Preview

Hk Airport (Construction Challenges)

Good Essays
Open Document
Open Document
700 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Hk Airport (Construction Challenges)
Summary of Hong Kong International Airport Project

The documentary video shows an extreme engineering works of constructing the Hong Kong International Airport. This project not only consists of new airport but also consists of super highways, tunnels and double Decker suspended bridges connecting to the main city. The construction of this project was definitely tough since only 7 years were given to complete the entire project. In fact, this project was estimated to be completed in 15 years.

There are several challenges faced during the construction stage. The main challenge is to construct the airport on a mountainous island. The mountains had to be removed and leveled. 200 million tons of rocks were removed by giant earth movers. To enlarge the surface area for the airport, reclamation works need to be carried out. The largest fleet of under water dredgers used to remove soft mud up to 120 meters the sea before reclamation works to ensure minimum consolidation settlement in the future.

The second challenge is to build a long tunnel through the sea. The construction method was to dig a basin and construct the concrete steel tunnel in sections. Once the tunnel sections were built, the basin will be flooded and the tunnel sections can be launched into designated location. After that, tunnel sections were to be laid 150 meters under water up to 1.6 km and capped with water tight seals to prevent water from entering. The seals were then removed carefully by hydraulic jacks.

Thirdly, there is an area with water width of 4.8 km where tunnels are not feasible due to heavy traffic on that route. The engineer proposed bridges to overcome the challenge. The bridges have to be long enough to span the islands and high enough to allow most gigantic ships below it. Two bridges with towers’ height of 60 stories were to be constructed. The most difficult construction method was practiced in this project where 75mm diameter cables (weigh up to 15000 tons) were built

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Some of the challenges would be that the architecture is very fragile, so it is falling apart very quickly. This causes them to have to be very carefully. Another challenge is that they can’t explore more into the tunnels because there are modern houses built on top.…

    • 403 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Most of the projects were done during the same time of each other and didn’t have to wait for one another. They had the Arizona approach and the Nevada Approach being constructed by two different companies and the bridge itself was constructed by two other…

    • 543 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Pratt Truss Bridge

    • 876 Words
    • 4 Pages

    Each type of design is although, unique in its own way, fulfills the desired goal that the Truss Brides are made for. The purpose of this experiment is to research various bridges and build a similar one that gave the students the highest inspiration. For one case in particular, the bridge design was in-spired by the Pratt Bridge and almost every height, width, and length met the requirements ex-cept for the length on the bottom part of the bridge, it exceeded the maximum height that was asked. Moreover the bridge held a total of 20 pounds before one of the top sticks snapped. Alt-hough it performed a decent job, the bridge could have held more weight if there were more di-agonals to provide more support so the bridge wouldn't break. Furthermore, this bridge fulfilled its goal and held a large amount of weight for such a small bridge. These bridges are also very significant for this planet because it is very resourceful and effective, as well as…

    • 876 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Essay On Truss Bridges

    • 536 Words
    • 3 Pages

    Cable-stayed bridges look similar to suspension bridges, but support the weight load very differently. They are similar in the way that they both have towers, and the roadways are hung from cables, but are different in the way the cables are connected to the towers. In cable-stayed bridges, the cables are attached to the towers, which support the weight load. Unlike suspension bridges, in which the cables ride freely across the towers. For medium-length distances, 500 to 2,800 feet, cable-stayed bridges are quickly becoming bridges of choice because they require less cable, and the are quicker to…

    • 536 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Essay

    • 1594 Words
    • 7 Pages

    In order to meet this aggressive schedule, the project will require around the clock construction crews, detailed project management, good construction weather, and some modern construction techniques.…

