Week Three Homework: AIB Problem PROJ586 Project Management Systems Problem 1 The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A‚ B E 3 Days C F 5 Days D G 5 Days E‚ F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of
Premium Critical path method Project management
Before starting this homework assignment‚ please review the AIB simulation in this week’s Lecture. This simulation will provide you with an understanding of how to create a network diagram‚ and how to do a forward and backward pass to determine the ES‚ LS‚ EF‚ LF and slack (float). You will also learn how to determine the duration of the project‚ and the critical path. In this homework assignment‚ you will be working through four Activity In Box (AIB) problems. Using the activity‚ duration‚ and
Premium Critical path method Diagram
Problem 1 The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A‚ B E 3 Days C F 5 Days D G 5 Days E‚ F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project? (5 points) b) What is the Critical Path of the Project
Premium Critical path method
New plant in Huntsville‚ Alabama Project Risk‚ Communication Plan & Documentation Name: Olatunbosun Osuro Instructor: Gloria Durham PM 586 Project management systems Email: bosun.opere@gmail.com Phone: 612-220-0454 Project Communication Plan Project communication plan defines the generation and distribution of a project documents among project stakeholders throughout the project (Clements‚ 2009). Project communication plan will allow stakeholders to have a medium of sharing information
Premium Project management Management
THE AIB STYLE GUIDE ©Australian Institute of Business . V2Mar11 – CD:2011:10ed 0 Contents HOW TO USE THIS DOCUMENT ......................................................................................... 2 SECTION 1 - REFERENCING ................................................................................................ 2 Importance of Citing and Referencing ................................................................................... 2 AIB’s Preferred Referencing System
Premium Citation Reference
Problem 1 The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A‚ B E 3 Days C F 5 Days D G 5 Days E‚ F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project. (NOTE: EF for activity H should be 19) Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project? (5 points) Answer: 32 days b) What is
Premium Critical path method English-language films
1st question When does a project use the critical path? A project uses the critical path when you are starting to build the projects network diagram. Critical Path is the path of activities that all have a slack or float of 0. This process is very important because if any of the projects critical path gets completed later than schedule than the project might not be completed on time. Can there be more than one critical path in a given project schedule? Why or why not? Yes a project
Premium Project management Critical path method
Aib Homework Wk3 Problem 1 The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A‚ B E 3 Days C F 5 Days D G 5 Days E‚ F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project? (2 points) 32 -> CORRECT b) What is the Critical Path of the Project
Premium Critical path method Project management
THE AIB EXAM GUIDE July 2011 ©Australian Institute of Business 1 V3-1July2011 GUIDE TO EXAMINATIONS This guide has two parts: Preparing for exams Taking exams It has an appendix with an example exam answer with comments about why it was so good. PREPARING FOR EXAMS Make sure you have noted the correct date‚ time‚ duration and place for the exam. Start a revision schedule for the exam several weeks beforehand – many rehearsals is a key to success and if you have not planned
Premium Pricing
Before starting this homework assignment‚ please review the AIB simulation in this week’s Lecture. This simulation will provide you with an understanding of how to create a network diagram‚ and how to do a forward and backward pass to determine the ES‚ LS‚ EF‚ LF and slack (float). You will also learn how to determine the duration of the project‚ and the critical path. In this homework assignment‚ you will be working through four Activity In Box (AIB) problems. Using the activity‚ duration‚ and
Premium Critical path method Project management