(Brown, 2002)
1. An Analysis of the Project’s Structure and Management:
1.1 Project Structure:
The West Gate Bridge in Melbourne was going to be, undoubtedly, the largest bridge of Australia, with four lanes in each direction and a total span of 2.6 kilometres. The bridge consisted of two parts:
1) Approach Spans:
Spans in reinforced concrete of 67 metres each.
2) Centre part:
Total length of 848 metres, in steel.
This steel section was a continuous box-girder …show more content…
bridge divided in five spans out of which, three centre spans, suspended by stay-cables, were over the Lower Yarra River.
The main span of 336 metres would be one of the largest spans for a bridge supported by stay cables.
Cross-section of Bridge:
The cross-section of the Bride was a trapezoid, having four webs, two inclined and two vertical, forming a three celled box-girder. The vertical webs contributed to the load carrying capacity and acted as inner support for the crossbeams in the lower and upper flange.
(Åkesson, 2008)
(Åkesson, 2008)
1.2 Management:
Western Industries Association – In 1951, formed by industries from Williamstown, Spotswood, Altona and Footscray and surrounding areas, this association was the most concerned that a crossing should be made across the River Yarra.
Lower Yarra Crossing Company Inc. (LYCC) - Due to lack of funds with the government, in 1961, a private company ‘LYCC’ was formed which had negotiations with the government for establishment of a project for the crossing.
Lower Yarra Crossing Authority (LYCA) - Due to voluntary liquidation of LYCC, in 1965, LYCA was formed by parliamentary act which had the powers for compulsory acquisition of land, managing finance, plans & engineering etc.
Maunsell & Partners (MP) – Since 1964, MP provided consultancy to the LYCC and LYCA on the bridge project.
Freeman, Fox & Partners (FF&P) – On recommendation by MP, FF&P were formally engaged in July 1967 to provide consultancy along with MP because of their successful Sydney Harbour Bridge.
John Holland (Constructions) Pty. Ltd (JHC) – In January 1968, the responsibility of bridge foundation and concrete works was given to JHC. World Services & Construction Pty. Ltd (WSC) – Steel works for the bridge were given to WSC.
(Commission, 1971)
1.3 Problems with Structure and Management:
JHC had been performing well in terms of foundation and concrete works but there was lack of co-ordination between FF&P and WSC as the latter was trying to create the designs made by the former.
(Commission, 1971)The delays and mismanagement led the contractor chose an unusual method of bridge construction. Thus to save time, it was decided to build the girder spans in two halves which were then to be lifted up and fitted.
(Åkesson, 2008)
Due to delays, steel works of the bridge were given to JHC which had no experience for large scale steel works and construction.
Due to miscalculations of the buckling stress, while on the ground, the free flange of the inner part had started to buckle due to self weight of the girder.
On bringing the two half girders into close proximity, it was observed that there was a gap of approximately 4.5 inches (114 mm). (Works)
Kent ledge to push down the north half span relative to its south counterpart was used and thus ten cube shaped blocks of concrete weighing eight tonnes each were placed on the bridge which further led to a buckle.
To release this buckle, screws were removed. On removal of 16 bolts, the buckles were reduced but the other bolts were squeezed tight jamming them in position.
It was then decided that the bolts should be tightened until they broke.
On removal of 37 bolts, the inevitable collapse started. Buckles spread in the transverse direction due to overloading. (Åkesson, 2008) (Building) ultimately span 10-11 collapsed killing 35 people including two onsite engineers (Victoria)
(Works)
2. A proposal for the Structure and Management of the Project:
2.1 Management:
One of the major reasons for the collapse of the West Gate Bridge was the inappropriate selection of the management for a project of that scale. Thus management should be laid stress upon.
Experienced Management:
Only companies which have good experience for handling such a large scale project should have been given the opportunity to manage a project like that.
Better co-ordination of the teams involved:
Lack of co-ordination can be seen between WSC and FF&P which was the main reason of all the collapse and miss management. Teams should have had better co-ordination among themselves in order to work efficiently.
Strict implementation of laws:
There must have been proper implementation of laws that govern the bridge construction work so that it was made sure that the materials used were up to the accepted grade mark.
Autonomous
committee:
An autonomous committee must have been made for fast tracking the processes of judgements on any matters that might have arisen during the project.
Involvement of the Government officials:
There must have been constant involvement of the government authorities to regulate the bridge work and create a positive pressure on the teams involved for taking the best of the results from them.
Second opinions:
Second opinions from highly experienced architects and construction companies must have been taken in order to double check all the designs for the steel as well as the concrete works for the bridge.
Positive pressure:
It should have been reassured that the deadlines given to the companies involved acted as a positive pressure rather that making them take decisions hastily which in return led to wrong decisions and ultimately, disasters!
2.2 Structure:
The collapse of the West Gate Bridge was aided because of choice of inappropriate design and unusual way of erection. Thus techniques for the erection of bridge should be laid stress upon.
Calculations:
Proper calculations of the stress due to self weight, tension and dimensions should have been done.
Erection Techniques:
Tried and tested erection techniques should have been used for bridge erection rather than using unusual ways such as half girder fabrication process.
Observations:
Proper observation of the fabricated parts should have been done so that any errors would have been recorded.
Proper error correction techniques:
Proper error correction measures should have been taken before the erection of the fabricated parts rather than taking shortcuts in order to complete the task within the given time period.
Bibliography
Åkesson, B. (2008). Understanding Bridge Collapses. The Netherlands: Taylor & Francis Group.
Brown, M. (2002). Australia 's Worst Disasters. Sydney: Hachette Australia.
Building, O. T. (n.d.). Retrieved from Old Treasury Building: http://www.oldtreasurybuilding.org.au/westgate-bridge-collapse-40-years
Commission, R. (1971). Report of Royal Commission into The Failure of West Gate Bridge. Melbourne: C. H. Rixon, Government Printer.
Victoria, S. G. (n.d.). Retrieved from Public Record Office Victoria: http://prov.vic.gov.au/whats-on/exhibitions/disaster-at-west-gate-the-west-gate-bridge-collapse-of-1970/the-disaster
Works, P. (n.d.). Retrieved from The West Gate Bridge Memorial: http://www.westgatebridge.org/