Rank Project 1 2 3 4 5 6 7 8 9 10 11 7 8 9 4 10 2 3 5 1
Rank Project 1 2 3 4 5 6 7 8 9 10 11 7 9 8 4 2 10 3 5 1
Rank Project 1 2 3 4 5 6 7 8 9 10 11 7 9 8 4 10 2 3 5 1
The equivalent annuity method would be the most suited for this exercise due to the fact that the projects being compared have different life spans. The effluent project
could be evaluated considering its cost today vs. the cost in four years when its mandated. 3. This ranking is solely based on monetary factors and it’s not taking into consideration any nonfinancial factors. In addition, this ranking is not assessing any of the risk factors for each of the projects. A weighted scoring model should help assist in the project selection ensuring that projects that most closely align to the organizations goals and objectives are properly taken into consideration during decision making. 4. The “Effluent