal Abdulwahab AlHellall - GUST1301102047 Gulf University For Science & Technology The Kirsten’s Cookies Company is new business established and located at the campus‚ with motivation toward fulfill to power-hungry learners at night time. The company would allow the learners to order customized cookies baked fresh under
Premium Marketing Process management Baking
case analysis yields the following points 1. The time taken to fill rush order will depend on whether there are any orders that are being processed currently or not. Accordingly we will have two scenarios a). No order is being processed when the rush order is received. The time in this case will be equal to the sum of the time required for all the processes. Time = 6 + 2 + 1 + 9 + 5 + 2 + 1 = 26minute b). An order is being processed when the rush order is received. In the worst case‚ the cookies will
Premium Baking English-language films Prince
Kristen’s Cookie Company – INDIVIDUAL WORK 2/8/12 MGT 6400 – Management of Business Processes and Operations Dr. Grady S. York 1.Assuming you have only one order‚ how long will it take you to fill the order? Based on the flowchart from the group analysis‚ it will take 26 minutes to fill one order. I came to this conclusion based on the number of minutes it takes to clean equipment and mix the dough (6)‚ scoop dough into tray (2)‚ pre-heat oven and set timer (1)‚ baking time (9)‚ cooling
Premium Flowchart Baking Rate equation
EINGB333 LAMBION Amaury Case report: Kristen’s Cookie Company Question 1 Total= 26 minutes (6+2+1+1+2+5+9) Question 2 The time we need for the first dozen of cookies is 26 minutes (see question 1). But the next orders only take 10 minutes. We can explain that by the fact that first we are obliged to do the whole operation. Then the mixing(6min) and the dishing(2min) can be done will an other dozen is baking (10 minutes). In the same reasoning cooking‚ baking and paying can be done when another
Premium Cooking Baking The Work