Critical Analysis of the Clift Village Shopping Centre Project Management Plan Essay Example
Critical analysis of the Clift Village Shopping Centre Project management plan

1/31/2011

Executive Summary
This paper has been prepared to critical analyse the project management plan (PMP) of the Clift Project Village shopping centre barrier guard upgrade. The shopping centre multistorey car park was audited by its public liability insurer and they deemed the perimeter barrier fence not compliant to Australia standards and a danger to the public, the fence had to be replaced with a complaint fence. TJA was approached to fix the problem which it completed with an Ingal anti-climb system with an integrated car barrier.
The paper discuss the need and justification of the PMP for this construction project, areas that are discussed further in this paper are the audiences of the PMP and why they need to sight the PMP, the major stakeholder, the project owner (Village Investments) is found to be the main audience for this projects as the project owner needs to approve the PMP for the project to continue. In the last section of the body of the paper, it identifies the PMBOK guide as the base of the structure and contents of the PMP, it identify the PMBOK’s nine functions of project management are in the Clift’s PMP in some way with the major function having a lot more detail put into them. The major functions discuss were scope, time, cost, HR, quality and procurement management. One major lesson to be learnt is in the HR management plan with the stakeholder analysis, the school next to the car park was not inputted into the analysis and issues occurred with the closure of the access point to the school, the project anger needs to spend more time on external orientation of the stakeholder analysis to reduce issues in the future. The project manger had a simple PMP that was useful within the budget restraints and time allocated to prepare it, if more time was allowed in preparing this plan some issues during the project may have been reduced or stopped.

You May Also Find These Documents Helpful

  • Powerful Essays

    CIS590: Project Plan Paper

    • 4496 Words
    • 18 Pages

    The purpose of this document is to define the scope of the project, assign a Project Manager (PM), define the scope of authority and responsibilities of the PM, identify the project team and its functions and responsibilities, indicate the sources of funding and key stakeholders, and outline oversight and governance organizations. This document also lays the groundwork for decisions and planning regarding project direction, outcomes, and delivery. Upon approval of this project plan, work will be initiated on the project and the necessary resources will be committed to achieve project success.…

    • 4496 Words
    • 18 Pages
    Powerful Essays
  • Powerful Essays

    completed. This resulted in the project commencing prior to the full scope of works being…

    • 1250 Words
    • 5 Pages
    Powerful Essays
  • Satisfactory Essays

    1. Ateck’s PMO was created to standardize the management of projects that created as an impact of the changes in environment that comes in many scales. Another purpose of PMO is to improve the planning productivity and Ateck’s initiatives performance. In 2007, PMO was built to supporting the office establishment and present the value of the company. PMO also need to found the benefits from the projects which are: cost reduction, and improvisation in new products management. In progress, PMO also provide consulting and monitoring in functional areas and personnel in order to establish, publish, and disseminate projects standards and tools. PMO also will be implemented from the lowest level in company until the top level.…

    • 417 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    PROJ 587 Week 5 Case Study

    • 2250 Words
    • 6 Pages

    The Case Study for PROJ587 will place the student in the role of a senior manager in charge of one of your company’s Strategic Business Units (SBU). Your first task in this new position is to develop a project portfolio management process and then use this process to select projects for your SBUs portfolio. The Case Study will involve the application of the tools and techniques of multi-project/program management and will deal with the analysis and establishment of project management systems based on the structure of the project.…

    • 2250 Words
    • 6 Pages
    Powerful Essays
  • Better Essays

    It301 Unit 5

    • 1300 Words
    • 6 Pages

    Project Management Institute. A Guide to the Project Management Body of Knowledge(PMBOK-Guide)– Fourth Edition (2008).…

    • 1300 Words
    • 6 Pages
    Better Essays
  • Better Essays

    The goal the paper is to provide a description of the managerial processes of project management. The paper will provide an overview of the project which is Access One’s Annual Blizzard. The paper will identify the primary goals of the project and show why the Blizzard is a project and not just the organizations day to day work. A description of the organizations structure will be included too identify how the project bodes with the organization. The paper will also provide the pros and cons the project has on the organizational structure. The paper will conclude by…

    • 1004 Words
    • 5 Pages
    Better Essays
  • Satisfactory Essays

    Project Management

    • 289 Words
    • 2 Pages

    Apply the project management concepts discussed in Weeks 1–3 to this project. This information will also be used in next week’s individual…

    • 289 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Matrix Template

    • 756 Words
    • 4 Pages

    GenRays Matrix Template Project Management Knowledge Areas|Recommended Tool(s)|Justification for Tool| Project Integration Management | Expert Judgment|-PM Plan is Formal, single document, approved (becomes officially the project plan. It defines how project is executed and controlled. Scope, schedule, and Cost, Change, and Configuration Management plans are created in this process and are part of the PM plan- Scope Management plan is developed here as well.| Project Scope Management | -Interviews -Focus Groups -Facilitated Workshops -Group Creativity Technique -Group decision making techniques -Questionnaires and Surveys -Observation(Job Shadowing) -Prototypes| Facilitated Workshops examples: JAD and Quality Function Deployment Group Creativity Technique examples: -Brainstorming -Nominal Group Technique: enhances brainstorming with voting process -Delphi Technique-Idea and Mind Mapping -Affinity Diagram: large numbers of ideas to be sorted into groups Group Decision making technique -Unanimity: everyone agrees on single course of action -Majority: support from more than 50% of the members of the group -Plurality: the largest block in a group decides even if a majority is not achieved Dictatorship: one individual makes the decision for the group| Project Time Management| -Bottom- up Estimating -Expert Judgment -Alternative Analysis -Published Est. Data -PM Software| Bottom-up estimating: Breaking down complex activities into pieces. -Published Est. Data: Published data as books and journals -Alte. Analysis: means considering several different options for how to assign resources| Project Cost Management | -Analogous Estimating -Bottom-up Estimating -Parametric Estimating -Cost of Quality -Vendor Bid Analysis -Reserve Analysis -Expert Judgment -Three-point estimates -PM estimating software| -Cost of quality: Cost that is incurred to achieve required quality -Rough order of magnitude: As the project moves, estimates should become more accurate -Direct Costs: Costs…

