Preview

Littlefield Case Study

Good Essays
Open Document
Open Document
875 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Littlefield Case Study
Before the simulation started, our team created a trend forecast, using the first 50 days of data, showing us that the bottleneck station was at Station 1. On day 50 of the simulation, my team, 1teamsf, decided to buy a second machine to sustain our $1,000 revenue per day and met our quoted lead time for producing and shipping receivers. On day 97, we changed Station 2’s scheduling rule to priority step 2. We noticed that the bottleneck was not just at station 1, but at all stations, and that buying a new machine would not be the right choice to make, but rather, changing the way in which the station’s processing is queued would be the better option. By doing this, we could produce all incoming kits with a priority enabling an even flow of kits to Station 3. At day 97, our team ranked first in the overall standing, and wanted to try to maintain this standing for the rest of the simulation.
On day 131, my team decided to change the Station 2 scheduling rule to priority step 4, because we started to see a 100% utilization for Stations 1 at day 120, and maintained 100% utilization continuously as station 2 had an average capacity of 50.3% as shown in the graph below. At this point, our team should have reevaluated our decisions, and purchased a new machine for Station 1, in order to get production moving faster to Station 2. As our utilization was remaining at a constant 100%, our lead times were also increasing. With full utilization, we were unable to produce enough product to meet our order demands, further increasing the queues at each station and increasing our lead times (as shown). We began to see our revenues drop drastically, as well as our ranking overall in the simulation. We thought that by setting the Station 2 scheduling rule to priority step 4, we would improve the throughput of the kits; we were wrong. We should have noticed this sooner, as its abrupt effect brought in $0 in revenue every day after day 134. On day 149, we decided to

You May Also Find These Documents Helpful

  • Satisfactory Essays

    With focusing on increasing the yields for the clear and the LoĒ² 272 we start with, Always have the WIN 3i system pulling from the maximum set of jobs allowed. There are times towards the end of the day or week when new orders do not get entered into the system and the amount of jobs to pull from decrease this also decreases the yield because the system is unable to fill empty spots from jobs down the queue. Another reason for there being less jobs is that there is not more orders to put in, in this case the supervisor will have to work with the plant supervisor to see how long they can hold off cutting the pieces until more orders come in to fill the queue.…

    • 369 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    The simulation allowed two types of cost cutting options to play with. The first option was to minimize the amount of the agencies staff within the facility. The reason this option was chosen is because contract laborers require more money for hire. Normally the higher pay is offered…

    • 1016 Words
    • 5 Pages
    Better Essays
  • Satisfactory Essays

    Finally, on day 150 we try an “all in” strategy spending $160.000 in 1 machine for station 1 and 2 to increase the capacity and to process jobs only on conditions of contract 3. This decision was taken based on a demand of 91 jobs and a utilization of station 1 of 0.83 between days 143 and…

    • 855 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    WGU JGT Task #1

    • 1134 Words
    • 5 Pages

    Catherine Pang provided the assembly schedule which denotes cycle time which is the maximum amount of time the boot is allowed to spend at each workstation. Upon initial inspection of the workflow, it is noted that a “bottleneck” is noted due to a variance between stations B and C (with a three minute difference) and stations E and F (with one minute difference). Both variances in sequential steps cause…

    • 1134 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    As a way of eliminate the wastage of time through performing of non-core tasks, we have introduced a CCT KPI of 4 hours a week, which translates into at least three 20 minute appointments per day. It is however, up to the discretion of the sales person how this is achieved, and can be distributed however works best throughout the week. This KPI is important, as it removes the excuses by setting an essentially unnegotiable benchmark.…

    • 468 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Lt Game

    • 384 Words
    • 2 Pages

    When we decided to purchase machine for three stations on day 66, we calculated the capacity rate for each station. We knew that we late for other groups for purchasing machine already. Then we saw the rank of team, we feel worry about the rank. So we decided purchase machine right now. Station 1 has the lowest capacity rate, and already saturation for one machine. And it has the most jobs waiting in the buffer, so we bought it first to see if whether it will get better or not. After one hours which is on the day 67 of the Game, when we had our group meeting, we found that the data is not change, so that mean we should add more machine in station 1. We decided to purchase 2 machines station 1 again totally 4 machines, because it has the closest full capacity rate compares to other two machines.…

    • 384 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Alex Rogo:His performance measure is the efficiency. That is to complete the order at a relatively lower cost and increase the economy scale. Alex said, “We can't just dedicate the entire plant to one order at a time. The economies of scale would disappear. Our costs would go well, they'd be even worse than they are now. We can't run the plant just by the seat- of-the-pants.”…

    • 641 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    The Goal Book Questions

    • 558 Words
    • 3 Pages

    First, they had to find the bottlenecks and non-bottlenecks. Second, the processes at bottlenecks were changed. Third, they subordinated everything to these changes and decisions. Fourth, they elevated the system constraints.…

    • 558 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    I have run this simulation for several times, each time I have to face some trade-off. If I want to gain full or even extra points from target scope part, which indicates more man-hour to input and heavier workload, I have to assign more upper-level workers to participate into the project, which means, of course, more cost. What’s more, since I do not want to change the target schedule, I have to encourage workers to work overtime and push them hard and these actions will definitely reduce my point in morale part.…

    • 461 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Critical Path

    • 1047 Words
    • 5 Pages

    As all the activities were processed exactly on schedule for the first 106 duration hours, the network diagram after the first 106 duration hours is as follow:…

    • 1047 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Capacity is calculated: (number of machines or workers) × (number of shifts) × (utilization) × (efficiency) and works in harmony with JIT, managing lead times and eliminating waste. Implementing a JIT system requires management to consider issues of worker stress, cooperation and trust among workers and management, and reward systems and labor classifications. In a JIT system, workers must meet specified cycle times and workers feel pushed and stressed, causing productivity losses or quality reductions and due to AP staff mindset been on doing a single activity per person it is going to take a lot of time for proper implementation. Workers at AP might feel that they have lost some autonomy because of the close linkages in materials flows between stations with little or no safety stocks due to elimination of waste through capacity planning.The fluctuation of demand creates problems regarding the procurement of resources to meet the customer demand and due to AP merely keeping up with demand JIT is going to be difficult to implement within a short period as capacity decisions are strategic in nature and is…

    • 1452 Words
    • 6 Pages
    Satisfactory Essays
  • Good Essays

    IEEE-30 Bus Case Study

    • 912 Words
    • 4 Pages

    This paper work has significantly accomplished many attainments in the area under discussion which is rescheduling the generations of Schedule Coordinators which are adjusted from the preferred schedules to relieve congestion.…

    • 912 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Cyclermate

    • 258 Words
    • 2 Pages

    Even out the production flow by reducing batch sizes, increase delivery frequency internally and if possible externally, level internal demand…

    • 258 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Work-in progress- output of preceding stage becomes input for succeeding stage Inventory decisions require analysis of workstation capacities, resource availability & bottlenecks…

    • 849 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    minimize total costs and activity days. The model was implemented successfully with savings over $100 million…

    • 312 Words
    • 1 Page
    Good Essays