Preview

EVM Assessment and Application on Finishing a Basement Project

Better Essays
Open Document
Open Document
2510 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
EVM Assessment and Application on Finishing a Basement Project
EVM Assessment and Application on Finishing a Basement Project

Table of Contents

Introduction

Earned Value Management (EVM) is a project management tool for measuring project performance and progress in an objective manner. The Office of the Assistant Secretary of DoD explains that EVM is “Earned Value Management is an essential Program Manager and Technical Lead tool for supporting proactive decision making” (Kranz, 2014, pg. 1). PMBOK describes EVM as “a management methodology for integrating scope, schedule, and resources, and for objectively measuring project performance and progress. Performance is measured by determining the budgeted cost of work performed (i.e., earned value) and comparing it to the actual cost of work performed” (PMBOK, 2008, pg. 433).
There are 3 elements for EVM: Planned Value (PV), Actual Cost (AC), and Earned Value (EV). PV is the total costs of the work schedule. AC is the total cost that was taken to complete the work. EV is the value performed by a status, measured in costs. Earned Value is the value earned for the past working being completed. For an example after 30 days of working on a $1000 dollar budget and the schedule showed that 40% of the work has been completed then $400 of the total budget should be spent. Anything less then the total budget would show that the project is under running and anything over $400 shows that the project is overrunning. This is important for the project lead so he is able to determine at any point past or present the financial health of the project. If the project becomes too large and he begins seeing a large over budget project then he needs to either go back to the customer and request more money or time to get the project back on budget.
Background

This paper will analyze how EVM will be used for completing the basement project. In this example the project lead is Daniel



References: Allex, Daniel S (2014). Interview. Kranz, Gordon M (2014). Earned Value Management (EVM) Divison. Office of Assistant Secretary of DOD. http://www.acq.osd.mil/evm/ . Project Management Institute (2008). A Guide to the project management body of knowledge (PMBOK Guide). (4th ed.). Newtown Square, PA: PMI.

You May Also Find These Documents Helpful

  • Good Essays

    The enterprise value (EV) measures the total value of the company. It can be defined as the sum of the present value of the projected free cash flows (FCF) during the forecast period and the present value of the terminal value after the forecast period. The mathematical formula is as follows:…

    • 1590 Words
    • 7 Pages
    Good Essays
  • Better Essays

    It Management Mgt2 Task 3

    • 4060 Words
    • 13 Pages

    Cited: A guide to the project management body of knowledge (PMBOK guide 5th edition).Newtown Square, Pa.: Project Management Institute, Inc., (2013)…

    • 4060 Words
    • 13 Pages
    Better Essays
  • Satisfactory Essays

    Ilab Week7

    • 297 Words
    • 2 Pages

    EV: this is a value indicating how much of a budgeted cost should have been spent given the amount of work actually completed = $7,120.19…

    • 297 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    Golden Bear Case

    • 1298 Words
    • 6 Pages

    Valuation was another relevant assertion to Paragon’s construction projects because it ensures that transactions are recorded at the appropriate amounts. Paragon took advantage of the percentage-of-completion revenue recognition method that construction companies typically use to value revenue earned throughout a project. Paragon switched from its “cost-to-cost” method to what they referred to as the “earned value” method. This latter method enabled the company to rely on subjective estimates of costs incurred rather than objective criteria. Thus, enabling the company to materially misstate its…

    • 1298 Words
    • 6 Pages
    Better Essays
  • Powerful Essays

    Ah531

    • 3543 Words
    • 15 Pages

    Valle, J., & Soares, C. (2005). The use of earned value analysis(eva) in the cost management of construction projects. Federal university fluminense, brazil, Retrieved from http://www.google.com/url?sa=t&rct=j&q=&esrc=s&frm=1&source=web&cd=4&ved=0CEQQFjAD&url=http://www.icoste.org/ICMJ%20Papers/Valle%20-%20EVA.pdf&ei=PkW7UeT0BobY8gS18YCADg&usg=AFQjCNFSA-RUj35ZNIwD-ii15E76nCs9-Q&sig2=Sktqkw1XxvD8CRFJnvkbVg…

    • 3543 Words
    • 15 Pages
    Powerful Essays
  • Powerful Essays

    BBA 360

    • 1876 Words
    • 9 Pages

    -measure of cost efficiency/ lets you know where you stand at any point of project…

    • 1876 Words
    • 9 Pages
    Powerful Essays
  • Satisfactory Essays

    Charter Wedding bells

    • 1190 Words
    • 8 Pages

    A guide to the project management body of knowledge, PMBOK guide, 5th Edition, PMI Inc. 2013.…

