Preview

Cost Variance

Good Essays
Open Document
Open Document
660 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Cost Variance
(EVM) will be used to perform the measuring and controlling of the project costs.
The Project Manager and Project Sponsor will review the following earned value measurements:
1. Schedule Variance (SV)
2. Cost Variance (CV)
3. Schedule Performance Index (SPI)
4. Cost Performance Index (CPI)
5. To Complete Cost Performance Index (TCPI)
6. Estimated Actual Cost at Completion (EAC)

Schedule Variance (SV) is a measurement of the schedule performance for a project, and is calculated by subtracting the Planned Value (PV) from Earned Value (EV). EV is the actual value earned in the project, and PV is the value the project schedule tool indicates should have been earned at the measurement point. Subtracting PV from EV provides a measurement to
…show more content…
CV is calculated by subtracting Actual Costs (AC) from EV. EV is the actual value earned in the project. AC represents actual costs incurred to date. Subtracting AC from EV provides a measurement to indicate the status of the project as it relates to budget and cost.
• If CV is zero, the project is considered to be on budget.
• If CV is greater than zero, the project is earning more value than planned and is considered to be under budget.
• If CV is less than zero, the project is earning less value and is considered to be over budget.

Schedule Performance Index (SPI) is a measurement of the progress achieved against that which was planned. SPI is calculated as EV/PV. If EV is equal to PV the value of the SPI is 1.
• If EV is less than the PV then the value is less than 1, which means the project is behind schedule.
• If EV is greater than the PV the value of the SPI is greater than one, which means the project is ahead of schedule.
• A well performing project should have its SPI as close to 1 as possible.

Cost Performance Index (CPI) measures the value of the work completed compared to the actual cost of the work completed. CPI is calculated as
…show more content…
• If CPI is less than 1, the project is considered to be over budget.

To Complete Performance Index (TCPI) measures the efficiency at which resources on the project should be utilized for the remainder of the project. TCPI is calculated as (Total Project Budget – EV)/(Total Project Budget – AC).
• If TCPI is equal to 1, the utilization of resources on the project can continue at the current level.
• If TCPI is greater than 1, the utilization of resources on the project should be more controlled than the current level.
• If TCPI is less than 1, the utilization of resources on the project can be more lenient than at the current level.

Estimated Actual Cost at Completion (EAC) provides a forecast of actual cost to complete the project based on the cost performance. There are three ways to calculate EAC:
• Actual Cost plus Total Project Budget (TPB) minus Earned Value (AC + TPB – EV).
• Total Project Budget divided by Cost Performance Index (TPB/CPI).
• Actual Cost plus the result of dividing the difference between the Total Project Budget and Earned Value by the product of Cost Performance Index and Schedule Performance Index (AC + ((TPB –

You May Also Find These Documents Helpful

  • Powerful Essays

    The resulting NPV indicates that the project should be accepted and the investor should expect a return on equity of 38.87%. The NPV provides the investor with an expectation of what all future cash inflows will be worth in today’s dollars. The profitability index is closely related to the NPV. It evaluates the project’s feasibility based on future cash flows compared to initial costs. In general, a project is deemed a valid investment if this ratio is over 1. For this investment opportunity the profitability index indicates that it should be accepted.…

    • 3248 Words
    • 13 Pages
    Powerful Essays
  • Satisfactory Essays

    BGA1 Task 4

    • 343 Words
    • 2 Pages

    Net present value (NPV) method is used to decide whether or not a company should take on a new project or acquisition. The formula for NPV is the difference between the present value of a project’s cash inflows and its cash outflows. To calculate the present values the future cash flows are discounted using the time value of money method. For the project to be accepted the NPV should be positive, because it means the return is greater than the required rate of return; or zero, because that means the return is equal to the required rate of return. However, if negative the project should be rejected, because its return is less than the required rate of return. This required rate of return is also referred to as the cost of capital.…

    • 343 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    PROJ 592

    • 2367 Words
    • 10 Pages

    An Earned Value analysis reflected that the project is currently behind schedule. The schedule variance (SV) indicated a negative $565,226.34 and the scheduled performance index showed as .69. When SV is a negative number and SPI less than one, this indicates the project is behind schedule. After calculating the CPI/SPI value (1/.69= 1.45), any values above 1.3 should be investigated immediately, because those numbers are much too good to be true. In addition based on the Work Breakdown Structure the total duration was 6 days behind schedule. The new completion date in the WBS also indicates that the schedule completion date currently is 10days behind schedule.…

    • 2367 Words
    • 10 Pages
    Powerful Essays
  • Satisfactory Essays

    Nt1310 Unit 4

    • 555 Words
    • 3 Pages

    Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than…

    • 555 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Ilab Week7

    • 297 Words
    • 2 Pages

    EV: this is a value indicating how much of a budgeted cost should have been spent given the amount of work actually completed = $7,120.19…

