Once you have constructed the networks, you will log into the “Homework Exam" in Week 4 and input the answers to the homework questions.
Problem 1
The following data were obtained from a project to create a new portable electronic.
Activity Duration Predecessors
A 3 Days ---
B 4 Days ---
C 6 Days ---
D 2 Days A, B
E 1 Days C
F 3 Days D
G 3 Days E, F
H 7 Days D
I 10 Days G
Construct a network for the project. Then review and answer the multi-part question found on the Homework tab in Week 4.
Question
(A.) What is the Scheduled Completion of the Project? [2 points]
(B.) What is the Critical Path of the Project? [3 points]
(C.) What is the EST for Activity D? [2 points]
(D.) What is the LST for Activity G? [2 points]
(E.) What is the EF for Activity B? [2 points]
(F.) What is the LF for Activity H? [2 points]
(G.) What is the float for Activity I? [2 points] (Points: 15)
Answer:
A. 22 days
B. B, D, F, G, I
C. EST = 4
D. LST = 9
E. EF = 4
F. LF = 22
G. Float = 0
Problem 2
The following data were obtained from a project to build a pressure vessel:
Activity Duration Predecessors
A 4 weeks ---
B 4 weeks ---
C 3 weeks B
D 2 weeks A, C
E 3 weeks B
F 5 weeks D, E, G
G 2 weeks B
H 6 weeks F
I 3 weeks G
J 1 week I
Construct a network for the project. Then review and answer the multi-part question found on the Homework tab in Week 4.
Question:
(A.) Calculate the scheduled completion time and identify the critical path. [7 points]
(B.) What is the slack time (float) for activities A, D, E, and G? [8 points] (Points: 15)
Answer:
A. 20 weeks / critical path is B, C, E, D, F, H
B. Float time for A 7-4 = 3
Float time for D