Western Blvd Case Study
Introduction:
Western Boulevard is a major roadway that bisects NC State’s Main and Centennial Campus as well as serves as a main gateway into the center of downtown Raleigh. Pedestrian, bicycle, and vehicular volumes are steadily rising each year and are expected to continue this trend as the university and city, are constantly developing and growing. The investigated section of Western Blvd has on average 30,000 vehicles per day and hundreds of students crossing at various locations throughout the corridor. The main area of concern is the intersection of Avent Ferry road and Western Blvd (shown in figure 1), which produces many safety concerns for students. The large amount of pedestrian traffic is a product of students walking to class from
…show more content…
wide bridge.)

$2,000⁄ft∙120 ft=$240,000 6-9 months including design and construction Design, engineering, installation and administration costs.
Pedestrian underpass $1,200 per linear foot (assuming 10 ft. wide underpass.)

$1,200⁄ft∙120 ft=$144000 About a year because of difficulty of raising road above. Design, engineering, installation and administration costs.
Speed limit change Virtually none 30 days for approval n/a

Advantages
Solution 1: Constructing a pedestrian bridge at the intersection of Avent Ferry road and Western Boulevard. When used properly, it eliminates pedestrian injuries and deaths caused by vehicles by 100%. A pedestrian bridge would allow for an increased flow of traffic, a necessity for Western Boulevard during rush hour. A pedestrian bridge has reduced impact on traffic during construction phase Bridges can be aesthetically pleasing structures and serve as a landmark on campus. Good visibility from surrounding areas, giving the end user a greater sense of safety.

Solution 2: building a pedestrian underpass or tunnel at the intersection of Avent Ferry road and Western Boulevard. When used properly, it eliminates pedestrian injuries and deaths caused by vehicles by

You May Also Find These Documents Helpful

  • Best Essays

    This proposal outlines the potential development of the Light Rail Transit (LRT) system for Northern to Southern formal region of Hamilton. LRT has 2 main routes that are being proposed; East-West route running from Eastgate Square Mall to McMaster University and North-South route running from Hamilton International Airport to Hamilton Harbour. The proposed system enclosed within this report will run from Hamilton International Airport to Hamilton Harbour. The report will outline the advantages and disadvantages of the proposed route in depth, as well as specific rejected routes. In addition, the report will go into detail of three chosen locations, which will discuss why the location was chosen, area amenities, as well as the pros and cons of the station selected. Furthermore, two maps are attached within the report, as well as site photography to help visualize the selected route and selected stop locations.…

    • 3410 Words
    • 14 Pages
    Best Essays
  • Powerful Essays

    From Downtown Vancouver take C-TRAN Bus #4 (Fourth Plain) eastbound to the Vancouver Mall Transit Center.…

    • 31752 Words
    • 128 Pages
    Powerful Essays
  • Satisfactory Essays

    Our last destination is on seventh street. You will be walking there. Simply head east, this is past the SlotZilla Zip Line and across Las Vegas Blvd. After crossing Las Vegas Blvd (this is the equivalent of fifth street in the downtown area), you will want to stay on the right side of the street. You need only walk two more blocks, and you will arrive at Container Park.…

    • 198 Words
    • 1 Page
    Satisfactory Essays
  • Satisfactory Essays

    Shuttle Info

    • 1441 Words
    • 6 Pages

    CrossIron Mills provides a private shuttle service for exclusive use of transporting current employees to and from their place of work. This is a private service that requires current proof of employment to be produced in order to purchase fare. CrossIron Mills does not provide intercity/regional transportation to members of the public. If you have questions or concerns regarding public transportation in your municipality, we encourage you to contact your local city or county council. LOCATIONS ROUTE #1 Dalhousie (5005 Dalhousie Dr. NW, the LRT lot) Harvest Hills Park & Ride (corner of Harvest Hills Blvd N & Country Village Way NE) ROUTE #2 Métis Trail & 64th Avenue NE LRT Station ROUTE #3 Airdrie (Sierra Springs Drive SE, east-side of the Co-Op Store) Employees MUST purchase a pass prior to boarding the Shuttle, NO PASS = NO RIDE. Passes are purchased at the Guest Services centre located inside CrossIron Mills. CURRENT PROOF OF EMPLOYMENT MUST BE PRESENTED TO PURCHASE A PASS (pay-stub, offer letter, letter from your Manager.) It is your responsibility to provide proof of employment. Phone calls to Managers, etc. will not be accepted. ONE –WAY TICKET = $1.50 MONTHLY PASS = $50.00…

