Preview

Costs and Contract Terms

Good Essays
Open Document
Open Document
963 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Costs and Contract Terms
LITTLEFIELD TECHNOLOGIES 2nd edition
The Return of The Honeybadgers

-------------------------------------------------
Executive Summary
Over the span of 168 simulated days, team Honeybadgers managed the Littlefield Technologies job shop. The team’s objective was to maximize the firm’s cash position relative to the rest of the class. Using 50 days of historical data, the team reviewed re-order points, re-order quantity, capacity, lead times, and therefore contract terms. The team also weighed the cost of new machines against capital for inventory and interest rates, evaluating the return on investment and the impact a new machine had on lead times. Using this consideration set, team Honeybadgers purchased one tuning machine, one stuffing machine, and changed the contract terms on ten occasions. Ultimately, the team placed 5th.
-------------------------------------------------
Actions & Analysis
Changing Contract Terms:
A 7 day lead time generated higher revenue than the other contract terms during the first 50 days. However, we observed that there was a stretch of 5-8 days when the lead time was below a 1 day lead time during the first 50 days. Evaluating the first 50 days more closely revealed that approximately every 15-20 days, the lead time dropped substantially. Noticing a pattern, and aware that a different contract time could generate more revenue, we decided to micromanage the contracts to optimize revenue. For the duration of simulation, we adjusted contract according to the trending lead time. In times of high demand, when a lead time was more than 18 hours, we opted not to use contract #3 because of the cost of each order (avg. job cost+ordering cost = $608.33)
Micromanaging the contracts according to lead times was a temporary solution. This strategy allowed us to optimize revenue when we did not have the capital to purchase a machine.
Purchasing Tuning and Stuffing Machines:
We originally wanted to purchase both a tuning

You May Also Find These Documents Helpful

  • Satisfactory Essays

    When the balance was achieved on the process, then we started to intervene contracts since contract 3 provides the best profitability when the Lab is able to accomplish a promised lead time of 0.5 days being careful of change to contract 2 or 1 if the promised lead time would not be accomplished due to the circumstantial conditions of the process. To optimize the profitability of the jobs received on the first day of every week, we began to modify the contracts according to the following criteria:…

    • 855 Words
    • 4 Pages
    Satisfactory Essays
  • Powerful Essays

    | Should approach 100% in order to meet customer lead time of less than 6 weeks…

    • 1525 Words
    • 7 Pages
    Powerful Essays
  • Better Essays

    This week assignment is to provide analysis on the Contract Creation and Management simulation provided in the University of Phoenix (UOP) materials website. The simulation involves two companies; Span Systems, a California-based custom e-banking software developer and Citizen-Schwarz AG (C-S), a Stuttgart-based bank with revenues of over $20 billion. Through C-S’s regional offices in the United States, they contracted out Span Systems to develop a Java-based transaction processing software so they can enter the competitive $640 billion retail financial services market in America (UOP, 2002). The contract between Span and C-S is for one year and worth $6 million. This contract is Span Systems’ biggest and most prestigious banking software project to date and is targeting C-S’s bigger e-Customer Relationship Marketing (CRM) order in the future. Span System’s chances of getting the order hinge on the performance of this contract. In this simulation, I act as Span Systems’ project manager and must deal with problems that have risen or risk losing this contract and any future business relationship with C-S.…

    • 1745 Words
    • 7 Pages
    Better Essays
  • Good Essays

    2 time was pressing. the lead time between contracts being signed and initial deliveries got increasingly shorter.…

    • 2591 Words
    • 11 Pages
    Good Essays
  • Satisfactory Essays

    In this simulation we decided to take the message of The Goal and apply it as fast as we could. The goal of our company was to make money, so we needed to upgrade to contract 3 as quickly as possible. We bought additional machines at stations with high utilization rates in an attempt to relieve those bottlenecks. As soon as we noticed our lead times drop sufficiently enough for a new contract, we upgraded immediately. This same approach was used until our lead times dropped enough to consistently fulfill contact 3. After contract 3 was reached, our simulation flowed very well with the maximum amount of profit for almost the full remainder of the simulation.…

    • 501 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Cost and Overhead Costs

    • 282 Words
    • 2 Pages

    Youngstown has a traditional cost system. It calculates a plant-wide overhead rate by dividing total overhead costs by total direct labor hours. Assume, for the calculations below, that plant overhead is a committed (fixed) cost during the year, but that direct labor is a variable cost.…

    • 282 Words
    • 2 Pages
    Good Essays
  • Best Essays

    Woody Company is a small sole-proprietorship that specializes in the manufacture of high quality bar stools. Currently, three types of bar stools are marketed with increases in standing orders currently reaching $750,000. Mr. Woody has decided to expand his organization to and aggressively pursue the market, but realizes that issues with defective wood from his suppliers, manufacturing quality defects and problems associated with late delivery of his finished product has impacted his profit margin (Bateman & Snell, 2007, p. 317). My assistance has been solicited to optimize the organizational structure, recommend pay structure and determine work allocation within the company.…

