Preview

Cantilever Sheetpile

Powerful Essays
Open Document
Open Document
1622 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Cantilever Sheetpile
CANTILEVER SHEET PILE WALL
By Lakshmi Radhakrishnan
Email id: lakshmiradhakrish@gmail.com
ABSTRACT:
A sheet pile wall consists of a series of sheet piles driven side by side into the ground, thus forming a continuous vertical wall for the purpose of retaining an earth bank. They are commonly used for: (1) water front structures, (2) temporary constructions, (3) light weight construction where sub soil is poor for supporting a retaining wall. A sheet pile may be of three types:
Cantilever sheet piling
Anchored sheet piling
Braced sheeting
Cellular cofferdams
The design of sheet pile retaining walls requires several successive operations: (a) Evaluation of the forces and lateral pressures that act on the wall, (b) determination of the required depth of piling penetration, (c) computation of the maximum bending moments in the piling, (d) computation of the stresses in the wall and selection of the appropriate piling section and (e) the design of the walling and anchorage system. Before these operations can be initiated, however, certain preliminary information must be obtained. In particular, the controlling dimensions must be set. These include the elevation of the top of the wall, the elevation of the ground surface in front of the wall (commonly called the dredge line), the maximum water level, the mean tide level or normal pool elevation and the low water level. A topographical survey of the area is also helpful. Earth pressure theories have developed to the point where it is possible to obtain reliable estimates of the forces on sheet pile walls exerted by homogeneous layers of soil with known physical constants. The uncertainties involved in the design of sheet pile structures no longer result from an inadequate knowledge of the fundamentals involved. They are caused by the fact that the structure of natural soil deposits is usually quite complex, whereas the theories of bulkhead design inevitably presuppose homogeneous

You May Also Find These Documents Helpful

  • Good Essays

    Unit 18 P4

    • 782 Words
    • 4 Pages

    Walls – these could be classed as load bearing or a none load bearing infill panels. When a wall is load bearing they are deemed structural elements as they carry a structural force down to the foundations. When building a load bearing wall they must be made to withstand great structural force this can be done with denser materials. None load bearing walls are none load bearing as the name suggests so they do not have no structural importance. They are usually walls like stud walls for…

    • 782 Words
    • 4 Pages
    Good Essays
  • Good Essays

    - Walled: a narrow upright structure, usually built of stone, wood, plaster, or brick, that acts as a boundary or keeps something in or out…

    • 1235 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Strategic Management

    • 1245 Words
    • 5 Pages

    References: to block size are based upon a standard block which is up to 700m2 with up to 1m fall across the block. "M" class soil classification, all services within boundaries, garage setback up to 5.5m from front boundary, even cut and fill.…

    • 1245 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Facs 240 Study Guide

    • 1015 Words
    • 5 Pages

    ~Sheetrock- A plasterboard made of gypsum layered between sheets of heavy paper. 10x4 or 8x4 depending on the space…

    • 1015 Words
    • 5 Pages
    Good Essays
  • Better Essays

    Soil is a non-homogenous blend of many materials. There are many factors that need to be considered when digging trenches in soil. To analyze the stability of unsupported trenches, the method selected will depend on the critical nature of the project, economics, and the amount of time available for design. For shallow utility line excavations, where time and economics are at a premium, a rapid technique for evaluating the critical depth and the maximum safe slope is required. The maximum safe slope is identified as the "angle of repose." The use of stability charts or tables coupled with a few simple equations is the most efficient approach.…

    • 1021 Words
    • 5 Pages
    Better Essays
  • Powerful Essays

    adjacent structures. As an alternative, I-walls and T-walls were built. Though the T-walls, shaped like…

    • 2785 Words
    • 12 Pages
    Powerful Essays
  • Powerful Essays

    Regarding to our meeting dated July 30, 1993; WestBan Construction Limited needs City’s approval for extra time and cost to precede with additional scope of the construction work (changing slope in North and East banks, adding required shoring for stabilizing the soil, leaving shoring in the ground, pouring tank concrete walls instead of shotcrete), according to the option B for both North and East Slopes (Attachment F2), the chosen schemes for slope remedies are attached in this document.…

    • 1987 Words
    • 12 Pages
    Powerful Essays
  • Good Essays

    This leaves a (1 meter wide) freestanding wall of earth known as balk, on each side of a unit. These vertical slices of earth allow archaeologists to compare the exact provenance of a found object or feature to adjacent layers of earth (strata). During Kenyon 's excavations at Jericho, this technique helped separate the long and complicated occupational history of the site. It was believed that this approach allowed more accurate observations than the earlier "horizontal exposure" technique which relied on architectural and ceramic…

    • 984 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    Figure 4 View of the 3D physical model testing of the entrance configuration conducted in the wave basin at UNSW…

    • 2444 Words
    • 10 Pages
    Powerful Essays
  • Good Essays

    Skellig By David Almond

    • 432 Words
    • 2 Pages

    “I sat on a pile of bricks against the house wall.” (7) The fact that there are a pile of bricks shows that there was either project that was not finished, or the structure was so old and deformed that it had fallen…

    • 432 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    5.2 Safety Meeting

    • 1621 Words
    • 7 Pages

    All piers and excavations are required to have a 6 foot perimeter around the hole/excavation to prevent objects from falling inside the hole.…

    • 1621 Words
    • 7 Pages
    Powerful Essays
  • Powerful Essays

    Curled Metal

    • 1589 Words
    • 7 Pages

    2) For those benefits that you can quantify, calculate the differentiation value of a pile pad. You should get a different number for Kendrick and Corey Construction.…

    • 1589 Words
    • 7 Pages
    Powerful Essays
  • Satisfactory Essays

    Sheet Piles

    • 690 Words
    • 3 Pages

    In order to maintain a straight line of vertical piles, it is necessary to provide one or two pairs of horizontal timbers, called waling,…

    • 690 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    * In case of Stone Crushing Plant operating with CTE /CCA of the Board existing since long, which are located at a distance less then 200 meter from highways, the unit shall provide minimum 6 meter high compound wall or barrier of GI sheets along their plot periphery towards highway/road side. 2)…

    • 797 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    The HZMB Hong Kong Boundary Crossing Facility (HKBCF) will be located on an artificial island of approximately 150 hectares to be reclaimed in a sustainable manner. The methodology for both the construction of the seawall and the main reclamation area will ensure that the marine soft compressible material remains intact during the process of land formation; i.e. a fully non-dredge reclamation - the first ever method adopted in Hong Kong. No dumping of marine sediments is thus required. With this design sandfill consumption, suspended particles and marine traffic during construction can be significantly reduced. The seawall will be made up of individual circular steel cellular units and physically connected with arc units to form the peripheral retaining structure for the main reclamation. To achieve stability, ground improvement technique using stone column shall be installed to render the subsoil’s enhancement in strength parameters.…

    • 4502 Words
    • 19 Pages
    Powerful Essays

Related Topics