    • 1441 Words
    • 6 Pages
    Satisfactory Essays
  • Good Essays

    This is going to be a multi-agency effort between our city and the city of Limewater as well as the metropolitan transportation council. In order for this project to take off, a great deal of intergovernmental cooperation will be needed so that burreacratic red tapes should not become an impediment for the smooth sailing of the light rail project. Everybody realizes that they have a stake in this and its timely completion will be a big relief for all parties involved.…

    • 619 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    The emergency response driver will be driving at extreme speeds through built up areas which has high risk to pedestrians.…

    • 282 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    Self Marketing Plan

    • 2525 Words
    • 11 Pages

    Map, G. (2012, 12 03). Driving directions to 750 Sunland Park Drive, El Paso, TX 79912. Retrieved from Map data ©2012 Google: https://maps.google.com/maps?ie=UTF-8&gl=us&daddr=750+Sunland+Park+Drive,+El+Paso,+TX+79912&panel=1&f=d&fb=1&dirflg=d&geocode=0,31.815214,-106.545541&cid=0,0,2107962478139008266&hq=sunland+park+mall&hnear=sunland+park+mall&ei=jfK8UL-dHZGK2QXN_4HAAg&ved=0C…

    • 2525 Words
    • 11 Pages
    Better Essays
  • Powerful Essays

    Foot walk into restricted areas. Replace reversing with forward movements. Allow planning of vehicle access routes to load points…

    • 4209 Words
    • 17 Pages
    Powerful Essays
  • Good Essays

    of these things have worked for him and appear to be working out for the pedestrians sharing his…

    • 687 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Have you ever stood 36 meters above the ground? No, probably not. Why not, though? It's because this feature is special to the Henderson Waves bridge. What a walkway for pedestrians, but it might also be your favorite tourist location. Did you know that up to about 5,500 pedestrians get hit by cars a year? This modern technology marvel might help prevent that, and it can be a great place to visit on vacation with your…

    • 77 Words
    • 1 Page
    Satisfactory Essays
  • Satisfactory Essays

    This is a complex situation dealing with tenants and their parking spaces. Reason being every body would like to have the better ....…

    • 450 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    12.As you stop for a stop sign A bicyclist is approaching from the right on a through street you should A.Yeild to the bicyclist…

    • 1326 Words
    • 6 Pages
    Good Essays
  • Powerful Essays

    References: 1. Ahuja. S, S Bose, T van Vuren and D Ragland, Towards the Provision of Ultimate Pedestrian Priority: Guidelines for Installation of Scramble (all red phase) Pedestrian Signals at Intersections Paper submitted for presentation at the European Transport Conference, the Netherlands 2008 Ishaque, M.M and R.Bm Noland, Micro-simulation Comparisons of Alternative Signalized Pedestrian Crossings, Paper submitted for presentation at the Transportation Research Board Annual Meeting, Washington D.C 2006 Bechtel, A.K, K.E. MacLeod and D.R. Ragland, Oakwood Chinatown Pedestrian Scramble: An Evaluation, UC Berkeley Traffic Safety Centre, December 2003 TD 50/04, The Geometric Layout of Signal-Controlled Junctions and Signalised Roundabouts, Design Manual for Roads and Bridges (DMRB), Vol. 6, Section 2.The Stationery Office (TSO). November 2004 Traffic Advisory Leaflet (TAL) 5/05, Pedestrian Facilities at Signal Controlled Crossings, Department for Transport (DfT) (March 2005) Fruin, J.J, Pedestrian Planning and Design. Alabama: Elevator World Inc, 1987 TA 16/81, General Principles of Control by Traffic Signals, Design Manual for Roads and Bridges (DMRB), Vol. 8, Section 1. The Stationery Office (TSO) September 1981 TTS6, Design Standards for Signal Schemes in London, Transport for London, August 2002…

    • 5834 Words
    • 24 Pages
    Powerful Essays
  • Good Essays

    Drivers can become frustrated as they wait for pedestrians to make their way through crosswalks, and fail to yield to the right-of-way of pedestrians. Drivers also may exceed speed limits throughout the state, increasing their chances of not seeing a pedestrian while reducing their potential reaction time to avoid a collision.…

    • 495 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    The Bay Bridge Tunnel

    • 334 Words
    • 2 Pages

    * The CBBT (Chesapeake Bay Bridge Tunnel) is a 17.6-mile long composite bridge composed of low-level trestles, high-level trestles, single-tube tunnels, and truss bridges. It was commissioned to be built in 1960 and funded by the Chesapeake Bay Ferry Commission with revenue bonds and private investors. Contracts for building were given to Tidewater Construction Corporation and Merritt-Chapman & Scott Corporation.…

    • 334 Words
    • 2 Pages
    Satisfactory Essays

Related Topics