Preview

operation management

Satisfactory Essays
Open Document
Open Document
252 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
operation management
Read the Specialty Contractors case (download) and submit your analysis of the exercise - i.e., identify which activities should be crashed and by how much time, what is the cost of doing this and how soon can the project be completed. (Hint: Use the greedy algorithm taught in class even though it is not guaranteed to always find the optimal solution.) [Please submit your assignment as an attachment.]
Solution:
According to the Specialty Contractors case, we get the critical path is PTV and the project duration is 12 weeks but it will be delayed 4 weeks in the beginning.

Greedy Algorithm:
PTV is critical path in this case. (Duration: 12 weeks)
The cheapest activity to crash on this path is T.
Marginal Crashing Cost = 4,000 $
Marginal Benefit = 9,000 $ (1 week delay reduction)

Now, PTV is still critical path. (Duration: 11 weeks)
Cut activity T by 1 week.
Cost = 4,000 $
Reduction in delay cost = 9,000 $

Then, PS, PTV, and QV are critical paths. (Duration: 10 weeks)
Since T cannot be crashed, we crash P and Q to expedite the project.
Cut activity P and Q by 1 week, respectively.
Cost = 5,000 $ + 6,000 $ = 10,000 $
Reduction in delay cost = 9,000 $
Since the cost is higher than savings, we accept two weeks delay.

Total cost of crashing = 4000 + 4000 = 8000 $
Total cost of delay = 9000 + 9000 = 18000 $ (delayed by 2 weeks)
Total cost of crashing and delay = 8000 + 18000 = 26000 $
To conclude, we cut activity T by 2 weeks. The project can be completed in 14 weeks.

You May Also Find These Documents Helpful

  • Good Essays

    Proj586 Week 4

    • 660 Words
    • 3 Pages

    The budget for the preparation phase is $1,282,442 and the duration of the preparation phase would be 47 weeks.…

    • 660 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    opma 317

    • 395 Words
    • 5 Pages

    Since two weeks were added to task #3 - Obtaining Final Drawings and Building Permits, in order to complete the project in the original normal time with minimal costs, he would crash activities #2, and #1 since these activities would reduce the project by two weeks’ time at a minimal cost of $7000 as shown by our project crashing…

    • 395 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    I a. Construct a network for the project. [pic] Slack or Float = LF – EF or LST – EST Activities on the critical path have zero slack/float. b. Calculate the scheduled completion time and identify the critical path.…

    • 562 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Do we have an allotted time to finish the project, or do we have indefinite time to complete this?…

    • 767 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    Gen 480 Case Study Essay

    • 1222 Words
    • 5 Pages

    Need to increase staffing cost by $250,000 to bring the product to the market on time.…

    • 1222 Words
    • 5 Pages
    Better Essays
  • Good Essays

    Not just that these activities cannot be delayed any further, their total time need to be reduced by at least 1 week so that the project can be finished on time. Following are a few techniques that can be used to cover this 1 week gap:…

    • 708 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    If the project is shorted to 38 weeks, R.C. Coleman will be able to achieve the goal of 80% completion at 40 weeks. R.C Coleman should crash activities to reduce the expected project completion time to 38 weeks.…

    • 656 Words
    • 3 Pages
    Powerful Essays
  • Good Essays

    Operation Management

    • 828 Words
    • 4 Pages

    This exam is to be completed as an individual assignment. Each question is from a corresponding chapter. For example, question 1 is from Chapter 1 and so on. Write 2-3 paragraphs for each of the four questions you choose to answer. In addition to your textbook, you should use and cite at least one other credible source and/or case study for each of the four questions you answer.…

    • 828 Words
    • 4 Pages
    Good Essays
  • Good Essays

    The total duration of the construction project by adding the estimated task duration serially would give us 70 weeks. But some tasks within some activities can be done in parallel sequence or simultaneously, which would significantly reduce the construction project completion time using the critical path method (CPM). In this method the longest path is the critical path which runs through one of the route in the project network diagram from start to finish. This project network diagram is illustrated on the printed assignment page, we have 10 tasks listed from A to J. Below is an activity list of the tasks;…

    • 1246 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    Space Constructors

    • 570 Words
    • 3 Pages

    1. Reduce total project duration as much as possible without unnecessary additional cost. Indicate the new critical path or paths. Show how much slack or float remain in the noncritical paths.…

    • 570 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    able to complete the construction prior to the start of the next season. After activity duration estimates, it now…

    • 564 Words
    • 8 Pages
    Satisfactory Essays
  • Satisfactory Essays

    As the duration of the project is directly dependent on the duration of critical path, we should make the critical path shorter; in this case we need to re-plan the project.…

    • 872 Words
    • 4 Pages
    Satisfactory Essays
  • Powerful Essays

    Gantt Chart Analysis

    • 1192 Words
    • 5 Pages

    The project that I am scheduling will take a lot of time to complete due to the size of the said project, according to the duration of each task that I have been provided with, the project will take at least sixteen months to complete as none of the tasks can be attempted until the tasks previous to it have been completed successfully.…

    • 1192 Words
    • 5 Pages
    Powerful Essays
  • Satisfactory Essays

    Costs and Earned Value

    • 557 Words
    • 3 Pages

    Sketch the earned value chart for this project, using Figure 7- 5 as a guide.…

    • 557 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Proposal

    • 979 Words
    • 4 Pages

    The time allocated to complete this project is 14 days. This will provide 2 ½ days to complete training for each program.…

    • 979 Words
    • 4 Pages
    Powerful Essays