Preview

Writing A Problem Analysis

Satisfactory Essays
Open Document
Open Document
330 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Writing A Problem Analysis
To: John Raines
From: Mia Grimm, Field Engineer
Date: November 07, 2014
Subject: Construction of a water-cooling tower

Introductory Summary I am writing to give an update on the observations that I have noticed on the construction site. I will be letting you know about all of the safety risks, delays, and any security issues that have occurred.

Safety We have had a couple of safety issues such as last week, Mary Powell, an M-Global safety inspector on the crew, cited 12 workers for not wearing their hardhats. Cement-truck drivers must slow down while driving through the site. Other workers complain about the excessive dust raised by the trucks. It is probably time, once again, to get all the subcontractors together to discuss safety at the tower site. Recently, two field hands had bad cuts from machinery.
Delays
There have been a few delays so far, three cement pourings for the tower wall were delayed an hour each on April 21 because of light rain. I heard from one of the subcontractors, Allis Wire, Inc., that there will be a two-day delay in delivering some steel reinforcing wires that go into the concrete walls. That delay will throw off next week’s schedule. Last Monday’s hard rain and flooding kept everyone home that day.
Security
I have also noticed that some of the materials have been disappearing. Though there have not been any major thefts at the site, some miscellaneous boards and masonry pieces are missing each day, probably because nearby residents doing small home projects think that whatever they find at the site has been discarded. Do you believe that additional No Trespassing signs needed to help solve this problem?
Conclusion
I am happy to inform that although we have run into more a few problems on the construction site, construction is only two days behind schedule. As long as nothing else goes wrong that hasn’t already been factored into the schedule we should be able to get back on track.

You May Also Find These Documents Helpful

  • Good Essays

    Nt1330 Unit 3 Assignment

    • 447 Words
    • 2 Pages

    We cannot complete the construction at this point in time due to the extension of the building project.…

    • 447 Words
    • 2 Pages
    Good Essays
  • Good Essays

    Risk Management Plan Devry

    • 1424 Words
    • 6 Pages

    3. Weather issues causing delay in outside work. This could cause construction delays on the roof and the outside fencing area.…

    • 1424 Words
    • 6 Pages
    Good Essays
  • Good Essays

    Jim Brown

    • 770 Words
    • 4 Pages

    From what we can determine so far the main issues revolving around your construction project are unionized workers starting strikes and weather concerns during December. We are also informed that the company will suffer from a $500 per week penalty fee on overhead expenses if the construction project is not finished on time. It is also stated in the contract that a penalty clause of $15,000 per week of delay beyond February 15 of the following year will be implemented.…

    • 770 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    After analyzing the headquarters and Riordan’s other sites it was found that they were not…

    • 2582 Words
    • 11 Pages
    Powerful Essays
  • Powerful Essays

    Irwin, P. A., & Baker, W. F. (June 2006). The Burj Dubai tower- wind Engineering. Structure Magazine .…

    • 3251 Words
    • 14 Pages
    Powerful Essays
  • Good Essays

    Now the report is done you can see we have some work to be done to comply with the different regulations and laws. It is important we keep our workers safe and injury free for our and their peace of mind as well the cost in having incidents. I feel we can make XYZ Company a great, safe place to work if we train our workers to indentify and control hazards as well report all incidents and near misses and we correct and educate staff on those incidents. Also we need to follow all the laws and regulations set out by the federal and provincial government. Doing all…

    • 1575 Words
    • 7 Pages
    Good Essays
  • Good Essays

    6. Lack of resources from contractors – job site will be full of equipment and materials that have yet install. As result would cause equipment shipment would put on hold and delay in deliver date. Also equipment will not able to install on time due to negotiation with equipment technician specialist…

    • 1078 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    Take reasonable steps to safeguard health and safety - When conducting site visits ensure that I have taken measures to have the correct personal protective equipment and ensure that others on site are safety. For example on 12 Julius Terrace, when conducting a site visit I completed a site specific safety plan and also conducting job safety analyses before visiting site.…

    • 400 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    This assignment was to investigate the constructor’s role so I want to talk about that a little bit. After learning about how this project failed I realized how important it is for construction managers to have a basic understanding of structural design. Had the construction manager on this Hartford Civic Center job understood the need for a structural engineer I might not be writing this paper. How he overlooked the deflection is shocking, that is a huge red light to get some structural help, especially on a job of this magnitude. In looking at the construction process a little broader than that of the construction manager; everyone involved, from the architect and engineer, to the sub-contractors doing the labor need to group together and work as a unit so failures like this don’t occur. It seems like there was a huge lack of communication between parties involved. Communication is a huge part of achieving and accomplishing a project successfully. This cannot happen or problems and failures like this will…

    • 882 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Take actions to deal with the results of delays, bad weather, or emergencies at construction site.…

    • 893 Words
    • 4 Pages
    Good Essays
  • Better Essays

    Construction sites are dangerous, and many accidents can occur. Each day on a work site, construction workers are subject to many tasks and pieces of equipment that can put their lives in danger. Workers are asked to work with heavy equipment and powered vehicles, such as forklifts (Powered vehicles), cranes and other heavy duty equipment, (OSHA, 2010). With all of the activities that occur on a construction site, accidents due to falls are the number one threat to construction workers on a work site, (OSHA, 2010). The U.S. Occupational Safety & Health Administration (OSHA) states that falls are the number one cause of construction injuries and deaths, (OSHA, 2010). Falls are the leading cause of deaths in the construction workplace. From 1995 to 1999 with an average of 362 fatal falls occurred; this trend is on the rise, (OSHA, 2010). OSHA states that it is important that safety and health programs have steps or measures to protect construction workers from falls on sites. Most fall-related injuries occur from unprotected side walls, wall openings, floor holes, not using scaffolding correctly, unguarded protruding rebar and not using ladders correctly, (OSHA, 2010). Falls from a height or from an elevation will count towards one third of all deaths in construction. Majority of construction work is conducted above ground, several stories in the air. Leading cause of falls are due to construction companies not having or utilizes the safety program that works towards a reduction in fall related accidents, (OSHA, 2010).…

    • 1241 Words
    • 4 Pages
    Better Essays
  • Satisfactory Essays

    Review each of the following scenarios and identify the risk events, the probability of those risks, and the impact of the risk events. Some scenarios may have more risks than others.…

    • 409 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    It is too difficult and unrealistic for the contractor to impact a delay into the construction programme without knowing the extent of the delay for example if a long lead item is delayed the contractor will have no idea on when the procurement item is due to arrive, the extent of the duration could affect the critical path in different ways…

    • 468 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Konopnicka Airport Case

    • 508 Words
    • 3 Pages

    Polish Airports agreed on repaying the loan on a monthly basis within 10 years. The loan repayment will at the moment Laumann finished the total construction. Weber-Merkel is authorized to collect the take-off and landing charges from foreign airlines, and the overflight fees. However, the bank is obligated to pay back excess charges and fee to Polish Airlines every month.…

    • 508 Words
    • 3 Pages
    Good Essays
  • Best Essays

    CAUSES OF DELAY

    • 4534 Words
    • 19 Pages

    investigation into the factors which cause delay in construction projects in Iran. In that study, eleven in-depth…

    • 4534 Words
    • 19 Pages
    Best Essays