Preview

Rental Power Status in Bd

Good Essays
Open Document
Open Document
1100 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Rental Power Status in Bd
Rental power is typically costlier than conventional power because production of it involves short term deals. A rental power company must have power generation equipment ready in its stock. But none of the dozen plus local companies awarded with rental power contracts have any stock of plant equipment or experience in rental power projects.

The PDB signed the contracts with the two sponsors on February 4 this year asking them to install and commission their respective plants within 120 days (4 months). Both have failed.

The had PDB moved for setting up the costly eight rental power plants with a total capacity of 530 MW, setting March 30 as deadline to begin their operation.

The target was set keeping in view the irrigation of last boro crop. But it was missed. PDB could finally sign deals for only 4 projects with a total capacity of 300 MW in February.

The PDB had flawless success with two rental power contracts with British company Aggreko that had launched their 200MW units ahead of their deadline. Aggreko 's units in Khulna and Ashuganj completed full power generation capacity test yesterday.

OTOBI-

With the setting up of two power plants with the production capacity of 100 MW each in Bheramara at Kushtia and Noapara at Jessore in an area of 5 acres, the company invested worth Tk 8.0 billion (Tk 800 crore) there, Managing Director of Otobi, Animesh Kundu, told the FE in an interview.

(http://www.thefinancialexpress-bd.com/more.php?news_id=150203&date=2011-09-21)

After paying the government Tk 11.55 crore penalty for failing to launch its 110 megawatt rental power plant in Bheramara in time, furniture giant Otobi obtained a court injunction against paying further penalties.
Otobi has also sought Power Development Board 's permission to convert the same diesel fired plant into a heavy fuel oil (HFO) fired plant and sought a new deadline of October 30 in that light. It has done so as a contractor is allowed 120 days to complete a

You May Also Find These Documents Helpful

  • Better Essays

    A factor that Caledonia must take into consideration when determining if to lease versus buying is the security that comes along with owning an asset versus leasing one. With Caledonia owning the equipment, the company could feel more secure than with the leasing of an asset. The lessor can take the asset at any time, when ending the contract. Another factor that Caledonia must take into consideration is the maintenance that comes with owning vs. leasing. Some maintenance issues Caledonia faces with owning an asset is the requirement to take care of its maintenance issues, whereas with leased assets the owner is responsible.…

    • 1027 Words
    • 5 Pages
    Better Essays
  • Satisfactory Essays

    Assignment1

    • 584 Words
    • 3 Pages

    Under the guidance and mentoring of Milind Kumar the team achieved success well under the time frame for the project. Milind Kumar made sure SA Water has been able to achieve an optimum management of project risks by adopting the (Design Build Operate Maintain (DBOM) delivery model. This contracting methodology was cost effective, with SA Water only paying the fixed lump sum costs of the plant and SA Water retains ownership of the critical water security asset. The DBOM contract model also has early…

    • 584 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Huntsville Plant

    • 654 Words
    • 3 Pages

    There are over allocated resources in the Huntsville Plant Project. The over allocation are in the months of May to July of the following year. The 40 weeks that are the…

    • 654 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Week 4 Ltb

    • 1043 Words
    • 5 Pages

    The intial outlay is 8,000,000 (7,900,000 for new plant and equipment and 100,000 for shipping).…

    • 1043 Words
    • 5 Pages
    Satisfactory Essays
  • Good Essays

    2. If city site permitting the process that require more than 3 days per submission for just a standard configurations. This would cause the project expand the launch date.…

    • 1078 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    operation management

    • 252 Words
    • 1 Page

    According to the Specialty Contractors case, we get the critical path is PTV and the project duration is 12 weeks but it will be delayed 4 weeks in the beginning.…

    • 252 Words
    • 1 Page
    Satisfactory Essays
  • Good Essays

    Risk Assessment

    • 768 Words
    • 3 Pages

    The project implementation deadline occurs in 9 months. Each month after the deadline is missed, a penalty of $100,000 is assessed. Three months after the deadline, the contract will be cancelled.…

    • 768 Words
    • 3 Pages
    Good Essays
  • Better Essays

    A potential investment consideration for Generation is ABB India; a market leader in power and automation, offering solutions for efficiency in power generation, electrical transmission and increased productivity. These values tie in consistently with Generation’s mission and vision. Furthermore, the company have a strong financial position with a healthy angle to capitalise on future growth trends, have a disciplined management and a strong track record.…

    • 1017 Words
    • 5 Pages
    Better Essays
  • Good Essays

    Blue Zuma Part 2

    • 310 Words
    • 2 Pages

    Once the changes are in place, the duration of the project has been reduced from 290 days to 274 days. This improvement has reduced the overall length of the project, thus allowing the deadline set by the Mr. Lane (President). We are confident we can now complete the project by January 27.…

    • 310 Words
    • 2 Pages
    Good Essays
  • Good Essays

    Zuma Project

    • 1253 Words
    • 6 Pages

    Since the project duration is 250 days from 1/2/08. It would meet the promised 2/1/2009 deadline.…

    • 1253 Words
    • 6 Pages
    Good Essays
  • Satisfactory Essays

    Summary: You have to know how to select the best emergency electrical services TX. It is important for you to find the ultimate one for you.…

    • 479 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Physics Project Case

    • 850 Words
    • 4 Pages

    The project is about building a coal-fired power plant which accomplish on 16 April, 2008 which 10 weeks is ahead of schedule. At the first of beginning they face rigorous tribulation, for example costs skyrocketed, skilled labor shortage and the location in middle of nowhere would make the project completion on time in jeopardy. Million of dollars in capital investment start to be spent, any delay would have considerable financial impact.…

    • 850 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    information to the secretariat within five days of receipt of the request. If the proponent…

    • 1384 Words
    • 7 Pages
    Powerful Essays
  • Satisfactory Essays

    Narrative Report Ojt

    • 258 Words
    • 2 Pages

    The five (5) units of generator at Agus 6 HE Plant Complex that generate 200 MW. The units 1 and 2 generates 25 MW while the unit 3,4 and 5 generates 50 MW. The generator 1, 2, 3 and 4 delivers 69 KV. In the unit 5 delivers 138 KV.…

    • 258 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    spinning mills report

    • 463 Words
    • 2 Pages

    Sufficient information needs to be collected about the existing procedure for procurement of raw material from members/other sources and existing procedure for marketing and selling of cotton yarn. Also identify the market for surplus production.…

    • 463 Words
    • 2 Pages
    Satisfactory Essays