Preview

Project Mangement

Good Essays
Open Document
Open Document
2339 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Project Mangement
Q1. Describe the CPM model. Briefly explain?

CPM model was developed for making risk free Projects. CPM approach is deterministic. In CPM analysis we work with single time estimates. The main focus on VPM analysis is on variations in activity times as consequences of changes in resource assignments. The major focus of CPM analysis is on time cost relationships and it seeks a project schedule that minimizes total cost.

Assumptions under lying CPM Analysis- 1. The costs associated with a project can be divided into two components. Direct costs and indirect costs. Direct costs are incurred on direct material and direct labor. Indirect costs consists of overhead items like indirect supplies, rent, insurance, managerial services, etc.2. Activates of the project can be expedited by crashing which involves employing more resources.3. Crashing reduces time but enhances direct costs because of factors like overtime payments, extra payments, and wastage. The relationship between time and direct activity cost can be reasonably approximated by a downward sloping straight line.

Direct cost of activity

Duration Crash Time Normal Time Activity

4. Indirect costs associated with the project increase linearly with project duration
Indirect cost of project

Procedure Duration Procedure Given above assumption, CPM analysis seeks to examine the consequences of crashing on total cost. Since the behavior of indirect project cost is well defined, the bulk of CPM analysis is concerned with the relationship between total direct cost and project duration. The procedure used in this is: 1. Obtain the critical path in normal network. Determine the project duration and direct cost.2. Examine the cost time slop of activities on the critical path obtained and crash the activity which has the least slope.3.Constrct the new critical path crashing as per step 3. Determine the project duration and cost.4.Repeat steps 2 and 3 till activities on the critical path are crashed.

You May Also Find These Documents Helpful

  • Good Essays

    How do the five major variables of project management-scope, time, cost, quality, and risk – relate to this scenario?…

    • 1016 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    Mcbride Financial Services

    • 4240 Words
    • 17 Pages

    References: APEGBC, (2009). Project Cost Control Basics. Retrieved July 22, 2010 from APGE website at…

    • 4240 Words
    • 17 Pages
    Powerful Essays
  • Powerful Essays

    Final Exam Pol 103

    • 2057 Words
    • 9 Pages

    1 A) Andrew Mark Cuomo born December 6, 1957 is the 56th and current Governor of New York, He was the 64th New York State Attorney General, and was the 11th United States Secretary of Housing and Urban Development. Born in Queens, New York, he is the son of Mario Cuomo, the 52nd Governor of New York (1983–1994). A member of the Democratic Party, he was a top aide to his father during his 1982 campaign for Governor. Andrew Cuomo was appointed to the Department of Housing and Urban Development as Assistant Secretary in 1993, a member of President Bill Clinton's administration. From 1984 to 1985 he was a New York assistant district attorney. He briefly worked at the law firm of Blutrich, Falcone & Miller. He founded Housing Enterprise for the Less Privileged (HELP) in 1986 and left the law firm to run HELP full-time in 1988 From 1990 to 1993, during the administration of former New York City Mayor David Dinkins, Cuomo served as Chairman of the New York City Homeless Commission, which was charged with developing policies to address the homeless issue in the city and to develop more housing options.…

    • 2057 Words
    • 9 Pages
    Powerful Essays
  • Powerful Essays

    Whatever the type of project, there are three important elements of cost, schedule and performance project managers must achieve in order to attain a successful project outcome. These elements are interrelated which means a slight change of one of the elements such as prolonging the project time schedule highly affect the element of cost or more…

    • 1428 Words
    • 6 Pages
    Powerful Essays
  • Satisfactory Essays

    How do the five major variables of project management—scope, time, cost, quality, and risk—relate to this scenario?…

    • 321 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Week Dqs

    • 274 Words
    • 2 Pages

    Accurate estimates are critical to effective project management because having accurate time and costs estimates helps ensure the project is a success. Project control is dependent on accuracy of estimates, time and cost, estimates are major inputs to project planning. Estimates are used to support good decisions to determine project duration and cost. Used to develop time phased budgets and estimating helps reduce error. Project managers can take steps to improve the accuracy of estimating projects by using techniques to scope, constrain and plan the projects conditions, this will help reduce risks, and increase the project’s success.…

    • 274 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    Time, in project management, is analyzed down to its smallest detail. Cost over runs can be easily resolved in-house, but schedule issues are open and visible to the customer. Choices have to be made about which work to do and how to allocate resources. Which may lead to constraints specifically in regards to time constraint and the cost constraint? Every components of the project are analyzed on the basis to the time that is required for completion of the project. When completion of this analysis is met, the components are then broken down further into the time required to do each task. And out of all of this we will be able to estimate the duration of the project as well as what and how many/much resources need to be dedicated to that particular project. Costs are usually related to the resources which are required in the project. Cost of a project refers to what needs to be applied or assigned to the project in terms of effort and money in order to complete the project. This includes resources like materials, manpower or any third party resources that night need to be secured. However, when we allocate additional resources to the project we need to redesign the schedules which may lead to different critical paths and therefore, make it even more difficult to manage the project. In other words, we cannot change cost or time without…

