PSP Exam Questions
Page |1

PSP Paper - 1
P.1 Which of the following is generally the MOST correct use of a project network diagram?
A. Showing the project schedule
B. Documenting task interdependencies
C. Defining project resources
D. Defining the project costs
P.2 At a minimum, periodic forecasts must be done at what interval?
A. monthly
B. as requested by the owner
C. as requested by the project manager
D. as specified in the contract documents
P.3 The calculated duration for a project is 28.166. The standard deviation is 5.5. What technique would you use to compute the probability of completing a project on a specific day?
A. PERT formula
B. Monte Carlo simulation
C. Probability analysis
D. Variance analysis
P.4 The best reason to use multiple calendars is to ___________
A sequence the float for the benefit of the contractor
B more accurately show how the project will be built
C give specialty contractors the information they need
D track owner activities according to their specific calendar in order to develop a good working relationship P.5 During planning you discover that the time needed to complete the project is longer than the time available. What do you do?
A. Tell the customer that the required date cannot be met
B. Tell management that the required date cannot be met
C. Spend time determining what work can be done for the length of time available and accomplish only that work
D. Determine options for crashing and/or fast tracking the project and present management with your recommended option
P.6 Free float is the ____________
A difference between the early dates and late dates of an activity
B amount of time an activity can be delayed without impacting the early start of the successor activity. C difference in float value of the critical path activities and the float value of the specific activity
PSP S1

AACEI-UAE

Page |2

being analyzed
D difference between the early finish dates and late finish dates of an activity
P.7

You May Also Find These Documents Helpful

  • Powerful Essays

    Nt1330 Unit 6 Paper

    • 579 Words
    • 3 Pages

    Create a project schedule using Microsoft Project. Project schedule will built from and contain the following information:…

    • 579 Words
    • 3 Pages
    Powerful Essays
  • Satisfactory Essays

    Nt1310 Unit 4

    • 555 Words
    • 3 Pages

    b. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?…

    • 555 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Managerial Statement: The expected duration of the project is 31 working days. Critical Activities are I, J, K, L, and M.…

    • 678 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Aib Problem Solution

    • 608 Words
    • 3 Pages

    30 b) Identify the critical path (4 points) B,C,D,F,H c) What is the slack time (float) for activity A? (2 points) 5 d) What is the slack time (float) for activity D?…

    • 608 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Question: To what extent was the Constitution a radical departure from the Articles of Confederation?…

    • 531 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    AIB Simulation

    • 771 Words
    • 4 Pages

    Before starting this homework assignment, please review the AIB simulation in this week’s Lecture. This simulation will provide you with an understanding of how to create a network diagram, and how to do a forward and backward pass to determine the ES, LS, EF, LF and slack (float). You will also learn how to determine the duration of the project, and the critical path.…

    • 771 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    In “War Making and State Making as Organized Crime” Charles Tilly argues that there is an analogy to be drawn between state, or war making and organized crime. He argues that the powers in control of both state and war making are “self-seeking entrepreneurs”. Tilly believes that the people who hold the control of both war and state creation are just as guilty of creating violence for their own personal advantages and gains as those “self- seeking entrepreneurs” he compares them to. Tilly argues that this comparison is true by pointing out the ways in which power holders organize violence to better fit their agendas. These ways being; extraction of resources, the give and take of protection, and both war/state making.…

    • 274 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    B. Inform the colleague that there is a problem and let them know when the job will be done…

    • 507 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    ARIBA Team 2

    • 263 Words
    • 3 Pages

    ARIBA IMPLEMENTATION IN MED-X Case Team 2: Yusuf Akkoca Tom Bloom Karen Delton Shweta Hire Eric Johnson David Mahzonni Greg Roy Which of the two components are underperforming according to the plan? How do you know this? • Technical Infrastructure is both behind schedule and over budget as indicated by the SPI (94.4%), Control Ratio (< .9) and CPI (91.7%)…

    • 263 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Scripted Services

    • 534 Words
    • 3 Pages

    a. Study each element of work to determine the “one best way” to do it.…

    • 534 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Gantt Chart

    • 2465 Words
    • 10 Pages

    This section consists of a suite of potential options broken out by sample phases. While it may be useful for grantees to consider these deliverables in designing their project, the particular suite of deliverables and the organizational structure that is ultimately incorporated will be project-specific. The grantee may also ask the Vendor to provide cost estimates on a per-deliverable basis in the bid response.…

    • 2465 Words
    • 10 Pages
    Powerful Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    The estimated project completion date is TUE 11/13/13 with duration of 127 days. After leveling and re-allocating work along the project line, the project got delayed for 3 days so that the completion day moved up to FRI 11/21/13 (total duration of 130 days). (MS Project 2007)…

    • 613 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Subway Project Plan Overview

    • 10327 Words
    • 42 Pages

    This project entails opening two Subway Restaurant franchises. The project is described and potential problems identified. The mission, scope, and measuring the progress of the project are also discussed. The first step is applying to Subway for a franchise. Once the application has been accepted, the real work begins. Using Microsoft Project, each phase of the project can be monitored to ensure successful completion.…

    • 10327 Words
    • 42 Pages
    Powerful Essays
  • Good Essays

    The network diagram display logical relationships among the various activities that take place within a project. It also allows the project manager to see how the various activities flow towards to…

    • 576 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Project Management

    • 836 Words
    • 4 Pages

    Projects often can exceed their planned schedule by a certain percentage, sometimes even 50 to 100 percent. Often this is attributed to uncertainty or the unforeseen. Managers and project personnel have learned to compensate to this dilemma by adding additional time to their schedule estimates (Larson and Gray, p.302). Yet even when they do, projects still overrun their schedules. Goldratt (1997) argues that there is a natural tendency for people to add safety time, just in case, to their estimations. One of the key problems identified in this case was the project time estimate. Even when management added 10 percent time to all activities or added 10 percent project estimates to ensure project durations would be met, the issues still remained (Larson and Gray, p.302). Then, Pinyarat explained that the activity durations had gotten squeezed down to less than the 50 percent guideline and that the estimates were impossible. Pinyarat also mentioned that she was allowed to put in a big enough project buffer and other members of the firm had no idea why management would use CCPM scheduling in these projects (Larson and Gray, p.303).…

    • 836 Words
    • 4 Pages
    Good Essays

Related Topics