Chapter 6 Resource Utilization
TRUE/FALSE
Resource-limited scheduling will not extend the project completion time if necessary in order to keep within the resource limits. ANS: F Feedback Correct Resource-limited scheduling will extend the project completion time if necessary in order to keep within the resource limits. Incorrect Resource-limited scheduling will extend the project completion time if necessary in order to keep within the resource limits. PTS:1 DIF: M OBJ: 4. Discuss resource-limited scheduling. KEY: Comprehension
MULTIPLE CHOICE 1. The statement, "Network diagrams illustrate the technical constraints among activities," means the activities are constrained because a. each of the activities are independent from the c. the activities use different resources to be other activities. completed. b. one activity cannot be started until the d. some activities use the same resources that may predecessors are finished. not be available. ANS: B Feedback A Network diagrams illustrate the technical constraints among activities because one activity cannot be started until the predecessors are finished. B Network diagrams illustrate the technical constraints among activities because one activity cannot be started until the predecessors are finished. C Network diagrams illustrate the technical constraints among activities because one activity cannot be started until the predecessors are finished. D Network diagrams illustrate the technical constraints among activities because one activity cannot be started until the predecessors are finished. PTS:1 DIF: M OBJ:1. Create a network