Cost & Schedule Week 5
Problems 5-1 through 5-2 (Graded) 5-1 Earned Value Calculation You are 4 months into a 6 month project. The project is linear, which means that the progress and spending occurs at a constant rate. Our crack project team of highly skilled associates has worked diligently and put in extra hours to keep the project going. Our accounting department has provided the following data at the end of month 4: Actual cost to date = $79,800 (This is what I actually spent by the end of month 4) Planned expenditures to date = $101,000 (This is what I should have spent by the end of month 4) The CFO is excited and has sent you an email congratulating you for being 12.07% under budget. However, is it really time to hold a team celebration? That would be fun but your project manager mentality kicks in. Those numbers look good but how are we ‘really’ doing? To understand the true project performance, we need to apply earned value techniques. The missing piece we need is Earned Value (i.e. what we have actually accomplished so far). You meet with your team and find that only 6 of the 7 tasks scheduled to be complete by the end of month 4 have actually been completed. Task 7 isn’t even started! This information gives you the final data you need to apply ‘Earned Value’ and develop an objective analysis. IMPORTANT: Use 2 decimal places when calculating % complete, that is .XX. And be sure to round properly. 1. What are the PV, EV, and AC for the project at the end of month 4?

PV=BCWS= | 101,000 | | AC= | 79,800 | | EV=BCWP= | (6/7)*101,000= | 86,860 |

2. What are the SV, CV, SPI, and CPI for the project? Provide CPI and SPI to 2 decimal places rounding properly.

SV=BCWP-BCWS= | 86860-101000= | (14140.00) | CV=BCWP-ACWP= | 86860-79800= | 7060 | SPI=BCWP/BCWS= | 86860/101000= | 0.86% | CPI=BCWP/BCWS= | 86860/79800= | 1.09% |

3. Assess the project performance to date? Do you get to have the celebration?

From observing this task,

You May Also Find These Documents Helpful

  • Powerful Essays

    PROJ 592

    • 2367 Words
    • 10 Pages

    An Earned Value analysis reflected that the project is currently behind schedule. The schedule variance (SV) indicated a negative $565,226.34 and the scheduled performance index showed as .69. When SV is a negative number and SPI less than one, this indicates the project is behind schedule. After calculating the CPI/SPI value (1/.69= 1.45), any values above 1.3 should be investigated immediately, because those numbers are much too good to be true. In addition based on the Work Breakdown Structure the total duration was 6 days behind schedule. The new completion date in the WBS also indicates that the schedule completion date currently is 10days behind schedule.…

    • 2367 Words
    • 10 Pages
    Powerful Essays
  • Satisfactory Essays

    Nt1310 Unit 4

    • 555 Words
    • 3 Pages

    a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?…

    • 555 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Hrm/531 Week 4

    • 643 Words
    • 3 Pages

    This assignment is based on an Earned Value analysis performed by a cost account manager, who has received a variance report (given below) from a performance measurement system. I have calculated the appropriate variances and included corrective measures for each of them.…

    • 643 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Ilab Week7

    • 297 Words
    • 2 Pages

    According to the Project summary, this project is currently on schedule. The project summary is currently indicating that the project is coming in under budget by $1,720.00.…

    • 297 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    QAT1 Task 4

    • 501 Words
    • 7 Pages

    QAT1 Task 4 Western Governors University ID# A. Company A 1. Determine expected completion times for each project activity. T= (Optimistic + 4Probable + Pessimistic)/6 A. T=(2 + 4(3) + 4)/6 –OR -- T=3 B. T=(5 + 4(6) + 13)/6 –…

    • 501 Words
    • 7 Pages
    Satisfactory Essays
  • Powerful Essays

    PT2520

    • 1263 Words
    • 7 Pages

    Upon completion of the project, you will submit a MS Word document with the answers to the three questions integrated within the project at key points. Questions 1 & 2 are located at the end of Step 11 and Question 3 at the end of Step 12 of the Technical Steps section of this lab. This MS Word document will be named nn_Projectanswers.doc where “nn” will be changed to your initials.…

    • 1263 Words
    • 7 Pages
    Powerful Essays
  • Satisfactory Essays

    · Overall evaluation of the project: In particular, how did you do against the triple constraints?…

    • 474 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    Est1 Task 3

    • 1740 Words
    • 7 Pages

    When considering the expenditure for the month of March the amount seems to be on target. However, when compared to the amount of money spent year to date there is a discrepancy. The amount spent year to date is $150,000. If…

    • 1740 Words
    • 7 Pages
    Good Essays
  • Good Essays

    consumption plan? Outline your sources and uses of funds for date 0 and date 1.…

    • 671 Words
    • 3 Pages
    Good Essays
  • Better Essays

    expenses the company expects to pay out over the same time frame. The issues surrounding budgetary…

    • 904 Words
    • 5 Pages
    Better Essays
  • Satisfactory Essays

    JDT@ task 1A

    • 625 Words
    • 2 Pages

    Gannt Chart and/orWBS Create a gannt chart and list all the projects, the estimated time to completion as well as estimated cost. List each part of the project and give it a time line on the chart. Using this you can track it daily, weekly, monthly, or whenever you wish. Could also use a WBS to breakdown the projects and put a time line on each part of the project to show how each team member worked on it. Using this will show you how close you can get to being finished by year end as the case study states it was finished 6 months early.…

    • 625 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Week 5 TCO F Project Monitoring and Control Project Management for Business, Engineering and Technology Chapter 11: Project Execution and Control (pp. 404-444) Earned Value Project Management Chapter 1: If Earned Value is so hot... (pp. 1-4) Chapter 2: Earned Value Project Management (Introduction) (pp. 5-13) Chapter 3: Earned Value Project Management (Overview) (pp. 15-25) Chapter 5: The Earned Value Body of Knowledge (pp. 35-46)…

    • 390 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Managerial Accounting

    • 380 Words
    • 2 Pages

    The reduction in downtime would have to have a present value of at least $11,816 in order for the project to be acceptable.…

    • 380 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Acc/291 Week 3

    • 627 Words
    • 3 Pages

    granted for the product on July 1. Its useful life is equal to its legal life.…

    • 627 Words
    • 3 Pages
    Satisfactory Essays
  • Better Essays

    It is difficult to have a clear understanding of how the work was spread out. So it is management’s task to have a system in place that provides a fair understanding of what is expected from the team. Team appraisal systems require that each individual be responsible for their own contribution. Although, the team is appraised as a whole, individuals should hold it their responsibility to contribute fairly. Another necessity in team would be to allow team members evaluate each other. Each member knows exactly what he/she contributed so therefore they can rate other members of the team depending on their…

    • 1967 Words
    • 8 Pages
    Better Essays

Related Topics