Preview

MGT 5211 Case II Questions Answered

Better Essays
Open Document
Open Document
1374 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
MGT 5211 Case II Questions Answered
Bisk College of Business: Extended Studies -- National Capital Region Site

MGT 5211 PROCUREMENT AND CONTRACT MANAGEMENT
Case No. 2 – Contract Issues
Instruction Sheet

Questions: 1. Given the difficult situation identified in this case, describe what you see as factors that contributed to the problems encountered by both parties.
A: 1) Poorly defined requirement. The specifications were not fully developed. Offerors are unable to provide a comprehensive quote for a poorly defined requirement.
2) Pressure from leadership. Interagency politics and lack of planning resulted in this procurement being somewhat rushed. Current year funds expiring and senior manager eagerness are not appropriate factors to force a contract specialist to consider.
3) The Agency did not advertise. There is not statement as to why the agency did not advertise. While competition was still sought the agency may have received better questions from interested vendors if it had advertised the requirement.
4) Selection Criteria – The scenario indicates the main reason the vendor was selected was that it performed other work on the system. FAR Part 15 notes many factors the evaluation team should consider.
5) Quality Assurance – No clear quality control plan was required in the contract. No agency approvals were contained in the contract terms which precluded the contractor from starting a new phase of the project. No acceptance testing procedures were included. The terms for quality control and acceptable performance are very vague.
2. Also identify the phase(s) in the contracting process where these factors originated and describe what actions could have been taken in each of the phases identified to prevent these problems from occurring.
A: 1) Poorly defined requirement. This should be addressed by the Gov’t in the acquisition planning phase before contracting is involved. If the program manager cannot fully understand what is required she should work with the technical team to fully

You May Also Find These Documents Helpful

  • Good Essays

    Mgmt 594 Course Project

    • 2448 Words
    • 10 Pages

    On behalf of American Pole and Timber (APT), I am pleased to present the National Guard Bureau with our response to Solicitation No. W912J313T0012. American Pole and Timber is currently registered in the System…

    • 2448 Words
    • 10 Pages
    Good Essays
  • Satisfactory Essays

    CTS 115 Chapter 10

    • 1106 Words
    • 4 Pages

    Security was not included and would need to be addressed. Feasibility is also not covered, which would include the schedule, technical and organizational aspect of the project.…

    • 1106 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    CIS 517 Assignment 2

    • 252 Words
    • 2 Pages

    2. Discuss the role of the project manager or team, the organizational setting, the recipient’s approach to project integration management, and obstacles that had the potential of adversely impacting the triple constraints.…

    • 252 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    Lowes

    • 916 Words
    • 4 Pages

    1. State the problem symptoms identified through the situation analysis, leading by logic to identification of the primary problem outlined in the case. The problem statement should identify the probable result of not taking action to correct the problem.…

    • 916 Words
    • 4 Pages
    Better Essays
  • Satisfactory Essays

    Law 531 Memorandum

    • 981 Words
    • 4 Pages

    This memo is in response to the dispute over the contract between Span Systems and Citizen-Schwarz AG (C-S). Management is taking the necessary steps in resolving the issues C-S is reporting of low quality deliverables and schedule delays. C-S is threatening rescission of their contract and demand immediate transfer of all unfinished codes (University of Phoenix, 2002, Legal Environment of Business: Contract Creation and Management, Law 531). C-S must prove a material breach is occurring and give adequate notice to Span Systems to issue a rescission (Cheeseman, 2010). Span Systems and C-S signed a one-year contract worth $6 million dollars that has five clauses for breach of contract and a project structure clause. This memo will identify what management is doing to avoid legal risks, minimize liabilities, and benefit from opportunities presented to make this contract successful.…

    • 981 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    Technology/Performance: Noted above the various precincts have a variety of legacy systems that complicate the integration of their systems into a shared environment. The government has levied on new requirements since the contract was established and those new requirements are outside the scope of the existing contract. The current vendor has been unsuccessful in providing any meaningful capability or solution in almost 5-6 years of effort. Typically in software development it is expected to have functionality available within 18-24 months. This far exceeds this timeframe and is beyond the time this vendor should have been considered for being fired. One of the other aspects not discussed in the case study is the management…

    • 2432 Words
    • 10 Pages
    Good Essays
  • Powerful Essays

    Cass Study

    • 2371 Words
    • 10 Pages

    Question 3: As a procurement officer what lessons can be learnt from this case study and what actions would you put in place?…

    • 2371 Words
    • 10 Pages
    Powerful Essays
  • Satisfactory Essays

    Unit 201 4.3

    • 431 Words
    • 2 Pages

    1. Identify at least two different types of problems that can occur in a business environment.…

    • 431 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    3. Why has the problem or issue arisen – what has led to this situation?…

    • 340 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Au Revoir Mrs.Williamson

    • 845 Words
    • 4 Pages

    1) What are the key problems you have identified in this case (List and briefly explain).…

    • 845 Words
    • 4 Pages
    Powerful Essays
  • Better Essays

    Senior Management

    • 1685 Words
    • 7 Pages

    6) Lack of project ownership from the senior management team – It was only Frank Carau and Ben Walker, who are juniors that are handling the project. It does not have enough clout to direct and influence the project on the senior management levels. However, with the leadership and sponsorship of Phil Faraci, the project came into a turn-around from being a slow-paced to fast-paced project, from being a…

    • 1685 Words
    • 7 Pages
    Better Essays
  • Satisfactory Essays

    free elc

    • 611 Words
    • 3 Pages

    2. Who were the person(s) involved and their responsibilities and how they contributed to the problem.…

    • 611 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Blozis Company

    • 1345 Words
    • 6 Pages

    My Decision is to analyze the current procurement process. And besides the procurement issues it seems there are not clear job descriptions and responsibilities and consequently some roles are overlapping each other creating problems in third party departments such as Accounts Payable.…

    • 1345 Words
    • 6 Pages
    Powerful Essays
  • Satisfactory Essays

    Buried Onions

    • 277 Words
    • 2 Pages

    3. Conflict: Identify and explain a source of conflict from an Act. Consider if and how it is resolved in the Act.…

    • 277 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    9. There was a lack of project management in the organization - Reichart planning was in isolation not involving functional managers where their input was most needed. The project manager reported directly to the operations manager, the appointed assistant programme manager interfered by attempting to install a system that tracked problems. Focus should have been on solving the problems not finding innovative ways to track them, this organisation wasted $50,000.…

    • 1618 Words
    • 7 Pages
    Better Essays