Preview

Paper -Econ

Satisfactory Essays
Open Document
Open Document
385 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Paper -Econ
Crashing Projects Exercise
Given below is the information for the IT project we discussed in our Week 5 commentary and its network diagram. In the Week 5 commentary, we crashed the project by three days, i.e., from 20 to 17 days by crashing Activity C for two days and Activity F by a day. Now proceeding from here:
Activity ID Predecessor Normal Time
(Days) Crash Time
(Days) Normal Cost Crash Cost ($'000) ($'000)
A - 5 2 $100 $205
B - 6 3 $140 $205
C - 7 5 $140 $200
D A, B 6 2 $100 $340
E C 3 1 $120 $200
F C 8 5 $580 $700
G D, E, F 5 3 $400 $660
Note: A "fully crashed schedule" means a project that has been crashed until the cost of crashing exceeds the marginal gain associated with eliminating overhead cost (which is $100,000 per day for this project). o Continue crashing the project until the cost of crashing exceeds the marginal gain associated with eliminating overhead cost ($100,000 per day). o Assume you have begun the project under the fully crashed schedule and you are now at the end of Day 6. Tasks A and C are finished, but Task B will require two more days of work. What corrective crashing decisions might you make to increase the likelihood that you can complete the schedule within the remaining 14 days? Are there any tasks you might consider uncrashing? What other actions could you consider?
Submission: You must submit your answers to this exercise in the form of a single word document. You may cut and paste your excel work on this word document. Name your file as: LastName_FirstName_CrashingProjectExercise.docx

Activity ID Predecessor Normal Time (Days) Crash Time (days) Normal Cost Crash Cost Crashed Days Days Available Crash Cost/Day
A 5 2 $ 100.00 $ 205.00 0 3 $ 35.00
B 6 3 $ 140.00 $ 205.00 1 2 $ 21.67
C 7 5 $ 140.00 $ 200.00 2 0 $ 30.00
D A,B 6 2 $

You May Also Find These Documents Helpful

  • Satisfactory Essays

    QAT1 Task 4

    • 501 Words
    • 7 Pages

    Expected Time to Complete Normal Cost Crash Cost Maximum Reduction in Time Crash Cost per week Normal (weeks) Crash (weeks) START A 3 2 $ 8,400 $ 11,200 1 $ 2,800 B 7 5 $ 28,000 $ 40,000 2 $ 6,000 C 4.5 3 $ 18,000 $ 24,000 1.5 $ 4,000 D 11.5 7 $ 36,800 $ 44,800 4.5 $ 1,778 E 5 3 $ 14,000 $ 16,800 2 $…

    • 501 Words
    • 7 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Ops/571 Final

    • 549 Words
    • 3 Pages

    11- WHAT IS THE NET RESULT OF REDUCING THE DURATION OF A TASK (CRASHING) NOT ON THE CRITICAL PATH?…

    • 549 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Ops 571 Final

    • 433 Words
    • 2 Pages

    What is the net result of reducing the duration of a task (crashing) not on the critical path?…

    • 433 Words
    • 2 Pages
    Good Essays
  • Good Essays

    Periodic inventory only sales recorded when inventory is sold. CMS is determined at the end of the accounting period…

    • 717 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Nhs It Project Report

    • 3047 Words
    • 13 Pages

    In this report, we will look through the stages of the project and figure out how a potentially successful IT project can turn out to be a disastrous failure.…

    • 3047 Words
    • 13 Pages
    Powerful Essays
  • Good Essays

    W4 Hw Ev

    • 534 Words
    • 3 Pages

    In this homework assignment, you will be working through two crashing problems and four earned value problems. All the information you need is included within this Homework packet. Make sure you answer all parts of the questions in their entirety.…

    • 534 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Econ 333 Paper

    • 4024 Words
    • 11 Pages

    According to the United Nations Economic and Social Council, Ethiopia is considered one of the forty-eight least developed countries (LDC). The list of LDC are looked over every three years and this list was recently updated in March 2012. To be considered a least developed country, the Committee for Development takes into consideration these three factors:…

    • 4024 Words
    • 11 Pages
    Powerful Essays
  • Better Essays

    This particular case is related to chapter 14 of our textbook. This chapter deals with project closure or what to do when your project is done. Although here our project is not done, these chapters discuss the main reason why it is so. It is said on page 505 of the textbook, “the closure phase is as important as any other phase of the project. Observation tells us that organizations that manage closure and review well prosper. Those who don’t tend to have projects that drag on forever and repeat the same mistake over and over”. It is said in our case that this project is not the first one Olaf and his company as difficulty with. Matter of fact, there were three other projects that could not be completed in the last 5 years. The CEO kept on investing resources into these projects knowing that they were dead end. We can therefore, affirm that Olaf did not learn from his mistakes. He needs to include in his future plan of action a review stage after each project completion. Here, we seem to have a “perpetual” project which is a never ending project. For instance, completing this project will take 6 additional months when it is already 4 months late. Also, this project initially demanded $600,000 and now requires $800,000 more. The team faces numerous issues such as power reduction, speed increase and use of a new technology battery.…