    • 1190 Words
    • 8 Pages
    Satisfactory Essays
  • Good Essays

    Pman 638

    • 856 Words
    • 4 Pages

    Project Management Institute (2008). A Guide to the Project Management Body of Knowledge (PMBOK guide) (4th ed.). Newtown Square, PA: Project Management Institute.…

    • 856 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    Project management has grown beyond the confines of simplistic canned applications into a discipline that is in large part process, combined with common sense and inspiration. The process of Project and Portfolio Management (PPM) derives from the practices common to project management, as expressed in applications and tools developed to help project managers collaborate with project team’s cross-enterprise.…

    • 1454 Words
    • 6 Pages
    Powerful Essays
  • Satisfactory Essays

    Earned Value Management System (EVMS) guiding principles incorporate top business practices to give strong benefits for program or enterprise planning and control. The process includes the incorporation of program scope, schedule, and cost objectives, establishment of a baseline plan for success during the execution of a program. The structure provides a solid foundation for problem recognition, corrective actions, and management replanning if required. This system helps program management integrate the work scope of a program with the schedule and cost elements for most favorable program planning and control. There are three basic elements of earned value management which are: Planned Value (PV) Actual cost (AC) and earned value (EV) each of these elements are used on a standard basis as of a reporting date. Planned value (PV) is the total cost of the work schedule calculated as PV or BCWS=Hourly Rate* Total Hours Planned or Scheduled. Actual cost (AC) is the cost taken to complete the work as of a reporting date calculated as AC or ACWP=Hourly Rate* Total Hours Spent. Earned value (EV) is the total cost of the work completed/performed as of a reporting date calculated as EV or BCWP=Baseline Cost* % Complete Actual. Some of the principles involved with earned valued management system (EVMS) are as follows:…

    • 559 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    During the evaluation process an assessment is made on cost, efficiency, programs outcome, programs impact, program implementation, design, and program logic. A reflection of the project scope takes place during the evaluation process where a comparison between what was needed and what was provided is examined. An impact evaluation measures whether the project has achieved its intended outcomes. Cost effectiveness analysis assesses the efficiency of a project. During the evaluation, an outline of the benefits and cost of the program will be reviewed for comparison. Throughout the life cycle of the project, the project team will collect lessons learned. While the project is in cycle, the team members will record both good and bad lessons learned. In essence, the team will record new events that occurred within the life cycle of the project. This type of evaluation will both strengthen individual team members and the project team. The evaluation process will include both internal and external evaluations. The internal evaluation will be done by the project manager. The project manager will have a better overall knowledge of the program and also possess informal knowledge of the program. The project manager is already familiar with the project staff allowing the evaluation process to be less threatening. Finally having the project manager perform the team evaluation is cost effective. The…

    • 3705 Words
    • 15 Pages
    Powerful Essays
  • Powerful Essays

    Project Management Institute(2008) A Guide to the Project Management Body of Knowledge:(PMBOK® Guide), 4th edition, PMI,…

    • 2275 Words
    • 10 Pages
    Powerful Essays
  • Powerful Essays

    POST PROJECT EVALUATION

    • 8415 Words
    • 38 Pages

    There is a general belief that post-project reviews are beneficial. However, such reviews are not conducted in a consistent manner, if at…

    • 8415 Words
    • 38 Pages
    Powerful Essays
  • Satisfactory Essays

    Project Portfolio Management (PPM) is a management tool whose process is designed to aid an organization in identifying and organizing all of its projects. The PPM organizes an organization’s projects by prioritizing each project according to its strategic value, resource impact, cost, etc. The PPM is a derivative of a financial portfolio and shares similar objectives. Some of these similar objectives consist of developing a consciousness of all the individual parts involved; presenting a better understanding of all its parts; and allowing the parts of the organizations to be sorted as well as prioritized based on their alignment with the organization’s long-term strategies or goals.…

    • 536 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Hextable Dance Case Study

    • 871 Words
    • 4 Pages

    The introducing of Value Management (VM) team recommended re-evaluating the project to focus on function. The project team effectively need to recheck all the function, to achieve maximum benefits by conducting the early stages of a VM study. Each stage normally involves a period of preparation, one or more workshops and a report, which identifies actions to develop and implement. In this case, the project team combined the first two stages to fast-track towards a solution.…

    • 871 Words
    • 4 Pages
    Satisfactory Essays