    • 1342 Words
    • 5 Pages
    Best Essays
  • Satisfactory Essays

    3 Assume a fixed cost and unit variable cost and (a) calculate the break-even points and (b) plot a break-even chart for the three prices specified in step 2.…

    • 405 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Costs and Price

    • 1595 Words
    • 7 Pages

    10. The intersection of supply and demand will be at a lower equilibrium price but a higher equilibrium quantity if…

    • 1595 Words
    • 7 Pages
    Good Essays
  • Good Essays

    Littlefield Case Study

    • 875 Words
    • 4 Pages

    At this point, our team should have reevaluated our decisions, and purchased a new machine for Station 1, in order to get production moving faster to Station 2. As our utilization was remaining at a constant 100%, our lead times were also increasing. With full utilization, we were unable to produce enough product to meet our order demands, further increasing the queues at each station and increasing our lead times (as shown).…

    • 875 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    (This is the contract that the lab starts with). • price = $1000; quoted lead time = 1 day; maximum lead time = 3 days. • price = $1250; quoted lead time = 0.5 days; maximum lead time = 1 day. As before, if a customer order’s lead time exceeds the quoted lead time, then the revenue for that order decreases linearly, from the prices above for the quoted lead time to $0 for the maximum lead time. A contract is assigned to a customer order as soon as it arrives at the lab, and that contract cannot be changed subsequently for that order. Contracts for future orders can be selected by clicking on “Edit Data” on the Customer Order icon. You will also notice a few days where zero jobs are completed by the lab. On such days, the daily average lead time and daily average revenues are meaningless, so a value of zero will appear in the plots and downloaded data on those days. You are also allowed to buy and sell machines, change the scheduling rule at the tester, and change the lab’s maximum allowed number of jobs, called the WIP…

    • 838 Words
    • 4 Pages
    Powerful Essays
  • Powerful Essays

    A Make-or-Buy Decision at Baxter Manufacturing Company Scenario Summary Baxter Manufacturing Company (BMC) is a leader in deep-drawn stampings. It has been in business since 1978 as a privately held company. The process for making these stampings is very involved and complex. BMC developed methods for efficiently producing large volumes of stampings while keeping their quality very high. BMC uses state of the art machines to make the stampings and they make all the tooling necessary for those machines. In the years since their founding, many changes have impacted the industry – especially when it comes to computer networks and software. In the 1980s many of BMC's customers went to Just In Time manufacturing which affected BMC production schedules and inventory management. Automotive customers began asking for Electronic Data Interchange (EDI) capabilities around 1992. All of this has affected BMCs Information Technology department. Over the years, BMC has embraced the use of computers, computer technology, and software to enhance their competitive advantage and customer relationships. They have added CAD/CAM capabilities, a homegrown scheduling spreadsheet, and financial applications. A Commercial Off the Shelf (COTS) scheduling package was purchased in 1989 but the implementation was unsuccessful. Another COTS scheduling systems was purchased in 1991 but, again, the software did not match the needs of BMC. A new MIS manager, Don Collins, was hired in 1994 and he led an effort to develop a mini-computer based system to accept EDI orders from customers and allow customer service to create shipping schedules, as well as raw materials tracking, in process inventories, and finished goods inventories. These internally developed systems were so successful that the MIS department was flooded with requests for more systems. Don believes that it will take 2 years to internally develop the manufacturing software systems BMC needs to…

    • 1808 Words
    • 8 Pages
    Powerful Essays
  • Satisfactory Essays

    Teamwork and Motivation

    • 265 Words
    • 2 Pages

    Imagine that you are the owner of a small manufacturing company. Your company manufactures a commodity, widgets. Your widget is a clone of a nationally known widget. Your company’s widget, WooWoo, is less expensive and more readily available than the nationally known brand. Presently, the sales are high; however, there are many defects, which increase your costs and delays delivery. Your company has fifty (50) employees in the following departments: sales, assembly, technology, and administration.…

    • 265 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Cost Structure

    • 332 Words
    • 2 Pages

    Like any large business, WaMu relies upon a pre-determined cost structure to account for and control expenses. WaMu primarily realizes transaction costs, fixed costs, and variable costs. Because WaMu doesn’t provide free services per-say, the sunk costs of the structure are fairly minimal.…

    • 332 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    Cost Management

    • 2519 Words
    • 11 Pages

    Our case study is on the Columbia City Bank. First of all we would like to talk about the general inner workings of a bank. A bank generates a profit from the differential between the level of interest it pays for deposits and other sources of funds, and the level of interest it charges in its lending activities. In recent history, investors have demanded a more stable revenue stream and banks have therefore placed more emphasis on transaction fees, primarily loan fees but also including service charges on an array of deposit activities and ancillary services. Lending activities, however, still provide the bulk of a commercial bank's income. Beside, Banks make money from card products through interest payments and fees charged to consumers and transaction fees to companies that accept the cards.…

    • 2519 Words
    • 11 Pages
    Powerful Essays