1. The town of Eden Bay has many workers that are all determined to succeed, but without having a strategic plan set in place, as well as a clear mission statement the employee’s are becoming frustrated. Some of the workers have mentioned that they work off a budget from year to year without any sight of a long-term plan set in place. This will surely add to their frustration and prevent the town from setting and reaching its desired long-term goals.
2. The Maintenance Department’s SWOT Analysis
Possible Strengths:
Dedicated Staff Possible Weaknesses:
Using Legacy Systems
Poor Records/Data Handling
Possible Opportunities:
Improving on Current System
Future Company Growth Possible Threats:
More Efficient/Organized Competitor
3. Specific Steps to Follow During Preliminary Investigation:
a. Analyze Systems Request
b. Make Recommendations
c. Interview with Management and Staff
d. Identify Constraints
e. Report to Upper Management with Findings
4. Out of the four tests of feasibility I would perform an operational feasibility analysis to determine whether the project is worthwhile and profitable to the company.
Countrywide Construction
1. The correct duration would be 65 Days.
2. Critical Path:
Prep Foundation (10d)→ Assemble Building (4d)→ Final Inspection (30d)→ →Arrange for Sale (3d)
4. PERT/CPM Chart:
Chapter 4 Review Questions
3. JAD and RAD are teams both composed of users, managers, and IT staff. They differ from traditional fact-finding methods because the users, managers, and IT staff all work together to gather information and define new system requirements, whereas traditional methods are composed of all IT staff. These teams get a wider range of input due to the diverse nature of the team members. However, this can be costly or not as efficient if too many people are involved.
4. Total Cost of Ownership is the sum of the direct and indirect costs of installing a system. This is important to