Contents
Title page
Contents pages
1.0 Project introduction and background
2.0 Project approvals required
3.0 Site location
4.0 Site geology
5.0 Project description of old system
5.1 Inlet
5.2 Three clarifiers
5.3 Digesters
5.4 Sludge bags
5.5 Three trickle filters
5.6 Settling lagoon
6.0 Additions and conversions
7.0 Project description of new system
7.1 Inlet
7.2 Storage tanks
7.3 Bioreactor
7.4 Two clarifiers
7.5 RAS pump station
7.6 Aerobic digester
7.7 Sludge press
7.8 Three sand filters
7.9 Chlorine holding tanks
7.10 Settling lagoon
8.0 Materials used on site and their sources
8.1 Concrete
8.2 Steel
8.3 Chlorine
8.4 PP and PVC (pipes, valves)
8.5 Filter bed material (rocks, gravel, sand)
8.6 Pumps and compressors
9.0 Construction methods used
9.1 Excavation and landscaping earthworks
9.2 Formwork and scaffolding
9.3 Steel reinforcement
9.4 Drilling and blasting
9.5 Piling
9.6 Hoisting and fitting
10.0 Plant used
10.1 Shovel bucket
10.2 Backhoe
10.3 Grader
10.4 Tamping foot roller
10.5 Truck
10.6 Crane
11.0 Management structure of the project
11.1 Preliminary investigation and final project definition
11.2 Planning and design
11.3 Contracting, construction and operation
12.0 Safety, environmental and traffic management
12.1 Safety management
12.2 Environmental management
12.3 Traffic management
13.0 Particular points of interest
14.0 Particular problems encountered on the project
15.0
References: Queensland Concrete & General Construction Co. Pty. Ltd. 2009, Nambour Representatives of the Queensland Government, Nambour, Queensland, viewed 4 May 2010, <http://www.qcgc.net.au/>.