    • 1283 Words
    • 6 Pages
    Better Essays
  • Powerful Essays

    Project Management

    • 2874 Words
    • 12 Pages

    Project Conveyor Belt Memorandum Subject: Conveyor Belt Project Part 2 Memo The Estimate Date Project To be Completed. The project forecast date to be complete is on Wednesday, 1st February 2012. The project lead-time is 530 working days. The Project Critical Paths. The project critical paths are…

    • 2874 Words
    • 12 Pages
    Powerful Essays
  • Good Essays

    mis 302

    • 1114 Words
    • 5 Pages

    The Critical Path is the Shortest Time in which the Project Can Be Completed. Any delay in Critical Path activities delays the project. Critical Path Activities have no slack time Variability in Activity Times: CPM assumes we know a fixed time estimate for each activity and there is no variability in activity times PERT uses a Probability Distribution for Activity Times to allow for Variability.…

    • 1114 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    Mgt150 Assignment 1

    • 970 Words
    • 4 Pages

    University of Management and Technology MGT 150 Project Management Assignment 1 Bottom-up cost estimating exercise (Module 3, pp. 19-20) 1.0 Research 1.1 Birdhouse Book…………………………………………………. …… $ 30.00 1.2 Jimmy’s time to read up on birdhouses…………………….… …… $ 4.00 1.3 Dad’s time………………………………………………………. ….… $ 80.00 2.0 Materials acquired 2.1 Lumber…………………………………………………………..…

    • 970 Words
    • 4 Pages
    Powerful Essays
  • Powerful Essays

    Pert Mustang

    • 2682 Words
    • 11 Pages

    construct a network diagram for a project determine critical path and expected completion time of a project with deterministic task times (note: some of us also do calculations for probabilistic times, but not required) calculate slack times for a particular task know how to “crash” a project down to a certain completion time at the lowest cost (note: just the concept of crashing needs to be discussed and not the calculations; some of us do the calculations, others do not)…

    • 2682 Words
    • 11 Pages
    Powerful Essays
  • Powerful Essays

    By using this different phase of the life cycle model, PMP handles the project in very well-mannered way. In the initiation phase, project manager with four other team members are selected and assigned. Stake holders are identified, and the scope is determined with the constraints and requirement. Various techniques are used in planning phase which includes identifying milestone, Work breakdown structure, Gantt chart, Network diagram, Risk management plan, and detailed budget. After careful planning and consideration, the project is executed in a controlled and effective manner. The project is monitored and controlled in each phase by identifying the completed milestones and responsibility assignment matrix which is then reported in a work summery report. The work done by each team member is reported by evaluating the weekly performance and quality, and change is alerted on a controlled manner in the change request form. All the details, task assignment to each team member, budget and time allocated for each task, relationship and start-end of each task are clearly mentioned in the PMP. The total budget for the project is $500,000 and the allocated time period is twelve months.…

    • 2679 Words
    • 11 Pages
    Powerful Essays
  • Satisfactory Essays

    Project Management

    • 1620 Words
    • 7 Pages

    A _______________ is a temporary endeavor undertaken to create a unique product, service, or result.…

    • 1620 Words
    • 7 Pages
    Satisfactory Essays
  • Powerful Essays

    Resource Allocation Paper

    • 2410 Words
    • 10 Pages

    Project management is the discipline of defining and achieving targets while optimizing the use of resources: time, money, people, materials, energy, space, etc., over the course of a project. The most important resources that project managers have to plan and manage on day-to-day basis are people, materials, equipment and working capital. Obviously, if these resources are available in abundance then the project could be accelerated to achieve shorter project duration. On the other hand, [Avoid using colloquial language, slang or jargon in formal writing (14)] if these resources are severely limited, then the result more than likely will be a delay in the project completion time. Depending on the type of resources, the costs of providing an abundance of such resources to accelerate project completion time can be very high. However, if resources are readily available and excess premiums are not incurred to use them on the project, then project cost should be low, as some project costs are resource related while others are likely to be time dependent.…

    • 2410 Words
    • 10 Pages
    Powerful Essays
  • Satisfactory Essays

    References: MILOSEVIC, D. (2003). ‘Project Management Toolbox: Tools and Techniques for the Practicing Project Manager’. Wiley Publishing Inc. Hoboken, New Jersey. LEACH, LAWRENCE P. (2000). ‘Critical Chain Project Management’. Boston: Artech House, Inc. LEACH, LAWRENCE P. (2000). ‘Simplified Critical Chain Project Management (S-CCPM)’. Advanced Projects Institute.…

    • 958 Words
    • 4 Pages
    Satisfactory Essays

Related Topics