    • 1594 Words
    • 7 Pages
    Powerful Essays
  • Good Essays

    Anzac Bridge

    • 342 Words
    • 2 Pages

    The materials that were used to construct this bridge consisted of prestressed concrete, steel casings, prestressed steel, reinforcing steel wire strands and polyethylene. It was built on each side of the land and was eventually connected together in the middle. It was constructed by using a formtraveller (a travelling formwork) and setting up the formwork before positioning and tensioning the cables. They then proceeded to place the reinforcement cement and pouring on the concrete. This was made in a cycle with each cycle being used to make…

    • 342 Words
    • 2 Pages
    Good Essays
  • Better Essays

    Big Dig Research

    • 1034 Words
    • 4 Pages

    The Big Dig was a megaproject in Boston that consisted in rerouting the Central Artery into a 3.5-mile tunnel, building the Ted Williams Tunnel, the Leonard P- Zakim Bunker Hill Memorial Bridge over the Charles River, and the Rose Kennedy Greenway in the newly vacated space. The project took 15 years to get done and finally concluded on December 2007. Even though there were several issues and problems along the way that today teach us lessons about managing megaprojects including increase of cost estimations, risk control and collaboration between the involved groups, the Big Dig was a success considering its complexity and technical challenges.…

    • 1034 Words
    • 4 Pages
    Better Essays
  • Satisfactory Essays

    Forensic Human Remains

    • 395 Words
    • 2 Pages

    C. Some of the challenges would be that the architecture is very fragile, so it is falling apart very quickly. This causes them to have to be very carefully. Another challenge is that they can’t explore more into the tunnels because there are modern houses built on top.…

    • 395 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    As a suspension bridge, the towers needed to hold the cables that hold the roadway. Thus, these towers had to be extremely strong and stable and had to be sunk down. In order to accomplish that, Washington Roebling started a new concept. He ordered a construction of caissons. These caissons were sealed, watertight, airtight chambers. They were made of wood and it would dumped into the water. In this way they would sunk down to the very deep end and all the water that is filled inside of caisson would be pumped out (History, 2010).…

    • 928 Words
    • 4 Pages
    Good Essays
  • Good Essays

    During the building of the Panama Canal many problems arose making it hard to construct, even on second try. Such problems involved were engineering, sanitation, and organization. Many lives were lost due to some of the hazards that were present at the time, but the canal was eventually finished in 1914.…

    • 849 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    The Channel Tunnel, or Chunnel Denver International Airport Panama Canal expansion project Three Gorges Dam, China Flying: balloons  planes  jets  rockets  reusable rockets…

    • 999 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    Civil Engineers build significant structures that can last more than a century, some of these structures such as Burj Khalifa, pyramids and evil towers in France can be considered as landmarks, because of its history and its beauty of design. Civil Engineers study the four factors of building structures to determine which tools and materials they will use in order to build permanent structures. Although engineers studying the factors and take the determination, there is some disasters occurred in many places because of many reasons. Nick Spurrier said “There will always be failures or disasters as engineers and designers push the boundaries by building taller buildings, longer bridges, or by reaching further into space”. In this outline I will show some of engineering disasters that happened before and what are the reasons.…

    • 635 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Case Study

    • 645 Words
    • 3 Pages

    London 2012 Olympic and Paralympic Games created the need for a major regeneration and constructions programme to provide the venues and infrastructure needed to stage the games. The project was extensive, technically and politically challenging and up against a fixed deadline of July 2012. The publicly funded body established in 2006, Olympic Delivery Authority, was in charge of completing the project and turning the vision of the Games in to reality. They had to ensure that the project would;…

    • 645 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    In 1970’s, after completing phase one, phase two stuck because of the many obstacles such as Frozen Soil and High Altitude Hypoxia. Then in 1995, with the police of Western Open, the construction was put back on the table again.…

    • 257 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    buss news

    • 637 Words
    • 2 Pages

    The Department of Transportation and Communication (DOTC) said the project covers the construction of a new world-class international passenger terminal building at the Mactan-Cebu International Airport and the renovation of the existing terminal and its conversion into an exclusively domestic facility.…

    • 637 Words
    • 2 Pages
    Satisfactory Essays