Preview

Project Management Case Study: MICC

Good Essays
Open Document
Open Document
726 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Project Management Case Study: MICC
1. What problems did MICC face in the refurbishing project? What could the possible causes be?
Mid-India Construction Company (MICC) granted a refurbishing project at Director of National Institute of Management (NIM). The project should finish 8 months after contract award (Contract award: 17/11/12 Planned date for end of project: 27/06/13) before new academic term starts (01/07/13). MICC kicked off the project with one week delay on 24/11/12. One month after project commencement slow progress stresses both MICC and NIM project managers and casts the on-time project delivery on a shadow of doubt. MICC project manager realized the project resources are inadequate and unproductive. Meanwhile, NIM project manager insists that MICC should start different activity in parallel to compensate the delay of last month and mitigate the risk of overall project delay. MICC project manager has promised to NIM to increase resources and start parallel activities. Contractual penalty for major milestone delays has been explained in Exhibit 4.

There is no reward or incentive model in the contract that motivates MICC to finish the project earlier. Accordingly, MICC will not gain of fast delivery unless they want to unlock resources from this project and allocate them in other (i.e. new) projects. Therefore, MICC project manager should plan resources carefully in order to deliver project just on time. Both too early and too late delivery cause extra cost for MICC.
To sum up, there is no detailed plan, resources are insufficient and unproductive and one month has passed with a little progress. The add-hoc planning caused improper resource planning, lack of on-going control over resource productivity and project progress.
2. What could the consequences of ad-hoc project planning be to various stakeholders?
MICC:
Project delivery delay will cause contractual penalty (Exhibit 4) and longer project on-going cost (overhead) for MICC. Accordingly, MICC will gain less profit or even loss.

You May Also Find These Documents Helpful

  • Powerful Essays

    PROJ 592

    • 2367 Words
    • 10 Pages

    An Earned Value analysis reflected that the project is currently behind schedule. The schedule variance (SV) indicated a negative $565,226.34 and the scheduled performance index showed as .69. When SV is a negative number and SPI less than one, this indicates the project is behind schedule. After calculating the CPI/SPI value (1/.69= 1.45), any values above 1.3 should be investigated immediately, because those numbers are much too good to be true. In addition based on the Work Breakdown Structure the total duration was 6 days behind schedule. The new completion date in the WBS also indicates that the schedule completion date currently is 10days behind schedule.…

    • 2367 Words
    • 10 Pages
    Powerful Essays
  • Best Essays

    Grant, K. P. et al. (2006, November-December). Delivering projects on time: Risk management can help managers anticipate the delays that make their development projects late. Research-Technology Management.…

    • 3043 Words
    • 13 Pages
    Best Essays
  • Good Essays

    Is3110 Unit 4

    • 406 Words
    • 2 Pages

    If the project is completed on time then there is no risk for completion. All of the regular risks that apply to a project built on time apply to this one regardless of whether you are building a new infrastructure or modifying an older one. If the project is finished one month early, the quantitative risk really does not exist. It is basically comparable to completing the project on time. Since the project is quoted at 3 million dollars it will stay the same regardless of how fast the project is finished. However, you may see differences. When you rush a project this large you could possibly cut corners or receive poor quality results. If the project is finished two months late there are additional risks. If the company expects to make $20 million dollars annually, and assuming that the 4% penalty is levied against this yearly figure and not within smaller period of time, one month late means that US Industries Incorporated loses $800,000 annually. There doesn't appear to be any additional risk, however, further penalties and the possible eventual loss of the contract to a competitor could result in a poor product. There again appears to be no real quantitative risk involved if the project is finished a month early with the security requirements. If the originally quoted $3 million dollars remains the same regardless of how fast the project is finished and not coupled with hourly or daily wages, then there is nothing to lose financially. However the companies go beyond the required 1.5% completion benchmarks that the contract demands. Rushing a project of this scale also comes with rushed results possibly cut corners or poor quality. The credibility of the company is at stake with such a high profile, high income project such as this, and it is important to use all of the time available to ensure the best product is on display for any customer. The finished project should meet both the time and security requirements but not the service agreement. There does not…

    • 406 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    Proj586 - Week 2 Quiz

    • 932 Words
    • 4 Pages

    b) If the project schedule is relaxed or lengthened, what is the impact on quality? (15 points)…