    • 297 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Is equal to the annual net cash flows divided by one half of the project’s cost when the cash flows are an annuity…

    • 836 Words
    • 4 Pages
    Satisfactory Essays
  • Powerful Essays

    Ah531

    • 3543 Words
    • 15 Pages

    Valle, J., & Soares, C. (2005). The use of earned value analysis(eva) in the cost management of construction projects. Federal university fluminense, brazil, Retrieved from http://www.google.com/url?sa=t&rct=j&q=&esrc=s&frm=1&source=web&cd=4&ved=0CEQQFjAD&url=http://www.icoste.org/ICMJ%20Papers/Valle%20-%20EVA.pdf&ei=PkW7UeT0BobY8gS18YCADg&usg=AFQjCNFSA-RUj35ZNIwD-ii15E76nCs9-Q&sig2=Sktqkw1XxvD8CRFJnvkbVg…

    • 3543 Words
    • 15 Pages
    Powerful Essays
  • Powerful Essays

    Hrm/531 Operational Plan

    • 2203 Words
    • 9 Pages

    Key Performance Indicators, also known as Performance Indicators or Key Success Indicators (KSI), help an organization define and measure progress toward organizational goals. Once an organization has analysed its mission, identified all its stakeholders, and defined its goals, it needs a way to measure progress toward those goals. Key Performance Indicators are those measurements.…

    • 2203 Words
    • 9 Pages
    Powerful Essays
  • Powerful Essays

    Proj 592 - CP3

    • 1453 Words
    • 11 Pages

    After setting the entire project to 40% complete on Oct 1, 2008 we can see that the project is behind schedule. The schedule variance of the entire project is $ (736,599) and Schedule performance index is at 0.68, which indicates that for every $1.00 spent in the project we are only getting $0.68 worth of work done. Since we do not have actual cost data, the MS Project calculates the budget is under budget by a negligible $80.…

    • 1453 Words
    • 11 Pages
    Powerful Essays
  • Good Essays

    CI’s cost system was developed to measure performance and profit potential, each materials and labor input is given and production…

    • 915 Words
    • 4 Pages
    Good Essays
  • Better Essays

    Manufacturing objective is make sure they have create a useful and efficient process that will imposed check points at all operating locations. Paperwork will be turned in and the information is loaded into the database. The target is recorded and a weekly or monthly report is run. These reports are called Key Performance Indicator (KPI) or Key Success Indicator (KSI). “These reports are a set of quantifiable measures that the company or an industry uses to gauge or compare performance in team meeting of the strategic and operational goal” (Key Performance Indicators (KPI) Definition | Investopedia. (n.d.). These reports will be posted in all appropriate departments and meetings are set-up for discussion to talk about great performance or what we need to improve…

    • 1038 Words
    • 5 Pages
    Better Essays
  • Good Essays

    Cost, Volume and Profit

    • 589 Words
    • 3 Pages

    CVP analysis is performed to calculate the break-even point. The break-even point is where profits equal zero or total expenses equal total revenues. In graphic form, Brewer states, “the break-even point is where the total revenue and total expense lines cross”. (Brewer, 2010, p. 263) Once the break-even point has been determined, it can be determined whether there will be a profit or loss. On the graph, anything to the right of the break-even point will be profit and anything to the left will be loss. In equation form, CVP relationships can be expressed as follows: (contribution format income statement) Profit = (Sales – Variable expenses) – Fixed expenses or (unit contribution margin) Profit = Unit CM x Q – Fixed expenses, where Unit CM is Net operating income = Sales – Variable expenses.…

    • 589 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Earned Value Calculation

    • 409 Words
    • 2 Pages

    According to the SPI of a value of .75 it implies that we are under schedule at this time. The CPI of .93 implies that we are over budget. The schedule variance is negative $6125 which means the project is running behind. As of right now the project is over it's…

    • 409 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    to indirect project costs. One of the most common constraints is having a limited project budget.…

    • 570 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    These are important because they are well known success measure criteria of any project. It places cost, time and money at the center of project. This is called Iron Triangle. This framework helps to evaluate and balance the competing demands of cost, time and quality within their projects. The quality management of a project provides customer satisfaction, cost reduction, increased productivity and better competitiveness. Cost provides monetary resources needed to complete project activities. It determines the budget of the project. It also monitors the status of the project. Time management is an often critical for any successful project. If time is of the essence then quality or cost should be harmonized. If completion of project should be accelerated then more resources should be used in project and its lead to cost increasing. Sometimes changing of time (schedule) will affect both, cost and quality. If project must meet specific deadline quality could be cut to meet the accelerated time frame.…

    • 734 Words
    • 3 Pages
    Satisfactory Essays