    • 756 Words
    • 4 Pages
    Satisfactory Essays
  • Better Essays

    PMBOK (2004) 3rd Ed. A guide to the project management body of knowledge, Project Management Institute.…

    • 1943 Words
    • 8 Pages
    Better Essays
  • Best Essays

    According to A Guide to the Project Management Body of knowledge (PMBOK Guide), Third Edition, “Project Management is the application of knowledge, skill, tools, and techniques to a broad range of activities in order to meet the requirements of a particular project. Project management is comprised of five basic Project Management Process groups and nine knowledge areas that are typical of almost all projects. The five process groups are Initiating, Planning, Executing, Monitoring and Controlling and Closing process. The nine Knowledge areas center on management expertise in Project Integration Management, Project Scope Management, Project Time Management, Project Cost Management, Project Quality Management, Project Human Resource Management, Project Communications Management, Project Risk Management, and Project Procurement Management.…

    • 1130 Words
    • 5 Pages
    Best Essays
  • Powerful Essays

    Orion Shield Project

    • 5525 Words
    • 23 Pages

    1.0 Project Integration Management …………………………………………………………………….. 3 2.0 Project Scope Management ……………………………………………………………………………... 4 3.0 Project Time Management ……………………………………………………………………………..… 4 4.0 Project Cost Management …………………………………………………………………………….….. 5 5.0 Project Quality Management ………………………………………………………………………….… 5 6.0 Project Human Resource Management …………………………………………………………….. 6 7.0 Project Communications Management …………………………………………………………….. 6 8.0 Project Risk Management …………………………………………………………………………………. 7 9.0 Project Procurement Management ………………………………………………………………….. 8 Section Two: Ethical Issues ……………………………………………………………………………………………… 8 Section Three: Legal and Contractual ………………………………………………………………………………. 9 Section Four: Recommendations ………………………………………………………………………………………10 Section Five: Responses to case study questions ………………………………………………………………11 References ………………………………………………………………………………………….…………………………….15…

    • 5525 Words
    • 23 Pages
    Powerful Essays
  • Powerful Essays

    Team PMP

    • 3308 Words
    • 9 Pages

    Project management is an important undertaking when it comes to the issue of implementing any projects may they be developmental, scientific or even technological. This is because in so far as the success of any project undertaking, there has to be a plan and a premeditated road map as the activities and measures that have to be taken into consideration when executing a project. Before delving into the full address of this essay, it is important to have some of the key words defined as they are used. Firstly, a project in general terms is a plan to design to promote the wellbeing of community. It is an undertaking by a person or a group of person with a view to address a certain challenge pertaining to the living condition of people in a given area.…

    • 3308 Words
    • 9 Pages
    Powerful Essays
  • Best Essays

    The essay discusses basic prices of project management. The first part tackles the initial technical aspect of project planning where scheduling is done to determined logical flow of activities. At this stage, a critical path is determined and project is visualised using Gantt chart and network diagram. Importance of network diagrams is also discussed. The second case discusses general skills and competencies that are needed to successful project management. A range of skills are classified by various authors. In this article, skills that are discussed include technical, communication, people management, and leadership and motivation skills.…

    • 3148 Words
    • 13 Pages
    Best Essays
  • Good Essays

    Risk management is a crucial step of the project planning stage that continuously evolves throughout the project. During phase one of the case study this stage is considered a high importance and value step thus resulting in the proper planning of the risks based of off the WBS. The objectives of phase one are clearly identified and the intention to identify major risks of the project, which will be used as a baseline when comparing each individual tender to the project’s risk outcomes, is clear and all major steps to do so are taken. Step one of the creating the tender phase one case study calls for the “project structure to be reviewed with the project manager and key staff” and creating “an agreed risk WBS”.…

    • 1084 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Stakeholder Management

    • 723 Words
    • 3 Pages

    The idea of project management has emerged as early as an when human started construct and build massive structure such as ancient pyramid in Egypt (Nicholas, 2001). Thus, the modern project management discipline nowadays has been around for a more than sixty years (Camci and Katnour, 2006). Since then, Project Management has become vast towards its own field, whereby supported by bodies of knowledge and researches under PMI (Project Management Institute). Project Management itself has many versions of definition, one of the noted is Project Management that can be defined as “the application of skills, knowledge, tools and techniques to meet the needs and expectations of stakeholders for a project” (Mathur, 2006). The word “stakeholder” itself indicates how important it is to manage them in order to achieve project success. It is commonly accepted perception that a project is successful when it is finished on time, within budget, in accordance with specifications and to stakeholders’ satisfaction. Thus it is also important to manage stakeholder. According to PMI (2000), project stakeholders are the individuals or organizations actively involved in the project, whose interest in it are positively or negatively affected by the project execution or the successful…

    • 723 Words
    • 3 Pages
    Good Essays