    • 932 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    Risk Management Plan Devry

    • 1424 Words
    • 6 Pages

    7. Unproductivity. This is a huge problem when project deadlines must be met. This project requires multiple steps to get it done…

    • 1424 Words
    • 6 Pages
    Good Essays
  • Good Essays

    Jim Brown

    • 770 Words
    • 4 Pages

    The reasons that we propose this are because that this is the method that will save the company the most time. Not only does it save the company time, but if the company were to ever fall into trouble with labor union strikes, this plan is guaranteed to be the most cost effective when facing with the steep penalties of not meeting the time limit. In addition if everything goes very smoothly the company will finish the project 8 weeks earlier than expected and save money on overhead expenses.…

    • 770 Words
    • 4 Pages
    Good Essays
  • Good Essays

    My partners and I have made a list of areas that might cause the project delays or failure with their respective outcomes. We have listed the risk below that can prevent the project to finish on time.…

    • 1078 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Investiong in Tufs

    • 524 Words
    • 3 Pages

    Another thing that went wrong in the project is the imbalance between its scope and the scheduling of the project as result of the management pressure to produce fast result regardless of what feasible. This problem would have avoided if the scheduling of the project take into account what was possible more than what was desired given the scheduling of the project.…

    • 524 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Pm Tests

    • 443 Words
    • 2 Pages

    b) If the project schedule is relaxed or lengthened, what is the impact on quality? (15 points) (Points : 30)According to the triple constraints: "Scope, Time, Cost". All three of these impact the quality depending on which trade off is affecteda) The longer a project takes to complete, the more it will impact the quality of the project as a whole. b) Being relaxed or expanding the time frame for completion will impact scope and cost. Why? More money and less time to complete the work package deliverables.…

    • 443 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    Project Management

    • 6379 Words
    • 26 Pages

    In order to stay competitive with other home improvement chain stores, Acme Home Improvement decided that it would be a wise investment to open their first international store in Mexico. Opening new retail facilities is not a new process for Acme. Since the company began in 1982, Acme Home Improvement has built 125 stores throughout the United States. The new location in Mexico is to follow Acme’s typical 100,000 square foot size, with a 10,000 square foot outdoor garden sales area, as well as a two story parking garage are what is outlined to be constructed. Work on this project is scheduled to begin January 3, 2011, with a budget of $18 million.…

    • 6379 Words
    • 26 Pages
    Powerful Essays
  • Good Essays

    Risk Assessment

    • 768 Words
    • 3 Pages

    The project implementation deadline occurs in 9 months. Each month after the deadline is missed, a penalty of $100,000 is assessed. Three months after the deadline, the contract will be cancelled.…

    • 768 Words
    • 3 Pages
    Good Essays
  • Good Essays

    1) What are some of the principal reasons why project management has become such a popular business tool in recent years?…

    • 687 Words
    • 3 Pages
    Good Essays
  • Good Essays

    The lack of planning out a project causes a variety of emotions from confusion and frustration with all members involved, the planning process starts at the introduction of the strategic plans for the whole organization. There are three levels of the planning process and these three steps create and implement the strategies for the accomplishment, these steps are strategic, this process occurs at the highest level of the organization and has a time frame of over five years. The tactical stage time frame is one to five years and concentrates on the production planning and integrates organizational resources at a lower level for the entire enterprise and the intermediate duration, and the operational part looks at the daily operation of local resources and happen in the current or short term (Whitman & Mattord, 2014).…

    • 705 Words
    • 3 Pages
    Good Essays
  • Better Essays

    In the world of project management, utilizing the three-point technique can prove to be an invaluable tool. In addition to the three-point technique applying the earliest-start (ES), earliest-finish (EF), latest-start (LS), and latest-finish (LF) procedure to identify the critical path, the project completion time, and the slack for each task can prove to be set of invaluable data that will assist the project manager in accurately determining task duration estimates for the entire scope of work for the project. In this week’s assignment we will explore a construction company and the associated time estimates for each task as it relates to their entire project.…

    • 1185 Words
    • 5 Pages
    Better Essays
  • Better Essays

    1. No proper project structure - this made the execution and management of the project very ineffective.…

    • 1618 Words
    • 7 Pages
    Better Essays

Related Topics