Preview

Operations - Aon and Crash Exercise

Satisfactory Essays
Open Document
Open Document
337 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Operations - Aon and Crash Exercise
1. Convert the project network to an Activity-on-node (AON) representation. What is the project completion time and critical path for this project ?

Critical path is A-B, B-D, D-E

3. Suppose that activity AD were delayed by 2 weeks (takes 8 weeks versus 6). What is the new project completion time and critical path?

A-D already has 2 hours of slack time, therefore if it becomes delayed by 2 hours it will have no impact on the finish time.

4. Suppose that you have extra resources available, but at a cost. Assuming that you can only improve the activity time for a single activity, which activity would you apply these resources to (if any) and how much would you apply (i.e. how many weeks of crash time)? How much profit would SCI earn if you did this? (Assume activity AD takes 6 weeks again).

Apply the crash to activity B-D, since it’s a node on the critical path and the lowest one cost wise to crash. It is also the best in terms of lowering the finish time. Applying 2 weeks of crash time would allow for the project to decrease to 10 weeks instead of 12. 10 weeks seems to be the absolute level allowed that would still improve the overall finish time. Profit would be $3,000.

Normal cost of project ($61,000) – penalty ($18,000) – Revenue ($9,000) – crash cost ($8,000) = Profit ($3,000)

5. Now assume that SCI can apply resources to any activities according. What’s the most profit SCI could earn?

Reduce one week of AB, one week of BD and one week of DE, that way you'd get a completion time of 9 weeks are are able to make a profit of $4,000.

Revenue ($90,000) - Fixed Cost ($61,000) = Gross Profit Margin ($29,000)

Gross Profit Margin ($29,000) - Savings on AB ($5,000) - Savings on BD ($4,000) - Savings on DE ($7,000) - Penalty ($9,000) = Profit

You May Also Find These Documents Helpful

  • Good Essays

    ACC 497 Final Exam

    • 2281 Words
    • 11 Pages

    15) A simple diagram that shows estimated completion times versus actual completion times for the various activities in a systems implementation project…

    • 2281 Words
    • 11 Pages
    Good Essays
  • Powerful Essays

    ____ 6. A(n) ________ path for a project is the series of activities that determine the earliest time by which the project…

    • 2493 Words
    • 10 Pages
    Powerful Essays
  • Satisfactory Essays

    Paper -Econ

    • 385 Words
    • 2 Pages

    Given below is the information for the IT project we discussed in our Week 5 commentary and its network diagram. In the Week 5 commentary, we crashed the project by three days, i.e., from 20 to 17 days by crashing Activity C for two days and Activity F by a day. Now proceeding from here:…

    • 385 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    In order to answer the question above I analyzed what is the actual costs incurred and profits…

    • 1040 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Satelite Problem

    • 506 Words
    • 3 Pages

    I would ask for NOK 222,975,000 for the project. This would include total cost of NOK 178,380,000 plus the desired 25% profit on total costs for all projects.…

    • 506 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    * 2. Answer 1 Total Actual Cost = 21224 Variable Costs for 103= Compensation Insurance+ Direct Labour+ Power+ Materials + Supplies + Repairs – Other Income Total Cost (after dropping 103)= 18712 Total Revenue (after dropping 103) = 16179 Loss= 16179-18712 = 2533 $2.533 million Loss…

    • 272 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    Greendale Stadium Case

    • 1281 Words
    • 6 Pages

    If the total project time has to be reduced, the length of the critical path has to be shortened. The length of critical path is equal to the sum of durations of critical tasks. Here, it is equal to 695 days. Any delay of a critical task will delay the entire project.…

    • 1281 Words
    • 6 Pages
    Better Essays
  • Satisfactory Essays

    This chart states that the critical path is A, D, E, F, G, O. Therefore the project will be completed in 34 weeks.…

    • 622 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Project Management Models

    • 989 Words
    • 4 Pages

    A project defines a combination of interrelated activities that must be executed in a certain order before an entire task can be completed. Project management has evolved as a field of study, with the development of two analytical techniques for planning, scheduling, and controlling projects. These techniques are the project evaluation and review technique (PERT) and the critical path method (CPM). The purpose of this exercise is for the student to appreciate project planning issues and the application of PERT\CPM techniques. Please answer the following questions.…

    • 989 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Group Presentation

    • 467 Words
    • 6 Pages

    ACC 208 Group 8 PROBLEM 5-20A Requirement 1 Compute the company’s CM ratio and its break-even point in both units and dollars. CM Ratio= CM / Sales ($270,000 - $189,000) / $270,000 CM Ratio= .30 = 30% Break-even point in units= Fixed Expenses / UCM 90,000 / [(270,000 / 13,500) - (189,000 / 13,500)]= 90,000/6= 15,000 units Break-even point sold in total sales dollars= Fixed Expenses/ CM Ratio 90,000 / 30% = $300,000 Requirement 2 The sales manager feels that an $8,000 increase in the monthly advertising budget, combined with an intensified effort by the sales staff, will result in a $70,000 increase in monthly sales.…

    • 467 Words
    • 6 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Case Responses

    • 488 Words
    • 2 Pages

    With the information provided and the dependencies that I created based on my assumptions, these are the tasks that have more than 8wk slack time:…

    • 488 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    4. Assuming the intracompany demand for service will average 205 hours per month, what level of commercial revenue hours of computer use would be necessary to break even each month.…

    • 812 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    mircoeconomic assignment

    • 547 Words
    • 14 Pages

    Tutorial 7 Question 5 Based on the table below,calculate and fill up the missing values The table below shows the water tumbler production at Drinkware's factory Output (unit Total Fixed Cost (RM) Total Variable Cost (RM) Total Cost (RM)…

    • 547 Words
    • 14 Pages
    Satisfactory Essays