Preview

Employing Lag Relationships

Satisfactory Essays
Open Document
Open Document
310 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Employing Lag Relationships
Robert Davenport
EC311
Mr. Manprisio
May 30, 2012
EMPLOYING LAG RELATIONSHIPS
Lag Relationships are put in place to help more properly setup forward steps within projects. This concept is introduced early on into any project as deliverables are being handed out for completion. This concept creates an environment more appropriate for creating the project timeline so project objectives are started and finished in the correct sequence. 1. Finish to Start a. The most common type of logical sequencing between tasks is referred to as the Finish to Start Relationship. An example of a delay would be if three activities are linked in a serial path, activity number 3 cannot begin until the scheduled task from activity number 2 is completed in full. 2. Finish to Finish b. Finish to Finish relationships require that two linked activities share a similar completion point. An example would be in a 10 step/activity project, some of the steps may have the same completion point, i.e. steps 4 and 5. This means you do not need to wait until step 4 is completed prior to starting step 5, you can work them at the same time and complete them on the same completion date. 3. Start to Start c. Often two or more activities can start simultaneously or a lag takes place between the start of one activity after an earlier activity has commenced. An example would be in a project when one activity can be labeled a ‘burst point’ to multiple successor activities. 4. Start to Finish d. Perhaps the least common type of lag relationship occurs when a successor’s finish is dependent upon a predecessor’s start. An example of this is when you are building a house, you cannot pour the concrete into the foundation ditch until the entire area is cleared out of groundwater and all drainage is

You May Also Find These Documents Helpful

  • Powerful Essays

    PROJ 586 Final Exam

    • 872 Words
    • 4 Pages

    6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time.…

    • 872 Words
    • 4 Pages
    Powerful Essays
  • Satisfactory Essays

    What is the slack time (float) for activity A? (1 points) d) What is the slack time (float) for activity D? (1 points) e) What is the slack time (float) for activity E?…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    proj 598 quizz

    • 821 Words
    • 4 Pages

    All these four process interact with each other and with other process in other knowledge areas in a project.…

    • 821 Words
    • 4 Pages
    Satisfactory Essays
  • Best Essays

    Is3350 Unit 1 Assignment

    • 3307 Words
    • 14 Pages

    In order to calculate the timing of an activity ‘Duration’ of the activity needs to be summed up with the ‘Earliest Finish…

    • 3307 Words
    • 14 Pages
    Best Essays
  • Powerful Essays

    Brs Mdm3 Tif Ch07

    • 2550 Words
    • 19 Pages

    4) Refer to the figure. What is the slack time, in days, associated with activity D?…

    • 2550 Words
    • 19 Pages
    Powerful Essays
  • Powerful Essays

    Sutter Medical Center Case

    • 1363 Words
    • 6 Pages

    In the Sutter Medical Centre project, project managers organised each task based on the progression of events, so each section and trade can complete their work with a timetable to abide to.…

    • 1363 Words
    • 6 Pages
    Powerful Essays
  • Powerful Essays

    ____ 6. A(n) ________ path for a project is the series of activities that determine the earliest time by which the project…

    • 2493 Words
    • 10 Pages
    Powerful Essays
  • Satisfactory Essays

    Mat 540 Quiz

    • 819 Words
    • 4 Pages

    Pioneers McCulloch and Pitts built their neural networks model using a large number of interconnected __________ artificial neurons.…

    • 819 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    Supporting Activity

    • 653 Words
    • 3 Pages

    Start-to-Start: this represents a true relationship between two activities and has nothing to do with their predecessors. If I happen to have two tasks that start at the same time because of a predecessor, that is better represented as two finish-to-start relationships (e.g. systems testing & developing documentation can both begin once development is complete, but there is no relationship between systems testing & developing documentation so we wouldn’t want to use a Start-to-Start dependency here). This dependency is often used with a lag to represent the connection between two activities that run in parallel but cannot start at exactly the same time (e.g. apply the first coat of paint & apply the second coat of paint). A true Start-to-Start example is a race between two runners where each runner is represented as a separate activity – while they will likely finish at different times, both must start at exactly the same time.…

    • 653 Words
    • 3 Pages
    Good Essays
  • Good Essays

    PROJ 586 Final Exam

    • 814 Words
    • 4 Pages

    6. (TCO C) If _____ is positive, it represents the maximum amount of time that the activities on a particular path can be delayed without jeopardizing the completion of the project by its required completion time.…

    • 814 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    4. Identify activities that have slack times and also indicate how long the slack times are.…

    • 335 Words
    • 8 Pages
    Satisfactory Essays
  • Good Essays

    Final Exam DB

    • 2715 Words
    • 11 Pages

    precedes every operation of the other. (Note, the schedule may not be serial.) Give an example of…

    • 2715 Words
    • 11 Pages
    Good Essays
  • Satisfactory Essays

    A series of defined activities/steps that should lead to solving a problem, these activities include:…

    • 989 Words
    • 6 Pages
    Satisfactory Essays
  • Powerful Essays

    Project Communication

    • 973 Words
    • 4 Pages

    • Timeline: the task timeline is the element of a project status report that often gets the most…

    • 973 Words
    • 4 Pages
    Powerful Essays
  • Good Essays

    Past Tense and Certain Time

    • 2711 Words
    • 32 Pages

    http://www.learnenglish.de/englishtestspage.html Table of English Tenses Tense Simple Present Affirmative/Negative/Question A: He speaks.…

    • 2711 Words
    • 32 Pages
    Good Essays

Related Topics