    • 993 Words
    • 4 Pages
    Better Essays
  • Satisfactory Essays

    Econ 305 Question Paper

    • 418 Words
    • 2 Pages

    a) Suppose that the money supply M=1000 and that the expected price level Pe=50. What are the short run equilibrium values of output Y, the price level P, and the unemployment rate u? What are the long run equilibrium values of these three variables?…

    • 418 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Econ 100a Question Paper

    • 3240 Words
    • 13 Pages

    Problem 2. (24 points total) Consider a perfectly competitive industry with 10 identical firms, each of which has variable costs of 10y 2 and fixed costs of 1000. We will define the short run as the time scale in which firms cannot enter or exit the industry, and cannot avoid their fixed costs. (In other words, in the short run firms must continue to pay their fixed costs even if they produce zero output.) In the long run, firms can enter or exit the industry, and can avoid their fixed costs by shutting down. (a) (8 points) Compute the short-run inverse supply curve of the firm, and the short-run inverse supply curve of the industry, and graph them on the same graph. [Hint: it matters a lot that firms can’t avoid their fixed costs in the short…

    • 3240 Words
    • 13 Pages
    Good Essays
  • Satisfactory Essays

    The IT projects are unique and complex, the majority of IT projects fail to meet at least one measure of success. The author of the article “IT Project management: Infamous failures, classic mistakes and best practices “consider some of the common causes of failures and best practices to avoid them. For a project to be successful every project manager must consider the triple constraint scope, cost, time and balance these three competing goals. A number of key factors contribute towards project failures. In this article it cited Steve McConell grouping the factors in four categories as people, process, product and technology. The article ranked top mistakes as poor estimation, ineffective stakeholder management, insufficient risk management, insufficient planning, poor quality, team issues and insufficient project sponsorship. The interesting finding is the mistakes are due to people or process-related, as opposed to product or technology related. The other interesting finding is given the importance given to scope in IT projects but scope creep was not in the top reason for project failure. The article also identifies that one-half of projects fails due to estimation and scheduling, stakeholder management and risk management. In conclusion, the author integrates different areas of failure and analyzed the reasons for failure and has proposed a framework for success.…

    • 363 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Crashing is a technique for schedule compression. It makes a trade-offs between the schedule and cost for obtaining the greatest amount of schedule compression for the least incremental cost. Crashing can be done by bringing in additional resources or working overtime or by paying extra to get the critical path activities delivered more quickly. Consider an example of applying security patches to all systems in the datacenter. Assume the duration was initially set as one month and there is only one resource working on it part time. If there is a decision to expedite the task due to security threats, there is a requirement of schedule compression. The options here will be either assigning the resource to full time or adding more resources to complete the task, or getting the tasks done quickly by engaging resources overtime. These options are part of crashing and help in reducing the activity duration. The project manager may use more resources to complete activities on Critical path. Project manager has to take in to account the slack available in non-critical activities. That helps in making sure the crashing is not impacting other activities in the Critical path of the project. The project manager also has to ensure the cost involved in crashing a project does not exceed the penalty costs. Crashing has to be done from the least expensive to the most expensive tasks. Crashing has to be done only for activities that are critical.…

    • 675 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Project Crashing Using Cpm

    • 1143 Words
    • 5 Pages

    We can however reallocate resources from one facet of the project and use it to speed up an activity that is lagging behind OR we can all together allocate new resources to our ACTIVITIES IN CRITICAL PATH. However care must be taken that, if the resources should always be withdrawn from activities that have more SLACK . In Short for project crashing we have to concentrate our efforts on THE CRIRICAL PATH i.e whatever efforts we have to do in term of time , resources or budget will be done on the critical path and these things have to be taken out either from the non-critical activities having enough SLACK or new allocation should be made.…

    • 1143 Words
    • 5 Pages
    Powerful Essays
  • Powerful Essays

    BM103

    • 537 Words
    • 3 Pages

    Exercise 11 1) Solve the ff. Modified Distribution (MODI) Warehouse A1:V1+W1= 3, W1= 3 B1:V1+W2= 5, W2= 5 B2:V2+W2= 8, V2= 3 C2:V2+W3= 4, W3= 1 C3: V3+W3= 4, V3= 3 VC C1: 3 – 0 – 1 = 2 A2: 4 – 3 – 3 = -2 A3: 3 – 3 – 3 = -3 B3: 8 – 3 – 5 = 0 A3: Table 2: OC B1: V1+W2= 5, W2 = 5 B2: V2+W2= 8, V2 = 3 C2: V2+W3= 4, W3 = 1 A3: V3+W1= 3, W1 = 0 C3: V3+W3= 4, V3 = 3…

    • 537 Words
    • 3 Pages
    Powerful Essays
  • Satisfactory Essays

    Scope Management Plan

    • 305 Words
    • 2 Pages

    Budget Information: The Company has allocated $650,000 for this project. Most costs will be from 60 hours of internal labor.…

    • 305 Words
    • 2 Pages
    Satisfactory Essays