Preview

Project Management Project Eight

Satisfactory Essays
Open Document
Open Document
397 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Project Management Project Eight
Project Eight

Determine the materials and labor to build a storage building, this will involve designing the building, figuring out what materials are needed, purchasing the materials, and putting together the various parts. Some of these tasks depend on the others, some must be scheduled, some take more labor than others, etc. The building design must include options such as: a choice among different types of siding, doors, windows, and roofing. Also, include the choice of a poured 4” deep concrete floor or a wooden floor. The total budget for the construction of the storage building is $2100 including sales taxes and $400 for labor.

Project management tasks
Before ordering any materials you will need to figure out:
• What tasks need to be done?
• In what order the tasks can be done?
• How long each task will take?
• How long the whole project will take?

Project scope statement
In order to make any decisions about the project, it needs to be made concrete. This is done by writing a scope statement, such as:
• We will build a garden shed capable of holding at least 2 bicycles, a lawn mower, and a small workbench
• Planning permission will not be needed
• We will not connect it to electric or water mains
• It cannot cost more than $2100 or take longer than 1 month (this may be a constraint rather than scope)
Note that the scope statement includes not only what it will do, but what will not be included.

Work breakdown structure
A WBS is a diagram showing the major subtasks of the project:
Constructing, Building the Shed, Planning and Obtaining Materials, Pouring the foundation, Building the frame, Installing the Siding, Installing the roof, and Finishing the project (door, window, etc.) As a rule of thumb break things down as far as necessary to estimate and schedule them, and no further.

Critical path
Develop a critical path chart taking care to show longest path through the network diagram – it is the minimum duration of the project (so that tasks can occur

You May Also Find These Documents Helpful

  • Powerful Essays

    Nt1330 Unit 6 Paper

    • 579 Words
    • 3 Pages

    Project Network Diagram which includes tasks, task estimates, task dependencies, resource names, and completion %.…

    • 579 Words
    • 3 Pages
    Powerful Essays
  • Good Essays

    -2- 6. The critical path of a project network is the: a. shortest time path through the network. b. path with the fewest activities. c. path with the most activities. d. longest time path throught the network.…

    • 882 Words
    • 8 Pages
    Good Essays
  • Better Essays

    A building will need to be chosen that would accommodate the size restaurant we envision in our business plan. We will need grills, ovens, microwaves, commercial dishwashers, cooler, freezer, and an assembly buffet for the kitchen. For the dining room, table, chairs, menus, silverware, plates, glasses are a few items that will need to be purchased (M.S. Segars, personal communication, July 6, 2015).…

    • 1090 Words
    • 4 Pages
    Better Essays
  • Satisfactory Essays

    The project is pouring a concrete patio in my backyard. The results will be a new patio to entertain guests. I am allowing two additional weeks in case there is inadequate funding or scheduling conflicts for the project ending in May of 2008. The two extra weeks are there in case there is an unexpected expense elsewhere, or I can’t get my brother to my house to help out because of scheduling conflicts. Each activity is defined within a week’s time.…

    • 784 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Proj586

    • 1206 Words
    • 5 Pages

    I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) 30 days b) Identify the critical path (6 points) BCDFH = 30 Days c) What is the slack time (float) for activity A? (1 points)…

    • 1206 Words
    • 5 Pages
    Satisfactory Essays
  • Good Essays

    Defines all the work required to complete a project successfully, and should ensure that the…

    • 1016 Words
    • 5 Pages
    Good Essays
  • Better Essays

    a. Unforeseen obstacles. The probability of unforeseen obstacles causing a negative impact to this project is rated at a moderate risk. Due to inability to determine the severity of the impact ATT impact could range from no impact to a show stopping impact. Each occurrence will be evaluated and solved at the lowest possible level. Each occurrence has the possibility to negatively impact the overall success of this project.…

    • 2438 Words
    • 10 Pages
    Better Essays
  • Satisfactory Essays

    Scope: Scope of the project is identified up front and once completed can meet the end deliverable for the project; however, scope can also change during the project life cycle. If the scope is not defined properly or understood up front the chances of failing the project can be high.…

    • 251 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) b) Identify the critical path (6 points) c)…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    I a. Construct a network for the project. [pic] Slack or Float = LF – EF or LST – EST Activities on the critical path have zero slack/float. b. Calculate the scheduled completion time and identify the critical path.…

    • 562 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Project Charter

    • 505 Words
    • 3 Pages

    This project will convert 1508 square feet of unfinished space in the basement of the Smith Residence, located in Maryland into a livable space. This space will be occupied on a full-time basis by the additional member of the household…

    • 505 Words
    • 3 Pages
    Good Essays
  • Good Essays

    What is a critical path, and why is it important to project managers? How do you…

    • 702 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    things which may be obvious to you and those who work around you. You also…

    • 2080 Words
    • 11 Pages
    Powerful Essays
  • Good Essays

    The project scope statement is the formal definition of the project and what needs to be accomplished. This process addresses and documents the characteristics and boundaries of the project and its associated products and services, as well as the…

    • 1086 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    A 15’x15’ off the living room with with two flower pots, LED lights, and four deck chairs on the far side of the deck. This project will be completed either personal sweat equity or the use of a qualified contractor.…

    • 293 Words
    • 2 Pages
    Satisfactory Essays