Agreggated Planning
Solutions

Chapter 14: Aggregate Planning

2. Bob Carlton’s Golf Camp a. The peak demand is 6,400 hours in quarter 2. As each employee can work 600 hours per quarter (480 on regular time and 120 on overtime), the level workforce that covers requirements and minimizes undertime is 6,400/600 = 10.67 or 11 employees.

| | |Cost |Calculation |Amount |
| | |Regular wages |($7200 per quarter)(11)(8 quarters) |$633,600 |
| | |Overtime wages* |(1,120 hr in quarter 2)($20 per hr) |22,400 |
| | | |(960 hr in quarter 6)($20 per hr) |19,200 |
| | |Hire costs |($10,000 per hire)(3 hires) |30,000 |
| | | |TOTAL |$705,200 |

* The 11 workers can produce (11)(480) = 5,280 hours of regular time in any quarter. The 6,400-hour requirement in quarter 2 exceeds this amount by 1,120 hours. The 6,240-hour requirement in quarter 6 exceeds this amount by 960 hours.

The total undertime hours can be calculated as:

| | |Quarter 1 |11(480) – 4,200 |1,080 | hours |
| | |Quarter 3 |11(480) – 3,000 |2,280 | |
| | |Quarter 4 |11(480) – 4,800 |480 | |
| | |Quarter 5 |11(480) – 4,400 |880 | |
| | |Quarter 7 |11(480) – 3,600 |1,680 | |
| | |Quarter 8 |11(480) – 4,800 |480 | |
| | | |

You May Also Find These Documents Helpful

  • Good Essays

    15 seasonal workers. Seasonal workers could work only between the dates of August 15 and…

    • 3588 Words
    • 15 Pages
    Good Essays
  • Satisfactory Essays

    ABurnett Chpt12

    • 344 Words
    • 1 Page

    18. Overtime will be worked for a period of two weeks to bring the project back on schedule by the end of next week.…

    • 344 Words
    • 1 Page
    Satisfactory Essays
  • Satisfactory Essays

    ¼ hours (20,000 x 60)/80,000 = 15 minutes 3. How many units were produced in the second quarter? 120,000 units Problem 7-54: Plantwide versus Departmental Rates, Product-Costing Accuracy: Activity-Based Costing, page 330-331 See Attached File…

    • 98 Words
    • 1 Page
    Satisfactory Essays
  • Better Essays

    Budgeting is important especially for the small or medium size organisation which could not afford to waste any money on any investments that are not worth the price. Furthermore, a structured budget must be able to provide information of where the cash will be spent on and how the organisation gathered the sufficient amount of capital for future investment. It is important to keep track on the organisation’s cash flow as it provides important information on how much money available within the organisation. Insufficient cash flow within the organisation may lead to financial distress or worst, bankruptcy. However, too much cash flow within the company is not good either as the money should be used to invest into profitable projects rather than keeping within the company. Budgeting helps the organisation to prepare sufficient amount of cash flow within the company to help dealing with day-to-day expenses, at the same time, fully utilised the excess capital in profitable…

    • 1142 Words
    • 5 Pages
    Better Essays
  • Good Essays

    Pm3110 Unit 4

    • 854 Words
    • 4 Pages

    Based on the demand mix, the time needed for the administrative support person is 15%*(20+50)+5%*(40+80)+50%*(20+30)+30%*(40+60)=71.50 minutes per case; the time needed for the senior accountant is 15%*(30+20)+5%*(40+60)+50%*(0+5)+30%*(0+30)=24 minutes per case; the time needed for the junior accountant is…

    • 854 Words
    • 4 Pages
    Good Essays
  • Good Essays

    a) A firm has three categories of employees: juniors, seniors and supervisors. They earn $12, $18 and $24 per hour respectively. They have an output of 10, 16 and 22 units of product per hour respectively. The 250 employees of the plant have a total…

    • 1317 Words
    • 6 Pages
    Good Essays
  • Satisfactory Essays

    Bus 630 Case Study

    • 392 Words
    • 2 Pages

    2) A department works one 8-hour shift, 250 days per year. It has demand for the following products. How many pieces of equipment are needed to meet the demand?…

    • 392 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Production schedules were changed within the company due to experienced growth. All production employees were required to work four…

    • 938 Words
    • 4 Pages
    Good Essays
  • Good Essays

    The above table showing the total capacity per hour of each machine center was calculated by taking the number of machines and multiplying them by the run time per piece per minute. This enables you to see the amount produced each minute from each machine center. I then multiplied that by the obvious 60 minutes per hour to determine the output from each machine center each hour. We know from the text that Al Beck is running two eight hour shifts so the machines are running for a minimum of 16 hours per day. Knowing this, I then take my output per hour and divide it by 16-hour days to find the actual production rate.…

    • 783 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    d) The case description of how many workers are needed when the plant runs over time is vague. Assume that there are 20 workers and that they are evenly split between full time and seasonal employees.…

    • 426 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Planning

    • 5587 Words
    • 23 Pages

    Look at the mark allocation to help you decide what to write. Remember ‘Explain’ for 2 marks means give a reason then use so to elaborate it.…

    • 5587 Words
    • 23 Pages
    Powerful Essays
  • Satisfactory Essays

    Wescott case study

    • 475 Words
    • 11 Pages

    According to the results, Model A has an overtime work of 2.75 hours if the standard working hours 8 hours. Same goes to Model B & C, both model worked for 2.77 if the standard working hours 8 hours. However, the production in Model D & E are overrun to 2.5 and 3 days which is insufficient.…

    • 475 Words
    • 11 Pages
    Satisfactory Essays
  • Satisfactory Essays

    • Resource planning – Current mix of staffing level leads to excess overtime payment. We propose to run two shifts during the peak time with mix of non seasonal and seasonal workers to cater seasonal demand and save manpower cost…

    • 1177 Words
    • 5 Pages
    Satisfactory Essays
  • Better Essays

    Your job is to allocate workers to tasks each week during the project. Planners ‘R Us has agreed to complete the project in 10 weeks (finishing two weeks before the Festival), and wants to minimize the costs associated with the project. All tasks A-K must be completed in 10 weeks. You have four (4) workers, although you do not need to use all of them every week – there are other tasks they can do in your company.…

    • 1009 Words
    • 5 Pages
    Better Essays
  • Good Essays

    Planning

    • 414 Words
    • 2 Pages

    2yourself a lot of time, and possibly avoid having your care plan returned to you…

    • 414 Words
    • 2 Pages
    Good Essays

Related Topics